CC 2013-09-24_08.f. Acceptance of Fair Oaks Ave Street ImpMEMORANDUM
TO: CITY COUNCIL
FROM:
BY:
GEOFF ENGLISH, PUBLIC WORKS DIRECT~
MIKE LINN, ASSISTANT CITY ENGINEER
SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE FAIR OAKS AVENUE
WATERLINE AND STREET IMPROVEMENT PROJECT, PW 2013-06
DATE: SEPTEMBER 24, 2013
RECOMMENDATION:
It is recommended the City Council:
1. Accept the project improvements as constructed by Brough Construction
Company in accordance with the plans and specifications for the Fair Oaks
Waterline and Street Improvement Project ("project");
2. Direct staff to file a Notice of Completion; and
3. Authorize release of the retention, thirty-five (35) days after the Notice of
Completion has been recorded, if no liens have been filed.
IMPACT TO FINANCIAL AND PERSONNEL RESOURCES:
The amended Capital Improvement Program budget included $319,718 for the project.
The actual total construction project cost, including authorized construction changes, is
$301,099. The total cost of the project, including all design, construction, contract
administration, inspection and testing costs is approximately $308,000.
BACKGROUND:
On June 11, 2013, Council awarded a construction contract to perform the project to
Brough Construction Company for $285,653 and authorized the City Manager to
approve change orders in the amount of $28,565. The project scope of work included
the following on Fair Oaks Avenue, between South Halcyon Road and Alder Street:
• Widening the roadway on the south side of the roadway, adjacent to Margaret
Harlee Elementary School, by demolishing a two foot segment of the existing
sidewalk;
• Installation of a 12" waterline as an upgrade to an existing 8" waterline;
• Installation of new ADA ramps and a new concrete valley gutter at the
intersection of Fair Oaks Avenue and Alder Street;
Item 8.f. - Page 1
CITY COUNCIL
CONSIDERATION OF ACCEPTANCE OF THE FAIR OAKS AVENUE WATERLINE
AND STREET IMPROVEMENT PROJECT, PW 2013
SEPTEMBER 24, 2013
PAGE2
• Construction of an asphalt overlay;
• Restriping of the roadway.
Since the project was performed directly adjacent to the Margaret Harlee Elementary
School, all work was performed entirely during the Lucia Mar Unified School District
summer break.
ANALYSIS OF ISSUES:
The contractor has completed the work in accordance with the approved plans and
specifications. There are no outstanding issues.
ALTERNATIVES:
The following alternatives are provided for the Council's consideration:
-Approve staff's recommendations accepting the project improvements;
Do not accept the project improvements;
-Accept the project improvements, but do not authorize release of retention; or
-Provide direction to staff.
ADVANTAGES:
The project is complete. Accepting the improvements will allow staff to close out the
project and return any remaining funds to the fund balance.
DISADVANTAGES:
The disadvantage of accepting the improvements would be if subsequent deficiencies in
the work are identified. However, the contract documents include a one-year warranty
period for the contractor to address any construction defects that may arise.
ENVIRONMENTAL REVIEW:
The project is categorically exempt from CEQA pursuant to Section 15301 (c).
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted in front of City Hall on Thursday, September 19, 2013. The
Agenda and report were posted on the City's website on Friday, September 20, 2013.
No public comments were received.
Attachment:
1. Notice of Completion
Item 8.f. - Page 2
RECORDING REQUESTED BY
AND WHEN RECORDED RETURN TO: Attachment No. 1
CITY'CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE,CA 93420
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2. The FULL NAME of the OWNER is: The City of Arroyo Grande
3. The FULL ADDRESS of the OWNER is: 300 East Branch Street,Arroyo Grande, California 93420
4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee
5. THE FULL NAME and FULL ADDRESS of ALL PERSONS,if any,who hold such interest or estate with the undersigned as JOINT
TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR'S in interest of the undersigned if the property was transferred
subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7. All work of improvement on the property hereinafter described was COMPLETED August 16, 2013
8. The NAME OF THE ORIGINAL CONTRACTOR,if any, for such work of improvement is:
Brough Construction, Inc.
9. The street address of said property is: None
10. The property on which said work of improvement was completed is in the City of Arroyo Grande,County of San Luis Obispo, State
of California,and is described as follows: Fair Oaks Avenue Waterline and Street Improvements Project, PW 2013-06
Verification of NON-INDIVIDUAL owner: I,the undersigned, declare under penalty of perjury under the laws of the State of California
that I am the Director of Parks,Recreation and Facilities of the aforesaid interest or estate in the property described in the above notice;that
I have read the said notice,that I know and understand the contents thereof,and the facts stated therein are true and correct.-
Geoff English, Public Works Director
September 25,2013,Arroyo Grande,California
--END OF DOCUMENT--