PC R 16-2243RESOLUTION NO. 2016-2243
A RESOLUTION OF THE PLANNING COMMISSION OF THE
CITY OF ARROYO GRANDE APPROVING CONDITIONAL USE
PERMIT NO. 15-002, APPLIED FOR BY VERIZON WIRELESS,
LOCATED ON HUEBNER LANE
WHEREAS, the Planning Commission of the City of Arroyo Grande considered
Conditional Use Permit Case No. 15-002 on January 19, 2016, filed by Verizon Wireless,
to install telecommunication antennas and related equipment on an existing City water
tank (Reservoir No. 4) and within an existing equipment cabinet located on the west side
of the water tank; and
WHEREAS, the Planning Commission has held a public hearing on this application in
accordance with the Arroyo Grande Municipal Code; and
WHEREAS, the Planning Commission has found that this project is consistent with the
General Plan and the environmental documents associated therewith; and
WHEREAS, the Planning Commission has reviewed this project in compliance with the
California Environmental Quality Act (CEQA), the State CEQA Guidelines, and the Arroyo
Grande Rules and Procedures for Implementation of CEQA and has determined that the
project is exempt pursuant to CEQA Guidelines Section 15311 regarding construction or
placement of minor structures accessory to existing facilities; and
WHEREAS, the Planning Commission finds after due study, deliberation and public
hearing, the following circumstances exist:
Conditional Use Permit Findings:
1. The proposed use is conditionally permitted within the subject district pursuant to
the provisions of Section 16.16.050 of the Development Code, and complies with all
applicable provisions of the Development Code, the goals and objectives of the
Arroyo Grande General Plan, and the development policies and standards of the
City. In addition, the facility will operate in full compliance with all state and federal
regulations including the Telecommunications Act of 1996.
2. The proposed use will not impair the integrity and character of the district in which it
is to be established or located. The installation of the facility will not result in any
material changes to the character of the immediate neighborhood or local
community.
3. The site is suitable for the type and intensity of use or development that is
proposed. The facility is not located within a predominantly residential
neighborhood.
4. There are adequate provisions for water, sanitation, and public utilities and services
to ensure the public health and safety.
RESOLUTION NO. 2016-2243
PAGE 2
5. The proposed use will not be detrimental to the public health, safety, or welfare, or
materially injurious to properties and improvements in the vicinity. The
telecommunication facility will be unstaffed, have no impact on circulation systems,
and will generate no noise, odor, smoke or any other adverse impacts to adjacent
land uses.
NOW, THEREFORE, BE IT RESOLVED that the Planning Commission of the City of
Arroyo Grande hereby approves Conditional Use Permit Case No. 15-002, with the above
findings and subject to the conditions set forth in Exhibit "A", attached hereto and
incorporated herein by this reference.
On motion by Commissioner Martin, seconded by Commissioner Mack, and by the
following roll call vote, to wit:
AYES: Martin, Mack, Fowler -Payne, Keen
NOES: None
ABSENT: George
the foregoing Resolution was adopted this 19th day of January 2016.
ATTEST:
DEBBIE WEICHINGE
SECRETARY TO THE COMMISSION
AS TO CONTENT:
RESA MCCLISH
OMMUNITY DEVELOPMENT DIRECTOR
LAOILOR
CHAI
RESOLUTION NO. 2016-2243
PAGE 3
EXHIBIT "A"
CONDITIONS OF APPROVAL
CONDITIONAL USE PERMIT CASE NO. 15-002
VERIZON WIRELESS
HUEBNER LANE
COMMUNITY DEVELOPMENT DEPARTMENT
PLANNING DIVISION
GENERAL CONDITIONS
This approval authorizes the installation of an unmanned wireless communication facility at the City's
Reservoir No. 4 site with equipment placed on the north, west and south sides of the water tank.
1. The applicant shall ascertain and comply with all Federal, State, County and City
requirements as are applicable to this project.
2. The applicant shall comply with all conditions of approval for Conditional use Permit Case
No. 15-002.
3. This application shall automatically expire on January 19, 2018, unless a building permit is
issued. Thirty (30) days prior to the expiration of the approval, the applicant may apply for an
extension of one (1) year from the original date of expiration.
4. Development shall occur in substantial conformance with the plans presented to the
Planning Commission at the meeting of January 19, 2016 and marked Exhibit B.
5. The applicant shall agree to defend at his/her sole expense any action brought against the
City, its present or former agents, officers, or employees because of the issuance of said
approval, or in anyway relating to the implementation thereof, or in the alternative, to
relinquish such approval. The applicant shall reimburse the City, its agents, officers, or
employees, for any court costs and attorney's fee's which the City, its agents, officers or
employees may be required by a court to pay as a result of such action. The City may, at its
sole discretion, participate at its own expense in the defense of any such action but such
participation shall not relieve applicant of his/her obligations under this condition.
6. Construction shall be limited to between the hours of 7 a.m. and 5 p.m. Monday through
Friday. No construction shall occur on Saturday or Sunday.
SPECIAL CONDITIONS
7. The facility shall not bear any signs or advertising devices other than certification, warning, or
other FCC required seals or signage.
8. To allow for adequate ventilation, the City -owned equipment shelter shall include a new
expandable metal wall between the City's equipment area and Verizon's leased equipment
area. The new wall must be secured (attached) on all sides of the equipment shelter. Wall
specifications shall be submitted and approved by the Director of Public Works prior to
issuance of a building permit.
9. All equipment placed on the water tank shall be painted to match the color of the tank.
RESOLUTION NO. 2016-2243
PAGE 4
10. The facilities shall have subdued colors and non -reflective materials, which blend with the
materials and colors of the surrounding area.
11. The facilities shall not bear any signs or advertising devices other than certification, warning,
or other required seals or signage.
12. All accessory equipment associated with the operation of the wireless facility shall be located
within a building, enclosure, or underground vault that complies with the development
standards of the PF zoning district.
13. Per the March 25, 2015 Radio Frequency Electromagnetic Fields Exposure Report prepared
for this facility by Hammett & Edison Inc., explanatory signs shall be installed at the access
ladder on the tank and at the antennas.
ENGINEERING DIVISION
GENERAL IMPROVEMENT REQUIREMENTS
14. Site Maintenance - The developer shall be responsible during construction for cleaning
city streets, curbs, gutters, and sidewalks of dirt tracked from the project site. The flushing
of dirt or debris to storm drain or sanitary sewer facilities shall not be permitted. The
cleaning shall be done after each day's work or as directed by the Public Works Director.
SPECIAL CONDITIONS
15. The applicant shall obtain an encroachment permit prior to any work done in the public right -
of way.
16. Zero Conflict with City's Communication: Prior to issuance of building permit, the
applicant shall perform a radio frequency study to determine possible conflicts with the
City's communication system, and to develop alternatives to eliminate any such conflicts.
Prior to activation of the proposed Verizon Wireless system, the applicant shall
perform a live radio test to ensure that there is no unanticipated interference with the
City's radio system. If the proposed system does interfere with the operation of the City's
communication system, the proposed system shall remain inactive until such time that the
proposed system can be made to cause zero interference.
BUILDING DIVISION
17. The project shall comply with the most recent editions of all California Building and Fire
Codes, as adopted by the City of Arroyo Grande.
18. Any review costs generated by outside consultants shall be paid by the applicant.
19. Building Permit fees shall be based on codes and rates in effect at the time of building
permit issuance.
20. Building permit shall be obtained prior to installation.