HomeMy WebLinkAboutSpiess Construction Co Inc RECORDING REQUESTED BY Doc No: 1997-027211 Rec No: 00035431
AND WHEN RECORDED RETURN TO:
Official Records NF 0.00
CITY CLERK San Luis Obispo Co.
CITY OF ARROYO GRANDE Julie L. Rodewa l d
Recorder
P.O. BOX 550 May 29, 1997
ARROYO GRANDE, CA 93421 T i m e : 14:00
[ 2] TOTAL 0.00
NOTICE OF SUBSTANTIAL COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is owner or agent of owner of the interest or estate stated below in the property hereinafter described.
2. The FULL NAME of the OWNER is: The City of Arroyo Grande
3. The FULL ADDRESS of the OWNER is: 214 East Branch Street. Arroyo Grande. California 93421
4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee
5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the
undersigned as JOINT TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR'S in interest of the undersigned if the property
was transferred subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7. All work of improvement on the property hereinafter described was SUBSTANTIALLY COMPLETED
May 14 1997
8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
Spiess Construction Co. Inc.. P.O. Box 2849 Santa Maria. CA 93457
9. The street address of said property is: None
10. The property on which said work of improvement was substantially completed (see attached list of items required for
completion) is in the City of Arroyo Grande, County of San Luis Obispo, State of California, and is described as follows:
REPLACEMENT OF PAVEMENT. WATER & SEWER IMPROVEMENTS IN BRIDGE NELSON.& SHORT STREETS
PROJECT City Project No. 60- 70- 90 -96 -5
Verification of NON - INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of
California that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice;
that I have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct.
John L. ,t .11ace Director of Public 4 44,____
M evi 1- 1 o 9 9 /
1 � c yr Y (✓�1 ✓a , I l ov-o
Page 1 0
This is a list of the items that are required to be complete by the Contract in order for the project to be deemed complete:
1. Correction of asphalt paving too high above the gutter (3 locations).
2. Correction of weakened asphalt paving on Nelson Street.
3. Correction of asphalt berms constructed with 3/4" mix.
4. Provide copies of the sewer video and log.
Page 2
May 20, 1997, Arroyo Grande, California
END OF DOCUMENT drt:232.4802\noticbns.wpd