CC 2014-09-23_08.c. Recycled Water Planning StudyMEMORANDUM TO: CITY COUNCIL FROM: TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR SUBJECT: CONSIDERATION OF PARTICIPATION IN A RECYCLED WATER FACILITIES PLANNING STUDY AND GRANT APPLICATION FOR A SATELLITE WATER RESOURCE RECOVERY FACILITY FOR THE SOUTH SAN LUIS OBISPO COUNTY SANITATION DISTRICT DATE: SEPTEMBER 23, 2014 RECOMMENDATION: It is recommended the City Council 1) approve participation in the preparation of a grant application and Recycled Water Facilities Planning Study (Study) for a potential Satellite Water Resources Recovery Facility (SWRRF) for the South San Luis County Sanitation District (SSLOCSD); and 2) appropriate $40,877 from the Water Fund for the City’s portion of the study and matching costs. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: It is recommended the City split the costs with the SSLOCSD. The total cost of the study and application is anticipated to be $156,700. Each agency would pay $40,877. The remainder of the cost would be paid by the grant provided through the State Water Resources Control Board’s (SWRCB) Water Recycling Facilities Planning Grant Program. Staff work would need to be dedicated to the project, but water resources is a priority goal in the City’s Critical Needs Action Plan. BACKGROUND: The Water Recycling Funding Program (WRFP) provides grants to assist public agencies with facilities planning studies to determine the feasibility of using recycled water to offset the use of fresh/ potable water from the state and/ or local supplies. The grant will cover 50 percent of the eligible costs up to a maximum of $75,000. The SSLOCSD provides wastewater treatment services for the City, as well as the City of Grover Beach and the Oceano Community Services District. Groundwater supply for these member agencies may be severely impacted due to drought conditions. On June 7, 2012, a public Water Recycling Forum was held at the South County Regional Center. In recent years, agencies have recognized that Water Recycling will be a necessary component of meeting our future water demands in the South San Luis Obispo County Area. Water Recycling can help to effectively manage groundwater resources, protect water quality, and meet California Recycled Water goals. Item 8.c. - Page 1 CITY COUNCIL CONSIDERATION OF PARTICIPATION IN A RECYCLED WATER FACILITIES PLANNING STUDY SEPTEMBER 23, 2014 PAGE 2 ANALYSIS OF ISSUES: At the City Council meeting of June 10, 2014, the Council directed staff to pursue grant opportunities for recycled water projects in order to provide long term protection of the groundwater basin. The development of a recycled water project such as the SWRRF could be used to offset groundwater pumping or provide recharge to the groundwater basin and improve water supply reliability for the City. Opportunities have been identified by SSLOCSD consulting staff that include locating a SWRRF adjacent to the Arroyo Grande trunk sewer line in the general vicinity of land south of Arroyo Grande High School. This project would intercept effluent prior to it entering the SSLOCSD plant within or immediately adjacent to the City and as such would create benefits directly to the City. Potential benefits of the satellite facility include: improved jurisdictional control; fewer permitting obstacles due to location outside of the Coastal zone, favorable conditions for groundwater recharge, cost savings due to minimized distance of distribution piping, ability to discharge brine through the existing truck sewer line, assists the SSLOCSD in meeting redundancy requirements of the Regional Water Quality Control Board, better overall feasibility of a SSLOCSD Recycled Water project and improved timing for potential water bond funding opportunities. The project is conceptual at this time, but it is generally anticipated that at 90% recovery, the project could generate approximately 500-600 acre-feet per year of water. In order to evaluate the technical and economic feasibility of the SWRRF, the SSLOCSD is engaging Water Systems Consulting (WSC) to develop the grant application and, if successful, prepare the Study. An initial investment analysis is included in the scope of work to determine economic feasibility first. If the project is deemed economically viable, WSC will proceed with development of projected water supplies and characteristics, wastewater characteristics and facilities, treatment requirements, recycled water opportunities, legal permitting requirements, and the recommended facilities project plan. ALTERNATIVES: The following alternatives are presented for the Council’s consideration:  Approve staff’s recommendations;  Do not approve staff’s recommendations;  Modify as appropriate and approve staff’s recommendations; or  Provide direction to staff. ADVANTAGES: The recommended action will allow the City of Arroyo Grande to take advantage of a grant opportunity to leverage funding, pursue a recycled water project that would benefit Item 8.c. - Page 2 CITY COUNCIL CONSIDERATION OF PARTICIPATION IN A RECYCLED WATER FACILITIES PLANNING STUDY SEPTEMBER 23, 2014 PAGE 3 the City and the SSLOCSD, and potentially position the project for additional funding opportunities in the future. The project is in line with long term water resource objectives of the City. DISADVANTAGES: Staff believes there is little disadvantage to proceeding with the study. With regard to any future project, there are a number of issues that will need to be resolved in order to proceed. These include costs, coordination and approval by partner agencies, environmental impacts, and the permitting process involved. ENVIRONMENTAL REVIEW: No environmental review is required for the study at this time. Environmental review will be required prior to proceeding with approval of any improvement project(s). PUBLIC NOTIFICATION AND COMMENTS: The Agenda was posted in front of City Hall on Thursday, September 18, 2014. The Agenda and report were posted on the City’s website on Friday, September 19, 2014. No public comments were received. Attachment: 1. Proposal from WSC, Inc. Item 8.c. - Page 3 J o·~wsc ;~ WATER SYSTEMS CONSULTING, INC. 8/12/2014 Shannon Sweeney South San Luis Obispo County Sanitation District SUBJECT: PROPOSAL TO COMPLETE A RECYCLED WATER FACILITIES PLANNING STUDY FOR A SATELLITE WATER RESOURCE RECOVERY FACILITY FOR THE SOUTH SAN LUIS OBISPO COUNTY SANITATION DISTRICT As requested, WSC has prepared the following proposal to prepare a grant application for and complete a Recycled Water Facilities Planning Study (RWFPS) for a potential Satellite Water Resources Recovery Facility (SWRRF) for the South San Luis County Sanitation District (SSLOCSD). The pu'rpose of the RWFPS will be to evaluate, identify a preferred alternative and develop an implementation plan for a SWWRF within the SSLOCSD's collection system. The SSLOCSD Wastewater Treatment Plant (WWTP) currently lacks sufficient redundancy for its secondary treatment system to allow for the existing trickling filter to be taken out of service for extended maintenance or in the event of a process upset. It is envisioned that development of a SWRRF would provide the SSLOCSD with increased upstream treatment capacity and the ability to reduce flow -rates at the existing WWTP to accommodate maintenance activities and process upsets. The SSLOCSD provides wastewater treatment services for the Cities of Arroyo Grande, Grover Beach and the Oceana Community Services District (Member Agencies). The water supplies for these agencies, specifically the Northern Cities Managemer:it Area (NCMA) of the Santa Maria Groundwater Basin, have been significantly impacted by drought conditions over the last 10 years. The development of a SWRRF would provide these agencies with access to a supplemental water supply that could be used to offset groundwater pumping or recharge the groundwat~r basin and improve water supply reliability for Southern San Luis Obispo County. In order assist the SSLOCSD in evaluating the economic feasibility and funding the development of a SWRRF, WSC proposes the following funding plan: 1. Develop an application for grant funding of $75,000 for a Recycled Water Facilities Planning Study through the State Water Resources Control Board's (SWRCB) Water Recycling Facilities Planning Grant Program (FPGP). 2. Prepare the RWFPS, including an initial investment analysis to determine if the proposed concept is economically feasible_ to implement. 3. Upon completion of the RWFPS, apply for a low interest loan through the SWRCB's Clean Water State Revolving Fund (SRF) for planning, design, and construction of the SWRRF. Funds from this PO Rox tfl)'i I s,111 I uis OIJl'.po, CA 93403 I Pho1lP: (805) 457-ll83·; I i:,1x: (80<>) ggg 276'] I 'vVWW.W~< -Ill<" COili ATTACHMENT 1 Item 8.c. - Page 4 loan could be utilized to reimburse the SSLOCSD for expenses accrued during the development of the RWFPS. This proposal does not include scope to complete the SRF funding process. To accomplish the steps described above, WSC prepared the attached scope of work, schedule and fee estimate for SSLOCSD review. If you have any questions please contact us at (aos) 457-8833; Jeff is at ext. 101 and Dan is at ext. 104. You can also email us at jszytel@wsc-inc.com or dheimel@wsc-inc.com. Sincerely, Water Systems Consulting, Inc. Jeffery Szytel, PE, MBA Principal Enclosures: Attachment 1. Scope Attachment 2. Fee Estimate Attachment 3. Schedule 2 Daniel Helmel, PE Project Manager Item 8.c. - Page 5 Attachment 1. Scope 8/12/2014 '-: ' ' ' ':, ,' •, ~ ' \ " ' -.: -: ' Item 8.c. - Page 6 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 TASK 1.0 FPGP APPLICATION ASSISTANCE WSC will assist the South San Luis Obispo County Sanitation District (SSLOCSD) to obtain funding from the Water Recycling Facilities Planning Grant Program (FPGP) administered by the State Water Resources Control Board (SWRCB) for a Satellite Water Resources Recovery Facility (SWRRF) project. This scope includes preparing, submitting and managing the FPGP application for the SWRRF project. 1.1 FPGP Application Management and Support );--WSC will manage the SWRRF project application through the FPGP process on behalf of SSLOCSD. >:-WSC will participate in an initial kickoff call with the SWRCB to start the application development process. );--WSC will provide ongoing coordination with SSLOCSD to gather required documentation and forms to complete and submit the FPGP application. );--WSC will coordinate and participate in a meeting with SWRCB staff to review the FPGP applications package. 1.2 FPGP Application Preparation );--WSC will complete the application form and compile SSLOCSD's resolution authorizing the FPGP grant application. );--WSC will prepare the Plan of Study consisting of the following components: 1. A description of the recycled water service area that will be studied. 2. The potential sources of recycled water and a summary of the unit processes currently in use at existing treatment facilities. 3. A description of the current disposal/reuse of the wastewater that is proposed to be recycled. 4. A map of the study area showing the sources of recycled water and potential service area(s). 5. Identification of the water and wastewater agencies having jurisdictions over the sources of recycled water and/or the potential service area. 6. A general description of water recycling and potable water supply alternatives that will be evaluated. 7. A description of the opportunities for stakeholder participation, for example, public meeting with the local community members, potential recycled water users, and other agencies that have a stake in the study. 8. A schedule with the start and completion dates of major tasks associated with the facilities planning study. Item 8.c. - Page 7 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 9. A list of potential problems that may cause delay in the progress of the study and description of the proposed actions to reduce the impact of these potential problems. 10. Identification of the entities that will be conducting the study and description of their roles. This may include a description of proposed subcontracts with consultants or interagency agreements with other agencies, and any force account work. 11. Proposed budget for the study, including estimated costs of specific tasks, sources of financing, and sources of funds for cash flow until grant reimbursement. ~ WSC will make necessary adjustments to the FPGP application package components after the review meeting with the SWRCB to obtain approval of the Plan of Study, thus allowing the SWRCB to issue a grant commitment. TASK 2.0 RECYCLED WATER FACILITIES PLANNING STUDY PREPARATION 2.0 lnvestment Analysis 2.0.1 Conceptual Design Criteria ~ Quantify the amount of water available for a SWRRF along the SSLOCSD trunklines from the City of Arroyo Grande through review of SSLOCSD Hydraulic Model. ~ Define conceptual design criteria for the facility. It is anticipated that the conceptual design for the facility will include the following: • Capacity to treat current Average Dry Weather-Flow (ADWF) • Advanced level of treatment suitable for groundwater recharge • Solids conveyed downstream with membrane concentrate ~ It is assumed that the SSLOCSD will provide information on potential locations and corresponding land acquisition costs for th~ treatment and recharge facilities. 2.0.2 Cost Estimates ~ Develop planning level cost estimates for constructing and operating a SWRRF in the SSLOCSD collection system. ~ Utilize existing planning level cost estimates for alternative SSSLOCSD WWTP improvements to meet the redundancy requirements for comparison with the SWRRF. ~ Utilize planning level cost estimates for supplemental water supply alternatives. Cost estimates to be obtained from the Pismo Beach Recycled Water Facilities Planning Study. Item 8.c. - Page 8 SSLOCSD SWRRF Facilities Planning Study 2.0.3 InvestmentAnalysis Scope of Work 8/12/2014 ~ Compare planning level cost estimates for the SWRRF against cost estimates for SSLOCSD redundancy requirements and supplemental water supply alternatives. · ~ Evaluate and summarize key considerations and constraints for project implementation 2.0.4 Draft Investment Analysis TM ~ Prepared draft Investment Analysis TM documenting the rest:1lts of the Investment Analysis. I Deliverable: Draft Investment Analysis TM 2.0.5 Investment Analysis Review Meeting ~ Plan, schedule and lead a meeting with SSLOCSD staff (and key stakeholders as appropriate) to review the results of the Investment Analysis. Deliverable: WSC will provide agenda and meeting materials at least three (3) _working days prior to the meeting will provide summary notes with action items within five (5) working days following the meeting. 2.0.6 Final Investment Analysis TM ~ Prepared a final Investment Analysis TM that incorporates comments from SSLOCSD staff and other stakeholders. I Deliverable: Final Investment Analysis TM 2.1 Project Management 2.1.1 Project Administration 2.1.1.1 Project schedule ~ Prepare project schedule and update as-required based upon actual progress and SSLOCSD direction. Submit revised schedules to the SSLOCSD as necessary. 2.1.1.2 Progress reports ~ Prepare progress reports to be submitted with each monthly invoice. The reports will include: 1) summary of activities accomplished in the current month; 2) outstanding information and/or coordination needs; and 3) schedule updates. Deliverable: WSC will provide a preliminary project schedule at the Kickoff Meeting and will provide updated project schedules as-needed throughout the project. WSC will provide monthly progress reports with project invoices. 2.1.2 KickoffMeeting ~ WSC will plan, organize and facilitate a l<ickoff Meeting with SSLOCSD staff. Item 8.c. - Page 9 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 );>-The purpose of the meeting will be to: (1) discuss the goals and objectives of the Planning Study including the Study Parameters identified in the Plan of Study approval by the SWRCB; (2) review the scope and schedule of the project including assumptions and proposed methodologies; (3) identify data needs and sources; (4) define coordination requirements; (5) set dates/times for the subsequent workshops; (6) confirm level and nature of SWRCB involvement during the project; (7) discuss and develop strategies for stakeholder involvement; (8) finalize the conceptual design criteria for the Investment Analysis; and (9) identify action items and required follow-up. );>-Budget is based on a 2-hour meeting attended by WSC's Principal, Associate Engineer I, and Assistant Engineer. Deliverable: WSC will provide agenda and meeting materials at least three (3) working days prior to the meeting and will provide summary notes with action items within three (3) working days following the meeting. 2.1.3 Workshops 2.1.3.1 Worf<shop #1: Conceptual Alternatives Development (1) Plan, schedule and lead a workshop with SSLOCSD staff (and key stakeholders as appropriate) to develop conceptual alternatives for the SWRRF, including customer/use type, treatment, storage, and distribution. The workshop is anticipated to include the following topics: (a) Review water supplies and characteristics (Task 2.3) (b) Review wastewater characteristics and facilities (Task 2.4) (c) Review treatment requirements (Task 2.5) (d) Review recycled water market/opportunities (Task 2.6) (e) Review legal, permitting and environmental criteria (Task 2.7) (f) Review planning and design assumptions (Task 2.8.1) (g) Develop up to three (3) conceptual treatment alternatives (h) Develop up to three (3) conceptual distribution alternatives (i) Develop up to three (3) conceptual storage alternatives (j) Develop non-recycled water alternative (2) Budget is based on a 3-hour workshop attended by WSC's Principal, Associate Engineer I, Assistant Engineer, and Staff Planner II. 2.1.3.2 Workshop #2: Alternatives Evaluation and Screening (1) Coordinate a workshop with SSLOCSD staff to evaluate and screen each of the conceptual alternatives developed in Workshop #1, and to develop/select a preferred alternative for treatment, storage and distribution. Item 8.c. - Page 10 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 (2) Develop screening/evaluation criteria for the conceptual alternatives, including: (a) Cost (capital, O&M, NPV, EAC and $/AF) (b) Water supply benefits (c} Water quality considerations (d) Flexibility, expandability (e) Sequencing/phasing/schedule considerations (f) Consistency with project goals/objectives (3) Evaluate and compare the conceptual alternatives by applying the selected screening/evaluation criteria (4) Select the preferred project alternative, which may combine aspects/components of more than one conceptual alternative (5) Budget is based on a 3-hour workshop attended by WSC's Principal, Associate Engineer I, Assistant Engineer, and Staff Planner II. Deliverable: WSC will provide agenda and meeting materials at least three (3) working days prior to each workshop and will provide summary notes with action items within three (3) working days following the meeting. 2.1.4 Deliverable Review Meetings 2.1.4.1 Deliverable Review Meeting #1: Draft Recycled Water Facilities Planning Study (1) Plan, schedule and lead a meeting to review the draft recycled water facilities planning study (2) Budget is based on a 2-hour meeting attended by WSC's Principal, Associate Engineer I, and Assistant Engineer. 2.1.4.2 Deliverable Review Meeting #2: Final Draft Recycled Water Facilities Planning Study (1) Plan, schedule and lead a meeting to review the final draft recycled water facilities planning study (2) Budget is based on a 2-hour meeting attended by WSC's Principal, Associate Engineer I, and Assistant Engineer. Deliverable: WSC will provide agenda and meeting materials at least three (3) working days prior to the meeting and will provide notes with action items within three (3) working days following the meeting. 2.2 Background 2.2.1 Study Area );:-Prepare a summary of the Study Area that includes: (1} Narrative description of the Study Area Item 8.c. - Page 11 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 (2) Descriptive maps and diagrams showing vicinity, jurisdictional boundaries, proposed annexation areas, regional topography/geography, gr~undwater basin boundaries, hydrologic features, and current and projected land use. ~ The proposed Study Area shall include the current SSLOCSD service area, proposed scalping locations along the SSLOCSD trunk lines for the City of Arroyo Grande, and the remainder of the Northern Cities Management Area (NCMA). 2.2.2 Goals and Objectives ~ Summarize goals and objectives defined during the Kickoff Meeting. 2.3 Water Supplies and Characteristics 2.3.1 Water supply characteristics ~ Summarize current and projected water supplies for the Member agencies based on 2010 Urban Water Management Plans (2010 UWMPs) and NCMA Technical Group (TG) Annual Reports. ~ For each water supply source, summarize: (1) Source characteristics (2) Capacities of existing facilities (3) Wholesale agencies and delivery mechanisms (4) Fixed and variable costs (5) Management considerations including reliability (6) Water quality considerations 2.3.2 Water Demand Characteristics ~ Summarize current and projected water demand from 2010 UWMPs and NCMA TG Annual Reports. 2.3.3 Water Pricing ~ Summarize the current water rate structures for the MEMBER Agencies and any planned or upcoming rate increases. 2.4 Wastewater Characteristics and Facilities 2.4.1 Existing Facilities ~ Describe existing wastewater treatment plant facilities including capacity, current flows, description of treatment processes and design criteria. It is assumed that this information will be readily available from previous documents. ~ Summarize the SSLOCSD's existing waste discharge requirements ~ Characterize current and projected future influent flows. It is assumed that flow projection estimates will be available from previous studies. ~ Characterize current effluent water quality including any seasonal variation Item 8.c. - Page 12 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 » Summarize source(s) of industrial or other problem constituents (including hlgh-TDS Infiltration) and control measures » Summarize current wastewater flow variations including peaking factors for maximum month (MM), maximum day (MD), peak hour wet weather flow (PHWWF) » Describe existing recycling including users, quantities, and contractual and pricing arrangements (none expected) » Summarize existing rights to use of treated effluent after discharge (none expected) 2.4.2 Future Facilities » Outline expected future waste discharge requirements based on conversations with the SSLOCSD staff, review of the Basin Plan, and meetings with SSLOCSD staff and the Regional Water Quality Control Board » Describe plans for new wastewater treatment facilities to achieve regulatory compliance 2.5 Treatment Requirements 2.5.1 Recycled Water Quality Requirements » Describe required water qualities and/or treatment requirements for each category of potential recycled water use » Describe regulatory requirements for recycled water Including Title 22 unrestricted irrigation, and groundwater recharge ~ Describe Basin Plan requirements for recycled water use » Describe water quality related requirements of the RWQCB to protect surface or ground water from problems resulting from recycled water ~ Describe operational and on-site requirements for recycled water (such as backflow prevention, buffer zones, etc.) 2.6 Recycled Water Market/Opportunities 2.6.1· Update Market Analysis » Obtain and review recent customer consumption data for potential recycled water customers identified in the Regional Recycled Water Strategic Plan » Describe validation and market analysis methodology. For each identified user or category of potential user, summarize type of use, expected annual use, peak use, estimated internal capital investment required (on-site ·conversion costs), needed water cost savings, desire to use recycled water, date of possible initial use of recycled water, present and future source(s) of water and quality of use, quality and reliability needs and wastewater disposal methods. Item 8.c. - Page 13 SSLOCSD SWRRF Facilities Planning Study 2.6.2 Preliminary Market Assurances Scope of Work 8/12/2014 );> Contact a representative sample of potential future recycled water users and obtain preliminary market assurances. It is anticipated that WSC would develop a plan to approach the top 20 potential customers (in terms of total projected recycled water use) and attempt to obtain a preliminary assurance in the form of a letter, email or other form of correspondence. It is assumed that the member agencies will assist in contacting and obtaining assurances from the identified customers within their service area. );> Develop map of proposed service area based on results of market assessment. 2. 7 Legal, Permitting and Environmental Criteria 2. 7.1 Tentative Water Recycled Requirements of RWQCB );> Contact RWQCB to obtain preliminary requirements for development of a recycled water treatment and distribution system. 2.7.2 Permitting Requirements );> Identify and summarize the probable permitting requirements for implementing recycled water projects. Utilize previously completed recycled water studies as the basis for developing the summary of probable permitting requirements. );> It is assumed that the SSLOCSD staff will take the lead in coordinating with the RWQCB and obtaining approval for utilizing a SWRRF to meet the WWTP's redundancy requirements. 2.7.3 Water Rights Considerations );> Summarize potential water rights impacts the development of the recycled water program could have on the NCMA Agencies' water rights. 2.7.4 Environmental Documentation Requirements (CEQA) );> Research and summarize the necessary environmental documentation requirements to implement a recycled water program. 2.8 Project Alternatives Analysis 2.8.1 Planning and Design Assumptions );> Develop relevant planning and design assumptions and criteria tha_t will be used when evaluating project alternatives. These assumptions should include: (1) Delivery and system pressure criteria (2) Peak delivery criteria (3) Storage criteria (4) Cost basis: key assumptions; cost index; cost escalation and contingency factors; discount rate; evaluation term for present worth analysis; etc. (5) Planning period (6) Conceptual infrastructure design criteria Item 8.c. - Page 14 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 2.8.2 Alternatives Development -Treatment );;>-Develop up to two (2) conceptual facility alternatives for each of the following levels of treatment: (1) Title 22 unrestricted irrigation (2) Partial Reverse Osmosis (3) Groundwater recharge (Advanced Treatment) );;>-Each conceptual treatment alternative will include: (1) Narrative description including summary of required unit processes and summary of pros, cons and/or key considerations (2) Simplified process flow diagram (3) Conceptual location and layout (4) Preliminary estimates of capital and O&M cost, net present value, equivalent annual cost, and cost per acre-foot of supply 2.8.3 Alternatives Development -Distribution systems );;>-Develop up to two (2) conceptual distribution system alternatives for each of the following levels of treatment: (1) Title 22 unrestricted irrigation (2) Groundwater recharge (Advanced Treatment) (a) Ana!Ysis of groundwater recharge distribution alternatives will be based upon findings from the Pismo Beach Recycled Water Facilities Planning Study. );;>-Each conceptual distribution system alternative will describe pumping and piping improvements, and will include: (1) Narrative description including summary of required infrastructure and summary of pros, cons and/or key considerations (2) Conceptual location and layout (3) Preliminary estimates of capital and O&M cost, net present value, equivalent annual cost, and cost per acre-foot of supply 2.8.4 Alternatives Development -Recycled Water Storage );;>-Develop up to two (2) conceptual alternatives for recycled water system storage. Each conceptual alternative will include: (1) Narrative description including summary of required infrastructure and summary of pros, cons and/or key considerations (2) Conceptual location and layout Item 8.c. - Page 15 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 (3) Preliminary estimates of capital and O&M cost, net present value, equivalent annual cost, and cost per acre-foot of supply 2.8.5 Non-recycled Water Alternative ~ Review the following previously completed studies to identify a preferred non-recycled water supply alternative: (1) 2010 Urban Water Management Plan (WSC, 2011) (2) Lopez Lake Spillway Raise Project (Stetson 2012) (3) Desalination Water Supply Study (Wallace 2006) (4) SSLOCSD of Arroyo Grande Water Supply Alternative Study (Wallace 2004} _ (5) South San Luis Obispo County Desalination Funding Study (Wallace 2008) (6) Coastal Branch Capacity Assessment (WSC 2011) (7) Other relevant water supply studies ~ Summarize existing estimates of capital and O&M cost, net present value, equivalent annual cost, and cost per acre-foot of the non-recycled water supply based on previously completed studies 2.8.6 Water Conservation/Reduction Analysis ~ Summarize the MEMBER agencies' current and future plans for water conservation. WSC will utilize 2010 UWMPs, NCMA TG reports, and other available resources as the basis for a water conservation summary. 2.8.7 No Project Alternative ~ Evaluate the no project alternative and include in alternatives analysis. 2.8.8 Conceptual Alternatives Analysis ~ Summarize the outcome from Workshop #2 including: (1) Screening/evaluation criteria (2) Results from the screening/evaluation (3) Preferred conceptual alternatives for treatment, distribution and storage 2.9 Recommended Facilities Project Plan 2.9.1 Preferred Alternative ~ Develop preliminary design criteria and refined pipeline routes for the preferred alternative ~ Prepare updated maps, figures, process flow diagram(s), and layouts to reflect the preferred treatment, distribution and storage alternatives ~ Update cost estimates based on final c;:onfiguration and considering expected time of construction Item 8.c. - Page 16 SSLOCSD SWRRF Facilities Planning Study Scope of Work 8/12/2014 > Prepare list of all potential users, quantity of recycled water use, peak demand and commitments obtained to-date > Compare reliability of the recycled water faciliti~s to the user requirements > Summarize on-site improvements required including cost > Prepare a schedule for the implementation of the recycled water project that includes design and construction of the treatment plant upgrades and construction of the distribution system infrastructure. Provide phasing considerations/recommendations in the preferred project plan. 2.10 Stakeholder Involvement 2.10.1 Stakeholder Outreach > Conduct stakeholder meetings to coordinate project objectives, elements, etc. Document stakeholder outreach efforts. > Budget based on three (3) 1-hr meetings attended by WSC's Principal and Associate Engineer I. 2.10.2 Public Outreach > Provide project updates at public meetings as requested by the SSLOCSD, including preparation of an explanatory presentation and/or graphics presenting the analysis and/or conclusions contained within the Recycled Water Facilities Planning Study > Document public outreach efforts. > Budget based on two (2) 1-hr meetings attended by WSC's Principal and Associate Engineer I. 2.11 Implementation Pian 2.11.1 Coordination and Governance > Determine needed agreements and ordinances for implementing a preferred alternative recycled water system. > Evaluate recycled water mandatory use ordinances and provide SSLOCSD with recommended course of action. > Prepare a draft user contract for connecting customers. 2.11.2 Construction Financing Plan and Revenue Program > Prepare funding plan that outlines sources and timing of funds for design and construction. > Summarize pricing policy recommendations for recycled water > Evaluate costs that can be allocated to water pollution control and/or water supply reliability > Develop criteria and annual projections for: (1) Water prices for each user or category of users (2) Recycled water used by each user (3) Annual costs (required revenue) of recycling project Item 8.c. - Page 17 SSLOCSD SWRRF Facilities Planning Study (4) Allocation of costs to users (5) Unit costs to serve each user or category of users Scope of Work 8/12/2014 (6). Sensitivity analysis assuming portion of potential users fail to use recycled water 2.11.3 Detailed Schedule ~ Develop a detailed schedule for the implementation of the recycled water project that includes design and construction, critical milestones from the financing and revenue program and on-site customer improvements. 2.12 Prepare Recycled Water Facilities Planning Study 2.12.1 Prepare Draft Recycled Water Facilities Pla~ning Study ~ Prepare draft Executive Summary and. compile draft report including title page(s), acknowledgements, table of contents, list of figures, list of tables, draft chapters, reference list and appendices. [ Delivemble: Draft Recycled Water Facilities Planning Study 2.12.2 Final Draft Recycled Water Facilities Planning Study ~ Prepare Final Draft Recycled Water Facilities Planning Study based on comments received from the SSLOCSD and any identified stakeholders on the draft Recycled Water Facilities Planning Study I Deliverable: Final Draft Recycled Water Facilities Planning Study 2.12.3 Final Recycled Water Facilities Planning Study ~ Prepare Final Recycled Water Facilities Planning Study based on comments received from the SSLOCSD on the Final Draft Recycled Water Facilities Planning Study. Deliverable: Final Recycled Water Facilities Planning Study Item 8.c. - Page 18 SSLOCSD SWRRF Facilities Planning Study Deliverable Description Format/Copies Scope of Work 8/12/2014 Due Date Item 8.c. - Page 19 Attachment 2. Fee Estimate 8/12/2014 ', '; ' ',\' ,,1'> I " '' _,::_ :_' ~ __ .... ", > Item 8.c. - Page 20 South San Luis Obispo County Sanitation District Recycled Water Facilities Planning Study Cost Proposal 7/31/2014 Task No. Task Description . 1.0 FPGP Application Assistance 1.1 FPGP Aoolication Mana!!ement and Suooort 1.2 FPGP Application Preparation 2.0 Investment Analysis 2.0.1 Conceptual Design Criteria 2.0.2 Cost Estimates 2.0.3 Investment Analysis 2.0.4 Draft Investment Analysis TM 2.05 Investment Analysis Review Meeting 2.0.6 Rn al Investment Analysis TM 2.1 Project Management 2.1.1 Proiect Administration 2.1.2 Kickoff Meeting 2.1.3 Workshops 2.1.4 Deliverable review meetinl!S - 2.2 Background 22.1 StudvArea 2.2.2 Goals and objectives 2.3 Water Supply and Characteristics 2.3.1 Water suoolv characteristics 2.3.2 Water demand characteristics 2.4 Wastewater Characteristics and Facilities 2.4.1 Existing facilities 2.4.2 Future facilities 2.5 Treatment Requirements ·2.5.1 Recycled water quality requirements 2.6 Recycled Water Market/Opportunities 2.6.1 Update market analvs1s 2.6.2 Preliminarv market assurances 2.7 Legal, Permitting and Environmental Criteria 2.7.1 Tentative water recyclin!! reauirements of RWQCB 2.7.2 Permitting reauirements 2.73 Water lights considerations 2.7.4 Environmental documentation requirements (CEQA) Z.8 Project Alternatives Ana Jysis 2.8.1 Planning and design assumptions 2.82 Aitemat1ves Development-Treatment 2.8.3 Alternatives Develooment -Distribution 2.84 Alternatives Develooment-Storatte - - - - - - - - - - Associate Assistant Principal Sr.Engineer Ill Engineer I Engineer 6 2 14 0 4 6 2 2 8 10 8 24 50 2 2 4 2 6 8 20 2 4 2 2 4 12 2 4 4 2 4 6 20 0 60 24 2 30 4 8 8 8 14 10 6 8 6 0 2 5 0 1 4 1 1 0 2 10 0 1 4 1 6 4 l 16 28 l 4 12 4 12 16 0 2 z 0 2 2 0 2 10 20 1 8 12 1 2 8 0 6 13 12 1 1 4 2 4 8 1 6 2 2 8 7 33 84 1 1 4 8 2 10 20 1 10 32 1 4 10 Pagel of 2 wsc Staff Clerical/ Total Labor Total Labor Total Planner Total Fee II Admin Hours Cost Expenses 16 2 40 $ 6,606 $ 200 $ 6,806 4 2 16 $ 2,752 $ 100 $ 2,852 12 24 $ 3,854 $ 100 $ 3,954 0 0 92 $ 13,670 $ 400 $ 14,070 8 $ 1,292 $ -$ 1,292 36 $ 5,306 $ 200 $ 5,506 6 $ 736 $ -$ 736 20 $ 2,910 $ 100 $ 3,010 10 $ 1,608 $ -$ 1,608 12 $ 1,818 $ 100 $ 1,918 8 14 126 $ 19,784 $ 600 $ 20,384 14 46 $ 6.472 $ 200 $ 6,672 20 $ 3,216 $ 100 $ 3,316 8 40 $ 6,534 $ 200 $ 6,734 20 $ 3,562 $ 100 $ 3,662 12 0 19 $ 2,824 $ 100 $ 2,924 10 15 $ 2,173 $ 100 $ 2,273 2 4 $ 651 $ -$ 651 16 0 28 $ 4,138 $ 200 $ 4,338 8 13 $ 1,911 $ 100 $ 2,011 8 15 $ 2,227 $ 100 $ 2,327 4 0 53 $ 7,335 $ 200 $ 7,535 2 19 $ 2,385 $ 100 $ 2,485 2 34 $ 4,950 $ 100 $ 5,050 8 0 12 $ 1,826 $ 100 $ 1,926 8 12 $ 1,826 $ 100 $ 1,926 42 0 74 $ 9,644 $ 300 $ 9,944 34 55 $ 7,209 $ 200 $ 7,409 8 19 $ 2,435 $ 100 $ 2,535 16 0 47 $ 6,796 $ 100 $ 6,896 2 8 $ 1,071 $ -$ 1,071 8 22 $ 2,982 $ 100 $ 3,082 2 9 $ 1,441 $ -$ 1,441 4 8 $ 1,302 $ -$ 1302 36 0 168 $ 22,591 $ 700 $ 23,291 2 8 $ 1,071 $ -$ 1,071 16 56 $ 8,462 $ 300 $ 8,762 8 51 $ 6,219 $ 200 $ 6419 2 17 $ 2,175 $ 100 $ 2,275 Item 8.c. - Page 21 South San Luis Obispo County Sanitation District Recycled Water Facilities Planning Study Cost Proposal 7/31/2014 Task No. Task Description 2 8.5 Non-recvcled Water Alternative 2.8.6 Water conservat1on/reductlon analvsls 2.8.7 No oroiect alternative 2 8.8 Conceptual alternatives analysis 2.9 Recommended Facilities Project Pian 2.9.i Preferred alternative 2.10 Stakeholder Involvement 2.10.1 • Stakeholder outreach 2.10.2 Public outreach 2.11 Implementation Plan 2.11.1 Coordination and ~ovemance 2.11.2 Construction financimi olan and revenue oro~ram 2.11.3 Detailed schedule 2.12 Prepare Recycled Water Facilities Pia nning Study 2.12.1 Draft Recvcled Water Facilities Plannin!! Studv 2.12.2 Final Draft Recvcled Water Facilities Planning Study 2.12.3 Final Recvcled Water Facilities Planning Study Column Totals! - - - - Principal Sr.Engineer Ill Associate Assistant Engineer I Engineer 1 2 4 2 4 1 4 10 4 4 24 20 4 4 24 20 s 0 12 8 3 6 4 2 6 4 6 10 18 26 2 4 2 4 2 4 12 16 2 2 4 6 16 16 48 68 6 6 24 28 6 6 16 24 4 4 8 16 340 I Page2 of 2 wsc Staff Planner Clerical/ Total Labor Total Labor Total Admin 'Hours Cost Expenses Total Fee II 2 9 $ 1,229 $ -$ 1,229 4 4 $ 524 $ -$ 524 6 $ 736 $ -$ 736 2 17 $ 2,175 $ 100 $ 2,275 8 0 60 $ 8,976 $ 300 $ 9,276 8 60 $ 8,976 $ 300 $ 9,276 28 0 S3 $ 7,794 $ 200 $ 7,994 14 27 $ 4,036 $ 100 $ 4,136 14 26 $ 3,758 $ 100 $ 3,858 16 0 76 $ 11,648 $ 400 $ 12,048 8 20 $ 3,264 $ 100 $ 3,364 8 42 $ 6,104 $ 200 $ 6,304 14 $ 2,280 $ 100 $ 2,380 42 0 190 $ 28,370 $ 900 $ 29,270 18 82 $ 12,144 $ 400 $ 12,544 12 64 $ 9,674 $ 300 $ 9,974 12 44 $ 6,552 $ 200 $ 6,752 252 I 161 1038 1s2,002 i 4,100 I s 1s6,102 I Item 8.c. - Page 22 Attachment 3. Schedule 8/12/2014 0 I A#~~Wn ~ilt,-a: ,, :_S_f J:l~~y~e :>·~·:·.:_ ·_ · ·-::_; -· _:_-:-->_ < ~.~::\. ·~-:1:=:~~Fi/.~\::·~·: ~ :.:~--:''i~~,~~:i('~ ·:;_'::~~:;:-~'.~::~~!!~~~ :~~ _"'-:~" :.'.'.'. :f: ~:~--:s~i~:i:: Item 8.c. - Page 23 Recycled Water Facilities Planning Study ID 1 2 3 4 5 6 7 ii - 9 10 11 12 13 Task Name •Notice to proceed :1.0 FPGP Application Assistance 1.1 FPGP Apphcation Management and Support 1.2 FPGP Application Preparation SWRCB Review of FPGP Apphcation Notification of FPGP Application Approval .2.0.1 Investment Analysis 2.0.1 Conceptual Design Criteria 2 0.2 Cost Estimates 2 0.3 Investment Analysis 2 O 4 Draft Investment Analysis TM, SSLOCSD Review of Draft Investment Analysis TM 2 0.5 Investment Analysis Review Meeting ----14 15 --· 16 17 -18 19 --20 ~- 21 2.0.6 Final Investment Analysis TM h'ask 2.1 Project Management i.1.1 Project Administration 2.1.2 Kickoff Meeting 2.1.3 Workshops Workshop #1-Conceptual Alternatives Development Workshop #2 -Alternatives Screening 2.lA Deliverable Review Meetings ii -23 Deliverable Review Meeting #1-Draft RWFPS Deliverable Review Meeting #2 -Final Draft RWFPS 24 •Task 2.2 Background -~ 2.2.1 Study Area 26 , 2 2.2 Goals and Objectives 2:[' ·;rask 2.3 Water Supplies and Characteristics 28 2.3.1 Water Supply Charactenstics 29 2.3.2 Water Demand Characteristics 30 2.3.3 Water Pricing 31 'Task 2.4 Wastewater Characteristics and Facilities 2 4.1 Existing Facilities 32 33 2.4.2 Future Facilities ~ Task 2.5 Treatment Requirements ~ 2.5.1 Recycled Water Quality Requirements 36 Task 2.6 Recycled Water Market/Opportunities 37 2 6.1 Update Market Analysis 38 2 6.2 Preliminary Market Assurances 39 il'ask 2.7 Legal, Permitting and Environmental Criteria Duration Odays 40davs 40 days 4wks 4wks 0 days 45daY, lwk 2wks lwk 2wks 2wks Odays 2wks 160davs 160 days 5 days 25days Odays Odays 40days 0 days Odavs lOdays lOdays 10 days lOdays 10 days 10 days 10 days 35days 25days 10days lOdays 10days 25days 20 days 25 days __ . __ .. 30days !Start jFin~h '· - Mon 9/1/14 Mon 9/1/14 Mon9/l/l4 Fril0/24/14 Mon9/1/14 Fri 10/24/14 Mon9/l/14 Fri 9/26/14 Mon9/29/14 Fri 10/24/14 Fri 10/24/14 Fri 10/24/14 Mon 10/27 /14 Fri 12/26/14 Mon 10/27 /14 Fri 10/31/14 Mon 10/27 /14 Fn 11/7 /14 Mon 11/10/14 Fn 11/14/14 Mon 11/17 /14 Fri 11/28/14 Mon 12/1/14 Fri 12/12/14 Fri 12/12/14 Fri 12/12/14 Mon 12/15/14 Fn 12/26/14 Mon 12/29/14 Fri 8/7 /15 Mon 12/29/14 Fn 8/7 /15 Mon 12/29/14 Fn 1/2/15 Fri 2/6/15 Fri 3/13/15 Fri 2/6/15 Fn 2/6/15 Fn 3/13/15 Fri 3/13/15 Fri 6/5/15 Fri 7 /31/15 Fri 6/5/15 Fri 6/5/15 Fri 7 /31/15 Fri 7 /31/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 'Fri 2/20/15 Mon 1/5/15 Fri 2/6/15 Mon 2/9/15 Fn 2/20/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 1/16/15 Mon 1/5/15 Fri 2/6/15 Mon 1/5/15 Fri 1/.30/15 Mon 1/5/15 Fri 2/6/15 Mon 1/5/15 Fri 2/13/15 !Predecessors 1 4 5 5 5 8,9 10 11 12 13 14 14 45 46,47,48,49,50,51 64 66 17 17 17 17 17 17 32 17 17 17 Task fiiffil&f1f!lliNIT&"A§lpg'l'J1 Project Summary ..,,.....,..~,--'-'J' Inactive Milestone Project: Schedule_SWRRF RWFPS Date· Tue 8/12/14 ' Tue 8/12/14 Sp ht Milestone Summary • External Tasks External Milestone Inactive Task @nm:1 ,.:'~ mtt•J1t;&f1'1, Inactive Summary ~ Manual Task Duration-only Pagelof2 ' I I I I 1. +10/24 • \ -- Manual Summary Rollup wn smr -' ,,,. Manual Summary Finish-only c J • -.. 2/6 i!ll ilil Ill im-- ~ ti. ---·- Deadline Progress 3/13 --- i I I I I I I I ' ' ! I L -_L ~ ... -If Item 8.c. - Page 24 Recycled Water Facilities Planning Study ID Task Name 2.7.1 Prellmlnary Recycled Water System Requirements 41 2.7.2 Permitting Requirements 42 2.7.3 Water Rights C~ns1derations ~ _ j 2.7.4 Environmental Documentation Requirements (CEci.A) 44 12.s Project Alternatives Analysis 45 -2.8.1 Planning and Design Assumptions 46 2.8.2 Alternatives Development-Treatment 47 2.8.3 Alternatwes Development -Distribution 48 2.8.4 Alternatives Development -Recycled Water Storage 49 2.8.5 Non-Recycled Water Alternative so 2.8.6 Water Conservation/Reduction Analysis 51 2.8.7 No Project Alternative 52 2.8 8 Conceptual Alternatives Analysis -~~ _ -'Tank 2.9 Recommended Facilities Project Plan 54 2.9.1 Preferred Alternative 55 :rask 2.10 Stakeholder Involvement 56 2.10.l Stakeholder Outreach 57 ' 2.10.2 Public Outreach 58 ~ask 2.11 Implementation Plan 59 I 2.11.1 Coordination and Governance I 60 ! 2.11.2 Construction Financing Plan and Revenue Program 61 ' 2.11.3 Detailed Schedule ~-_~ask 2.12 Prepare RWFPS 63 ! 2.12.1 Draft RWFPS ---i 64 ! SSLOCSD Review of Draft RWFPS Gs-; 2.12.2 Final Draft RWFPS GG-I SSLOCSD Review of Draft RWFPS 67 ' 2.12.3 Final RWFPS ------------ Task Pro1ect: Schedule_SWRRF RWFPS Spht Date: Tue 8/12/14 Milestone + Summary Tue 8/12/14 1ourat1on !Start /Finish ~---------j ___ --I 15 days Mon 1/5/15 Fri 1/23/15 15 days Mon 1/26/15 Fn 2/13/15 20 days Mon 1/5/15 Frl 1/30/15 10 days Mon 1/5/15 Fri 1/16/15 65 days Mon 1/5/15 Fri 4/3/15 25 days Mon 1/5/15 Fri 2]6/15 25 days Mon 2/9/15 Fri 3/13/15 25 days Mon 2/9/15 Fri 3/13/15 25 days Mon 2/9/15 Fri 3/13/15 20 days Mon 2/9/15 Fri 3/6/15 20 days Mon 2/9/15 Fri 3/6/15 20 days Mon 2/9/15 Fri 3/6/15 15 days Mon3/16/15 Fn4/3/15 20days Mon4/6/15 FriS/1/15 20days Mon4/6/15 Fri 5/1/15 20days Mon4/6/15 FriS/l/15 20 days Mon4/6/15 Fri 5/1/15 20days Mon4/6/15 Fri5/l/15 20days Mon4/6/15 FriS/1/15 20 days Mon4/6/15 Fri 5/1/15 20 days Mon4/6/15 Fn5/1/15 20 days Mon4/6/15 Fri 5/1/15 90days MonS/4/15 Fri9/4/15 3wks Mon5/4/15 Fri 5/22/15 2wks Mon5/25/15 Fn 6/5/15 3wks Mon 6/2!1/15 Fri 7/17/15 2wks Mon 7/20/15 Fri 7/31/15 2wks -~~ ~!'!:~~--F!_i_~4/~~ ,Predecessors 17 40 17 17 17 19 19 19 19 45 45 20 52 52 52 52 52 52 24,27,31,34,36,39,4': 63 22FS+ 15 days 65 ?~S_+ ~5 day~ .,,.. ----~ Jnactive Milestone External Tasks External Milestone Inactive Task Manual Task Duration-only Page2 of2 Manual Summary Rollup ~s '~·~,,Tl~--· --- Manual Summary ..... _.,....,,_,_.... Finlsh~only c J I ~ Deadline Progress Item 8.c. - Page 25 SSLOCSD SWRRF Preliminary Cost Estimates Unit Cost Unit C-33 C-10 Assumed Units Assumed Units Source ADWF(mgd) 0.56 0.82 PWWF(mgd) 1.67 2.45 Construction Costs MBR $ 15,230,774 $/mgd $ 8,487,806 $ 12,457,554 AWT $ 6,000,000 $/mgd $ 3,343,680 $ 4,907,520 Land Purchase $ 200,000 $/acre $ 614,815 $ 614,815 3.07 RRWSP for Alt S3b: 8.3 acres for 2.7 MGD Recharge Pond $ 15,000 $/acre $ 46,111 $ 46,111 3.07 RRWSP for Alt S3b: 8.3 acres for 2.7 MGD Storage Facility $ 1,500,000 $/MG $ 835,920 $ 1,226,880 Pump Station Contingencies/ Soft Costs Construction Contingency 30% % of Construction and O&M $ 1,306,303 $ 1,822,370 Engineering/ Admin/CM/et c. (Implementation Costs) 40% % of Construction and O&M $ 2,264,259 $ 3,158,776 Total $ 16,898,894 $ 24,234,026 O&MCosts Treatment-Full AWT (MF/RO/AOP) $ 600,000 $/mgd $ 334,368 $ 490,752 Recharge Basin $ 5,000 $/acre $ 15,370 $ 15,370 3.07 RRWSP for Alt S3b: 8.3 acres for 2. 7 MGD Total $ 349,738 $ 506,122 Item 8.c. - Page 26 SSLOCSD SWRRF Preliminary Cost Estimates Unit Cost Unit C-33 C-10 Assumed Units Assumed Units Source ADWF(mgd) 0.56 0.82 PWWF(mgd) 1.67 2.45 Construction Costs MBR $ 15,230,774 $/mgd $ 8,487,806 $ 12,457,554 AWT $ 6,000,000 $/mgd $ 3,343,680 $ 4,907,520 Land Purchase $ 200,000 $/acre $ 614,815 $ 614,815 3.07 RRWSP for Alt S3b: 8.3 acres for 2.7 MGD Recharge Pond $ 15,000 $/acre $ 46,111 $ 46,111 3.07 RRWSP for Alt S3b: 8.3 acres for 2. 7 MGD Storage Facility $ 1,500,000 $/MG $ 835,920 $ 1,226,880 Pump Station Contingencies/ Soft Costs Construction Contingency 30% % of Construction and O&M $ 1,306,303 $ 1,822,370 Engineering/ Adm in/CM/et c. (Implementation Costs) 40% % of Construction and O&M $ 2,264,259 $ 3,158,776 Total $ 16,898,894 $ 24,234,026 O&MCosts Treatment-Full AWT (MF/RO/AOP) $ 600,000 $/mgd $ 334,368 $ 490,752 Recharge Basin $ 5,000 $/acre $ 15,370 $ 15,370 3.07 RRWSP for Alt 53b: 8.3 acres for 2. 7 MGD Total $ 349,738 $ 506,122 Item 8.c. - Page 27 THIS PAGE INTENTIONALLY LEFT BLANK Item 8.c. - Page 28