Halcyon Complete Streets Project
Pre-Bid
1
Project Goal
Transform Halcyon Road from a vehicle-centric facility to a welcoming environment that will provide for safe mobility and accessibility, connecting people by enhancing the built environment
for all modes of travel.
2
Project Elements
Storm drain line
New paving
Continuous, repaired sidewalks
Bike lanes
Trees
Roundabout at Halcyon and Fair Oaks
3
Background
Project initiated in 2013.
Active Transportation Program Grant
Conceptual Plan adopted by Council 7/25/23
Hired North Coast Engineering
30% design review 2/25/25
CTC allocated construction funding 3/19/26
100% plans 3/13/26
4
Street Trees
Goal: 200
Actual: 127
Why not more?
Sight Distance
19 cross streets
84 drive approaches
Utility conflicts
5
On-street Parking
161 existing parking spaces.
Conceptual Plan – keep 39, lose 122.
Actual – lose 127.
6
Budget
Current construction funding: $9,548,500
ATP grant: $6,885,000
Measure E-24 sales tax: $1,875,000
Development Impact Fees: $788,500
7
Utilities
8
Outreach
Conceptual Plan
4 interactive Charettes
Surveys
City Council Meetings
7/25/23 - Conceptual Plan
2/25/25 – 30% design review
Community Meeting
4/27/26
173 letters mailed
Project Webpage: arroyogrande.org/hcs
Project email: halcyon@arroyogrande.org
9
Review specific details of the draft final design of the Halcyon Complete Streets Project (“Project”) and direct staff to advertise the Halcyon Complete Streets Project for construction
as designed.
Recommendation