Halcyon Complete Streets Project
30% Design
Review and Discussion
2/25/25
1
Background and Future Schedule
State ATP grant funding 2022.
Conceptual Plan approved July 25, 2023 .
Design contract with North Coast Engineering approved June 25, 2024.
Secure right-of-way by August 2025
CTC allocation December 2025
Advertise construction January 2026
Begin construction March 2026
2/25/25
2
Project Construction Finances
2/25/25
Estimates
Funding Sources
3
Pavement Treatment
2/25/25
Slurry seal - $1,430,000
Overlay - $3,670,000
4
Vehicle Lane Width
2/25/25
Existing
Alternate
5
Road Diet
2/25/25
Existing
Alternate
6
On-street Parking
2/25/25
7
Halcyon/Fair Oaks Intersection
Signal - $881,000
Roundabout - $1,470,000
2/25/25
8
Roundabout
2/25/25
Signal
Halcyon/Grand Intersection
9
Bicycle Box
2/25/25
10
Bicycle Lanes
2/25/25
Class II
Unbuffered
Class IV
Class III
“Sharrows”
Class II
Buffered
11
Green Paint
2/25/25
Green paint in conflict locations (intersections) let vehicles know that bicycles may be present where bicycle lanes are not able to be marked
12
Trees
2/25/25
2
6
16
17
13
Trees - continued
2/25/25
28
26
21
19
14
Recommendation
Review and provide input regarding design considerations associated with the Halcyon Complete Streets Project.
2/25/25
15