HomeMy WebLinkAboutCC 2025-07-22_09h Acceptance of 2024 Street RepairsItem 9.h. MEMORANDUM TO: City Council FROM: Bill Robeson, Assistant City Manager/Public Works Director BY: Theresa Wren, Capital Improvement Projects Manager SUBJECT: Notice of Acceptance, 2024 Street Repairs Project, PW 2024 -01 DATE: July 22, 2025 RECOMMENDATION: 1) Accept the 2024 Street Repairs Project; 2) Direct staff to file a Notice of Completion; and 3) Authorize release of retention thirty-five days after the Notice of Completion has been recorded, if no liens have been filed. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: The final total construction contract cost and contingency for the 2024 Street Repairs Project was $4,399,888.90, including $221,000 in contract costs and $399,989.90 in contingency costs for changes in materials quantities and field change orders, including the overlay and traffic circle on Fair Oaks Avenue in front of Arroyo Grand e High School. The FY 2024-25 budget included $4,430,000 for the Project, consisting of the following funds: $390,000 of Regional SHA, $2,360,000 of the general fund, $450,000 of SB 1 Funds, $966,833 of Measure O-06 Local Sales Tax Fund, $204,207 of American Rescue Plan Act (ARPA), and $58,960 of CDBG. A carryover from FY 2023-24 of $65,083.90 was approved by the Council with the FY 2024 -25 First Quarter Financial Status Report. It was used to address a shortfall in construction, contingency, and special materials testing costs. With this final total, the project was completed on time and on budget. BACKGROUND: At its October 22, 2024,1 meeting, the City Council awarded a construction contract to Papich Construction Company, Inc. (Papich) to complete the 2024 Street Repair Project. Staff value engineered the information available in the 2 022 PMP to provide a recommended list of work to be done with available funds. This 2024 Street Repairs Project included treatment of 5.2 miles of streets in Stagecoach, Brighton , and Rancho 1 https://pub-arroyogrande.escribemeetings.com/Meeting.aspx?Id=83d01e22-c872-418b-a248- 1eabf256b8a5&lang=English&Agenda=Agenda&Item=40&Tab=attachments Page 161 of 440 Item 9.h. City Council Notice of Acceptance, 2024 Street Repairs Project, PW 2024-01 July 22, 2025 Page 2 Grande neighborhoods, as well as Station Way and overlay of Fair Oaks Avenue in front of Arroyo Grande High School before installing the temporary traffic circle. ANALYSIS OF ISSUES: The 2024 Street Repairs Project was completed to the satisfaction of Engineering staff and Public Works Manager. Papich worked with City staff and was cognizant of the timing considerations for the Traffic Way Bridge project that affected both the work on Station Way and Fair Oaks Avenue. There are a few minor punch list and administrative items that Papich is working to complete, including monument corner records, warranty documentation, and certified payroll paperwork. These items are scheduled to be completed before the final retention is released. ALTERNATIVES: The following alternatives are provided for the Council’s consideration: 1. Accept the 2024 Street Repairs Project; 2. Do not accept the project; 3. Accept the project but do not authorize release of retention; 4. Provide other direction to staff. ADVANTAGES: The project is complete pending some minor punch list items, and accepting the improvements will allow staff to file the Notice of Completion and close out the project. DISADVANTAGES: No disadvantages have been identified in accepting this project. ENVIRONMENTAL REVIEW: At its October 22, 20242 meeting, the City Council determined the project is categorically exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guideline Section 15301 covering the repair and maintenance of existing streets, sidewalks, gutters and similar facilities. PUBLIC NOTIFICATION AND COMMENTS: The Agenda was posted at City Hall and on the City’s website in accordance with Government Code Section 54954.2. ATTACHMENTS: 1. Notice of Completion 2 https://pub-arroyogrande.escribemeetings.com/Meeting.aspx?Id=83d01e22-c872-418b-a248- 1eabf256b8a5&lang=English&Agenda=Agenda&Item=40&Tab=attachments Page 162 of 440 ATTACHMENT 1 RECORDING REQUESTED BY AND WHEN RECORDED RETURN TO: CITY CLERK CITY OF ARROYO GRANDE 300 EAST BRANCH STREET ARROYO GRANDE, CA 93420 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN THAT: 1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below. 2. The FULL NAME of the OWNER is: The City of Arroyo Grande 3. The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420 4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee 5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as JOINT TENANTS or as TENANTS IN COMMON are: NAMES ADDRESSES None 6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was transferred subsequent to the commencement of the work of improvements herein referred to: NAMES ADDRESSES None 7. All work of improvement on the property hereinafter described was COMPLETED June 24, 2025 8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is: Papich Construction Company, Inc. 9. The street address of said property is: Various locations including Stagecoach, Brighton, Rancho Gramde, Station Way 10. The property on which said work of improvement was completed is in the City of Arroyo Grande, Co unty of San Luis Obispo, State of California, and is described as follows: 2024 Street Repairs Project PW 2024-01 Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct. _________________________________________________ Bill Robeson, Assistant City Manager/Public Works Director _________________________________________________ Date Signed, Arroyo Grande, California -- END OF DOCUMENT -- Page 163 of 440