MEMORANDUM
TO: City Council
FROM: Matthew Downing, City Manager
BY: Aleah Bergam, Management Analyst
SUBJECT: Update on City Council Goals and Priorities
DATE: January 27, 2026
RECOMMENDATION:
Receive an update regarding progress made toward meeting the City Council’s Goals
and Priorities for Fiscal Year 2025-27 (July 1, 2025 through December 31, 2025).
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
There are no financial impacts associated with the receipt of the update regarding
progress toward meeting the Goals and Priorities for FY 2025-27. Any fiscal impacts
associated with the implementation of Goals and Priorities will be analyzed at the time
actionable items are brought to the City Council for consideration.
BACKGROUND:
Every two years, staff and the City Council prepare a Biennial Budget document, which
commits government resources and services to accomplish the City’s mission of making
Arroyo Grande the best place possible for everyone who lives, works, and visits here. As
part of the budgeting process, the City utilizes a thoughtful process to establish the City’s
focus and priorities, culminating in the City Council determining goals for th e following
two-year period. These goals become the foundation upon which staff prepare the
Biennial Budget.
On March 11, 20251, the City Council considered and approved a list of Goals and
Priorities for FY 2025-27 to help direct the work of the City during the biennial budget
cycle. The identified Goals and Priorities are outlined below. This report provides an
update regarding the City’s progress throughout 2025, with an emphasis on completing
the identified Goals and Priorities for FY 2025-27 (July 1, 2025, through December 31,
2025). This also provides an opportunity for the public to learn of the City’s progress and
1 https://pub-arroyogrande.escribemeetings.com/filestream.ashx?DocumentId=14042
Page 166 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 2
share input with the City Council on any of the Goals and Priorities or for consideration of
any additional direction to staff.
Major City Goals
The City Council has set five goals for the City for Fiscal Years 2025-27.
Goal #1: Pursue New Revenue Sources
Strategies for the next two years:
Revenue Generation
Consider Cannabis as a Means of Economic Development
Transient Occupancy Tax Changes
Goal #2: Achieve Water Resilience
Strategies for the next two years:
Pursue 2026 State Water Ballot Measure
Seek new Water Sources
Work with Regional Partners to Preserve Current Water
Sources
Goal #3: Implement Road and Sidewalk Improvements
Strategies for the next two years:
Prioritize Key Infrastructure Projects
Pursue Alternative Funding Sources for Infrastructure
Needs
Goal #4: Complete the General Plan Update
Strategies for the next two years:
Economic Development Tasks
General Plan Elements
Environmental Impact Report
Code Update
Climate Action Plan
Page 167 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 3
ANALYSIS OF ISSUES:
While each of the goals is large and complex, staff is pleased to report that substantial
progress has been made in many areas. Below is additional information and details of
each goal accompanied by major accomplishments toward meeting those goals.
Additional information regarding the status of work toward meeting the Goals and
Priorities is included in Attachment 1.
Review of Major City Goals
Goal #1: Pursue New Revenue Sources
Strategy: Revenue Generation
The City Council held a Pre-Application hearing for the proposed hotel
development at 400 W. Branch Street and supported continued work with the
developer.
Staff continued working with the developer of the proposed hotel to identify
information necessary to achieve a complete development application .
Staff are currently working with regional partners on potential new events to drive
visitation during shoulder and winter months, as well as build destination
awareness.
Staff worked with the South County Chamber of Commerce to implement a Buy
Local Program to support businesses during the construction of the Traffic Way
Bridge Replacement Project, which led to over 930 submissions and $179,388.49
in direct sales to local merchants.
Strategy: Consider Cannabis as a Means of Economic Development
At the December 9, 2025 Council Meeting2, the City Council conducted a Study
Session on Cannabis Policy Regulation. At that meeting, City Council directed staff
to move forward with preparing items for Council consideration to place a
2https://pub-arroyogrande.escribemeetings.com/filestream.ashx?DocumentId=16587
Goal #5: Redevelop the East Grand Avenue Corridor (Halcyon
Road to Elm Street)
Strategies for the next two years:
Scope of Work and RFP
Kick Off and Public Outreach
CEQA
Plan Draft
Final Draft and Hearings
Page 168 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 4
cannabis-related tax measure on the November 3, 2026, ballot to generate
discretionary revenue for City services and infrastructure.
At the Study Session, Council provided direction to staff that a development
agreement approach would not be in lieu of a cannabis tax, but may be in addition
to a general cannabis tax.
Strategy: Transient Occupancy Tax Changes
At the August 26, 2025, Council Meeting3, the City Council adopted Ordinance No.
2025-008 amending Chapter 3.46 of the Arroyo Grande Municipal Code regarding the
authorized improvements and activities to be funded by assessments imposed
through the Arroyo Grande Tourism Business Improvement District.
At the January 13, 2026, Council Meeting4, the City Council conducted a Study
Session on a potential TOT ballot measure and potential opportunities related to the
AGTBID. Council directed staff not to move forward with an increase to the AGTBID
lodging partners at this time, and to consider a potential TOT Ballot Measure in a
future election cycle.
Goal #2: Achieve Water Resilience
Strategy: Pursue 2026 State Water Ballot Measure
Staff will be coming to Council in the coming months to get direction on putting a
State Water Ballot Measure on the November 2026 Ballot. This would allow the
City the ability to purchase state water any time not just during a declared water
shortage emergency.
Strategy: Seek new Water Sources
The City is currently conducting a water and wastewater Financial Plan update to
adjust rates based on changes to water supply, Lopez Litigation impacts, and
changing or new regional partnerships.
The City is looking at possible state water options that may be available with state
water contractors in San Luis Obispo County and Santa Barbara County.
Strategy: Work with Regional Partners
Significant time has been spent by City management working with the County of
San Luis Obispo on the Lopez litigation.
Staff worked with a consultant to develop a webpage to ensure the public has
access to the latest Lopez litigation news, at
www.arroyogrande.org/lopezlakelitigation5.
Staff continues to participate with NCMA partners on Management Agreement
Amendments.
3 https://pub-arroyogrande.escribemeetings.com/filestream.ashx?DocumentId=15706
4 https://pub-arroyogrande.escribemeetings.com/filestream.ashx?DocumentId=16799
5 https://www.arroyogrande.org/889/Lopez-Lake-Water-Release-Litigation
Page 169 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 5
Staff has started working with Golden State Water Co. on a possible interconnector
with the City.
The City is actively participating in the San Luis Obispo County Regional
Desalination Plant Study.
Goal #3: Implement Road and Sidewalk Improvements
Strategy: Prioritize Key Infrastructure Projects
The City Council adopted the Plan for Pavement Management for the maintenance
of all City streets over the next 13 years.
The 2025 Pavement Management Program is currently in design.
Staff developed an updated sidewalk management program to prioritize sidewalk
improvements throughout the city, which was adopted by the City Council.
The City Council adopted the 2025 ADA Transition Plan.
The Traffic Way Bridge Replacement Project has been substantially completed,
detours have been removed, and the bridge is open to the public. The project was
completed on time and on budget.
The City has entered into a contract for construction of concrete repair work,
including sidewalk repairs, which is in progress.
Construction documents for the Halcyon Road Complete Streets Project were
developed to the 60% review phase, and the City Council provided direction to
staff regarding trees and parking considerations to help finalize construction
documents in the near future.
Easements and right-of-way have been obtained from necessary properties to
implement the Halcyon Road Complete Streets Project.
Replacement of Traffic Safety Guardrails throughout the City has been completed.
The biennial Corrugated Metal Pipe (CMP) lining project has been completed.
The Cornwall Avenue Watermain Replacement Project was completed.
Strategy: Pursue Alternative Funding Sources for Infrastructure Fu nding
The City has entered into a contract with Townsend Public Affairs, Inc. for
legislative advocacy and grant writing. The firm has already submitted one grant
application, and staff anticipates more grant submissions in the coming months.
Goal #4: Complete the General Plan Update
Strategy: General Plan Elements
The Preliminary Public Draft of the General Plan was released on November 19,
2025. Two outreach events were held the week of December 1, 2025, including a
study session with the Planning Commission and a public workshop to obtain
community feedback.
The Planning Commission made recommendations for the City Council’s
consideration at an upcoming study session, scheduled for February 24, 2026.
Page 170 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 6
Strategy: Climate Action Plan
Two foundational documents for the Climate Action Plan are currently under review
by staff. The Greenhouse Gas (GHG) Emissions Inventory Report (Inventory
Report) was prepared to assess emissions within city limits and serves as the
foundation for forecasting and setting reduction targets in the updated CAP.
Other
The City Council adopted a preferred land use scenario for the General Plan
Update.
Goal #5: Redevelop the East Grand Avenue Corridor (Halcyon Road to Elm Street)
Strategy: Scope of Work and RFP
Staff worked as part of an interdepartmental team to develop and refine a scope
of work and anticipate release in the near future.
Other Administrative Accomplishments
In addition to making substantial progress on the City Council’s goals, staff has made
noteworthy progress in other administrative areas, including:
The City Council held a Goal Setting Workshop and identified the five goals
identified above for the FY 2025-27 Budget
Staff negotiated a new lease with a local Italian restaurant for continued use of City
property for their outdoor patio
Staff Completed the implementation of a new payroll system and human resources
management system
The City reinvigorated the staff Safety Committee, who is responsible for o ngoing
implementation of Risk Management Evaluation recommendations
Staff initiated a Classification and Compensation study
Staff implemented a robust communications strategy for the Traffic Way Bridge
Replacement Project
Staff implemented ADA tools and launched a refreshed City website with g reater
functionality
Staff managed upgrades to the City’s Emergency Operations Center to replace
outdated equipment and implement current technology
Staff installed water bottle filling stations utilizing a $10,000 grant from the
Integrated Waste Management Authority
The City Council adopted updates to the City’s Wireless Telecommunication
Facilities regulations in response to changes in technology
The City Council adopted the City’s first Active Transportation Plan
In response to City Council direction, staff created the Measure E-24 Citizen Sales
Tax Oversight Committee
The City Council adopted updates to the City’s Water Well regulations
Page 171 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 7
Staff coordinated with the County of San Luis Obispo for consistent animal
regulations
Staff presented the City’s first workforce vacancy, recruitment, and retention trends
compliance report in accordance with Assembly Bill 2561
Staff and the Council developed the Biennial Budget with an expanded, accessible
format and a Ten-Year Capital Improvement Program
The City Council adopted updated State Fire Hazard Severity Zone Maps in
accordance with state law
The City Council adopted Revision 4 of the Sewer System Management Plan
Staff secured an $80,000 grant from the California Office of Traffic Safety for traffic
safety programs
A new lease agreement for existing parking in the Village was negotiated and
approved
Staff completed the triennial update to the California Building Standard Code
The franchise agreement with Phillips 66 was updated and renewed
Staff executed an agreement with FlashVote to conduct statistically valid surveys
in the city and conducted three surveys in 2025
Staff began the migration of City records to SharePoint
The Parkside Park Play Structure Replacement Project has been completed.
The City Manager appointed a new Chief of Police following a national recruitment
process, which has also led to 4 department promotions.
The Police Department has implemented new technologies to manage records,
property & evidence, personnel files, investigations, and improve radio
communications.
In collaboration with City staff and the San Luis Obispo Fire Safe Council, the Five
Cities Fire Authority (FCFA) completed three Hazardous Fuel Reduction projects
within the city.
The FCFA additionally deployed personnel and provided incident support of the
Madre and Gifford Fires.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Receive an update regarding progress toward the Goals and Priorities for FY 2025-
27; or
2. Provide other direction to staff.
ADVANTAGES:
Receiving the status report on the Goals and Priorities for FY 2025-27 provides an update
to the City Council and the public on the City’s efforts toward completing and
accomplishing a number of vital work efforts.
DISADVANTAGES:
There are no disadvantages at this time.
Page 172 of 175
Item 11.b.
City Council
Update on City Council Goals and Priorities
January 27, 2026
Page 8
ENVIRONMENTAL REVIEW:
Receiving an update on FY 2025-27 Council Goals and Priorities is not a project subject
to the California Environmental Quality Act (“CEQA”) because it has no potential to result
in either a direct, or reasonably foreseeable indirect, physical change in the environment.
(State CEQA Guidelines, §§ 15060, subd. (b)(2)-(3), 15378.) Alternatively, receiving an
update on FY 2025-27 Council Goals and Priorities is exempt from CEQA on the basis
that it can be seen with certainty that there is no possibility that the activity in question
may have a significant effect on the environment. (State CEQA Guidelines, § 15061,
subd. (b)(3).)
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
ATTACHMENTS:
1. Goals and Priorities for FY 2025-27 Status Update
Page 173 of 175
Goal Strategy Task/Action Carryover Action
or New
Responsible
Department
Anticipated to
Start Completion Target Update
1.1 Revenue Generation 1.1a 400 W. Branch Disposition and Development Agreement Carryover CMO/CA/CD In Progress 1Q FY 2026-27 In Progress
Pursue New Revenue
Sources
1.1b Develop a Special Event that drives visitation during shoulder and
winter months and build destination awareness Carryover Rec In Progress 4Q FY 2025-26 In Progress
1.1c Develop an Economic Development Program New CMO 1Q FY 2025-26 4Q FY 2025-26 In Progress
1.2 Consider Cannabis as a Means
of Economic Development 1.2a Evaluate cannabis operations that bring in revenue New CD/CMO 1Q FY 2025-26 2Q FY 2025-26 In Progress
1.2b Conduct study session with the City Council regarding potential
cannabis ordinance Carryover CD/CA/CMO/LIS 3Q FY 2025-26 3Q FY 2025-26 Completed
1.2c Conduct study session with the City Council regarding potential
cannabis development agreement Carryover CD/CA/CMO/LIS 4Q FY 2025-26 4Q FY 2025-26 Not Started
1.2d Prepare and adopt cannabis ordinance, if directed by the City
Council Carryover CD/CA/CMO 4Q FY 2025-26 1Q FY 2026-27 Not Started
1.2e Evaluate feasibility of a Cannabis Tax, if directed Carryover CD/AS/CA/CMO 4Q FY 2025-26 1Q FY 2026-27 Completed
1.3 Transient Occupany Tax
Changes
1.3a Work on changes to TBID ordinance for expanded use of TOT
funds New CMO/Rec/LIS 1Q FY 2025-26 1Q FY 2025-26 Completed
1.3b Bring changes to TBID assessment and ordinance to Council for
approval New CMO/Rec/LIS 1Q FY 2025-26 1Q FY 2025-26 Completed
1.3c Evaluate opportunities related to City TBID and potential TOT
Measure New CMO/Rec/LIS In Progress 4Q FY 2024-25 Completed
1.3d Hold study session with City Council and visitor serving
accomodations to eliminate TBID New CMO/Rec/LIS 1Q FY 2025-26 1Q FY 2025-26 Completed
1.3e If directed by Council, issue RFP for consultant to develop a survey
and outreach strategy to community for TOT New CMO/LIS 1Q FY 2025-26 2Q FY 2025-26
Council Directed
not to Move
Forward
1.3f Award contract for consultant to survey and develop outreach
strategy for TOT New CMO/LIS 2Q FY 2025-26 2Q FY 2025-26
Council Directed
not to Move
Forward
1.3g Conduct public education regarding need for TOT New CMO/LIS 2Q FY 2025-26 2Q FY 2026-27
Council Directed
not to Move
Forward
1.3h Bring TOT measure to City Council for consideration of placing on
the November 2026 ballot New CMO/Rec/LIS 4Q FY 2025-26 4Q FY 2025-26 Completed
2.1 Pursue 2026 State Water Ballot
Measure
2.1a Meet with Department of Public Works at the County of San Luis
Obispo to begin discussion surrounding purchasing some allocated
State Water
New CMO/PW 4Q FY 2024-25 1Q FY 2025-26 In Progress
Achieve Water
Resilience
2.1b If directed by Council, Issue an RFP for a Consultant to evaluate
feasibility of State Water Ballot Measure New CMO/PW/LIS 1Q FY 2025-26 1Q FY 2025-26 Not Started
2.1c Award bid to consultant and begin public outreach and community
messaging regarding a potential State Water Ballot Measure New CMO/PW/LIS 2Q FY 2025-26 2Q FY 2026-27 Not Started
2.1d Seek Council approval on placing a November Ballot Measure New CMO/PW/LIS 4Q FY 2025-26 4Q FY 2025-26 Not Started
2.2 Seek new Water Sources 2.2a Identify opportunities and constraints associated with new Water
Sources New CMO/PW In Progress Ongoing Ongoing
2.2b Support ongoing development and financing of regional water
solution New CMO/PW In Progress Ongoing Ongoing
2.2c Conduct a water and wastewater rate study to adjust rates based
on changes to water supply and changing or new regional partnerships New AS/PW 1Q FY 2025-26 4Q FY 2026-27 In Progress
2.3 Work with Regional Partners 2.3a Preserve Lopez water supply by working with the County on Lopez
litigation New CMO/PW/CA In progress Ongoing Ongoing
2.3b NCMA Management Agreement Amendments Carryover PW In progress Ongoing Ongoing
FY 2025-27 City Council Goal's Work Plan
(Q2 Status Update 7/1/2025-12/31/2025)
Attachment 1
Page 174 of 175
Goal Strategy Task/Action Carryover Action
or New
Responsible
Department
Anticipated to
Start Completion Target Update
FY 2025-27 City Council Goal's Work Plan
(Q2 Status Update 7/1/2025-12/31/2025)
Implement Road and
Sidewalk
Improvements
3.1 Prioritize Key Infrastructure
Projects 3.1a 2025 Pavement Management Program Construction New PW
4Q FY 2025-26 1Q FY 2026-27 In Progress
3.1b Traffic Way Bridge Replacement Project Carryover PW In progress 3Q FY 2025-26 In Progress
3.1c Halcyon Complete Streets Design and Construction Carryover PW In progress 4Q FY 2026-27 In Progress
3.1d Concrete Repair Program Carryover PW 3Q FY 2025-26 Ongoing In Progress
3.1e CMP Lining Carryover CD/PW Completed 2Q FY 2025-26 Completed
3.2 Pursue Alternative Funding
Sources for Infrastructure Funding
3.2a Pursue Grant applications and administration for infrastructure
projects
Carryover PW/CD/AS In progress Ongoing Ongoing
4.1 Economic Development Tasks 4.1a Retail Market Analysis Carryover CD 4Q FY 2024-25 1Q FY 2025-26 Completed
4.1b Market Demand Studies Carryover CD 4Q FY 2024-25 1Q FY 2025-26 Completed
4.2 General Plan Elements 4.2a Land and Safety Analysis Carryover CD 3Q FY 2023-24 2Q FY 2025-26 In Progress
4.2b Administrative Draft Carryover CD In Progress
4.3 EIR 4.3a Complete draft EIR Carryover CD 1Q FY 2025-26 3Q FY 2025-26 Not Started
4.3b Complete final EIR Carryover CD 3Q FY 2024-25 4Q FY 2025-26 Not Started
4.4 Code Update 4.4a Kick off code update Carryover CD/LIS Not Started
4.4b Bring code changes to Planning Commission for approval Carryover CD 3Q FY 2025-26 3Q FY 2025-26 Not Started
4.4c Bring draft Ordinance of code revision update to Council Carryover CD 4Q FY 2025-26 4Q FY 2025-26 Not Started
4.5 Climate Action Plan 4.5a Kick off CAP and research Carryover CD 1Q FY 2025-26 4Q FY 2025-26 In Progress
4.5b Admin Draft Carryover CD 4Q FY 2025-26 2Q FY 2026-27 Not Started
4.5c Final CAP Carryover CD 2Q FY 2026-27 3Q FY 2026-27 Not Started
5.1 Scope of Work and RFP 5.1a Define scope, research other communities New CD 4Q FY 2024-25 3Q FY 2025-26 In Progress
5.2 Kick Off and Public Outreach 5.2a Kick Off New CD 1Q FY 2025-26 3Q FY 2025-26 Not Started
5.2b Public Outreach New CD Ongoing Ongoing Not Started
5.3 CEQA 5.3a Environmental Review New CD 2Q FY 2025-26 3Q FY 2025-26 Not Started
5.4 Plan Draft 5.4a Administrative Draft Plan New CD 3Q FY 2025-26 1Q FY 2026-27 Not Started
5.5 Final Draft and Hearings 5.5a Final Draft New CD 4Q FY 2025-26 1Q FY 2026-27 Not Started
5.5b Planning Commission Hearings New CD 1Q FY 2026-27 2Q FY 2026-27 Not Started
5.5c City Council Hearings New CD 2Q FY 2026-27 2Q FY 2026-27 Not Started
CMO
AS
LIS
PD
PW
Rec
Fire
CD
Legislative and Information Services
Police Department
Public Works
Recreation Services
Five Cities Fire Authority
Community Development
Complete the General