HomeMy WebLinkAboutCC 2025-05-27_09f Acceptance of Cornwall Ave Watermain Replacement
Item 9.f.
MEMORANDUM
TO: City Council
FROM: Bill Robeson, Assistant City Manager/Public Works Director
BY: Theresa Wren, Capital Improvement Projects Manager
SUBJECT: Notice of Acceptance, Cornwall Avenue Watermain Replacement
Project, PW 2024-02
DATE: May 27, 2025
RECOMMENDATION:
1) Accept the Cornwall Avenue Watermain Replacement Project;
2) Direct staff to file a Notice of Completion; and
3) Authorize release of retention thirty-five days after the Notice of Completion has been
recorded, if no liens have been filed.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
The total construction cost from the final construction contract and change orde r was
$622,654.90, including $610,680.90 in contract costs and $11,974 in contingency costs
for changes in materials quantities and field change orders. This project was completed
on time and under budget.
The FY 2024-25 budget included $750,000 for the Cornwall Waterline Replacement
Project, consisting of the following funds: $578,700 from the American Rescue Plan Act
(ARPA), and $171,300 from the Water Fund. The construction contract amount was
$611,654.59, and allowable contingency was $61,165.46, for a total of $672,820.05,
which was within the available budget.
The total construction cost from the final construction contract and change order was
$618,636.59, which was $611,654.59 from the contract and $ 6,982.00 for changes in
materials quantities and field change orders. This project was completed on time and
under budget.
The FY 2024-25 budget included $750,000 for the Cornwall Waterline Replacement
Project, consisting of the following funds: $578,700 from the American Rescue Plan Act
Page 135 of 236
Item 9.f.
City Council
Notice of Acceptance, Cornwall Avenue Watermain Replacement Project, PW 2024 -
02
May 27, 2025
Page 2
(ARPA), and $171,300 from the Water Fund. The construction contract amount was
$611,654.59 and contingency estimate was $61,165.46, which was within the available
budget.
BACKGROUND:
The City’s Water System Master Plan (“Plan”) was adopted on January 22, 2013. In the
Plan, it was recommended that several sections of cast iron water mains be replaced due
to their condition and age, including a section of 8-inch cast iron pipe in Cornwall Avenue
from west of El Camino Real to North Rena Street. This section of water main was
installed in 1929 and has a useful life of 50-100 years.
On November 26, 20241, the City Council awarded a construction contract to The JF Will
Company, Inc. (“JF Will”), to complete the Cornwall Watermain Replacement Project in
the amount of $611,654.59, and authorized the City Manager to approve change orders
for 10% of the contract amount, $61,165.46, for unanticipated costs during the
construction phase of the project.
The project replaced 1,350 feet of water main, new service connections (meters to water
main), new fire hydrant laterals, and connections to piping on Alpine Street, Bell Street,
and Oak Street, as well as asphalt patching and restriping pavement affected by the
project.
ANALYSIS OF ISSUES:
This waterline installation was completed to Utilities Division staff satisfaction. The
waterline is in service and fully operational. There are a few minor punch list items noted
by Utilities Division staff that JF Will is working to complete including as-built plans, and
return of materials. These punch list items are scheduled to be completed by June 27,
2025. No complaints have been received by customers.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept the Cornwall Watermain Replacement Project;
2. Do not accept the project;
3. Accept the project but do not authorize release of retention; or
4. Provide other direction to staff.
ADVANTAGES:
The project is complete pending some minor punch list items and accepting the
improvements will allow staff to file the Notice of Completion and close out the project.
1 https://pub-arroyogrande.escribemeetings.com/Meeting.aspx?Id=8cf6f9db-0e05-48f6-93b1-
44a4035fe6c3&lang=English&Agenda=Agenda&Item=44&Tab=attachments
Page 136 of 236
Item 9.f.
City Council
Notice of Acceptance, Cornwall Avenue Watermain Replacement Project, PW 2024 -
02
May 27, 2025
Page 3
DISADVANTAGES:
No disadvantages have been identified in accepting this project. The project was deemed
substantially complete on May 6, 2025, and all items identified on the punch list are
scheduled for completion by the Council date of June 27, 2025.
ENVIRONMENTAL REVIEW:
At its November 26, 2024 meeting, City Council determined that construction of this
project was categorically exempt from the California Environmental Quality Act (CEQA)
pursuant to Guidelines Class 1 Section 15301 Existing Facilities, Class 2 Section 15302
Replacement or Reconstruction, and Class 4 Section 15304 Minor Alterati ons of Land.
No further environmental review is required.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
ATTACHMENTS:
1. Notice of Completion
Page 137 of 236
ATTACHMENT 1
RECORDING REQUESTED BY
AND WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE, CA 93420
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2. The FULL NAME of the OWNER is: The City of Arroyo Grande
3. The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420
4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee
5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as
JOINT TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was
transferred subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7. All work of improvement on the property hereinafter described was COMPLETED May 27, 2025
8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
The JF Will Company, Inc.
9. The street address of said property is: Cornwall Avenue between west of Oak Street and N. Rena St.
10. The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo,
State of California, and is described as follows: Cornwall Watermain Replacement PW 2024-02
Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California
that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the
said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct.
_________________________________________________
Bill Robeson, Assistant City Manager/Public Works Director
_________________________________________________
Date Signed, Arroyo Grande, California
-- END OF DOCUMENT --