CC 2015-11-10_09e Accept Reservoir No 5_Ext Recoating ProjectMEMORANDUM
TO: CITY COUNCIL
FROM:
BY:
GEOFF ENGLISH, PUBLIC WORKS DIRECTOR
SHANE TAYLOR, UTILITIES MANAGER
SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE RESERVOIR NO. 5
EXTERIOR-RECOATING PROJECT, PW 2015-11
DATE: _NOVEMBER 10, 2015
RECOMMENDATION:
It is recommended the City Council:-
1. Accept the project improvements as constructed by Paso Robles Tank, Inc. in
accordance with the plans and specifications for the Reservoir No. 5 Exterior
Recoating Project; -
2. Dir~ct staff to file a Notice of Completion; and
3. Authorization release of the -retention, thirty-five (35) days after the Notice of
Completion has been recorded, if no liens have been filed.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
The FY 2015-16 capital improvement program budget includes $125,000 for the
Reservoir No. 5 Recoating project. The total project co~t (design, construction,
administration, testing, etc.) is estimated at $53,300. The contractor's final construction
cost is $41,400. The recommended action will not result in any impact on staff
resources.
BACKGROUND:
On August 25, 2015, Council awarded a construction contract to perform the subject
project to Paso Robles Tank, Inc. for $41,400 and authorized the City Manager to
" approve change orders in the amount of $4, 140. The project scope involved
preparation, minor surface repairs and painting the exterior of the existing 1,200,000
gallon above ground steel water Reservoir No. 5, accesse.d from a driveway off Puesta
Del Sol.
ANALYSIS OF ISSUES:
The contractor has completed the work in accordance with the approved plans and
specifications. There are no outstanding issues.
Item 9.e. - Page 1
CITY COUNCIL
CONSIDERATION OF ACCEPTANCE OF THE RESERVOIR NO. 5 EXTERIOR
RECOATING PROJECT, PW 2015-11
NOVEMBER 10, 2015
PAGE2
ALTERNATIVES:
The following alternatives are provided for the Council's consideration:
1. Approve staff's recommendations to accept the Reservoir No. 5 Exterior
Recoating project;
2. Do not accept the Reservoir No. 5 Exterior Recoating project;
3. Accept the Reservoir No. 5 Exterior Recoating project but do not authorize
release of retention; or
4. Provide direction to staff.
ADVANTAGES:
The project is complete. Accepting the improvements will allow staff to close out the
project. Remaining funds in the project account will be returned to the Water Fund
Balance.
DISADVANTAGES:
The disadvantage of accepting the improvements would be if subsequent deficiencies in
the work are identified. However, the contract documents include a one-year warranty
period for the contractor to address any construction defects that may arise.
ENVIRONMENTAL REVIEW:
The project is categorically exempt from CEQA pursuant to Section 15301 (b ).
PUBLIC NOTIFICATION AND COMMENTS:
The agenda was posted at City Hall on Thursday, November 5, 2015. The agenda and
staff report was posted on the City's website on Friday, November 6, 2015. No public
comments were received as of the time of preparation of this report.
Attachment:
1. Notice of Completion
Item 9.e. - Page 2
RECORDING REQUESTED BY
AND WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE, CA 93420
NOTICE IS HEREBY GIVEN THAT:
ATTACHMENT 1
NOTICE OF COMPLETION
1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2. The FULL NAME of the OWNER is: --"-'Th'""e'-C=itv~of'""'A""'r_,_r""'"oy,__,o'-G~ra=n=d=e ______________ _
3. The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande. California 93420
4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: ~'~·n_,_fe=e'--------------
5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as
JOINT TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR'S in interest of the undersigned ifthe property was
transferred subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7. All work of improvement on the property hereinafter described was COMPLETED September 30, 2015
8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
Paso Robles Tank Inc.
9. The street address of said property is: None
10. The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo,
State of California, and is described as follows: Reservoir No. 5 Exterior Recoating Project, PW 2015-11
Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of
California that I am the Community Development Director of the aforesaid interest or estate in the property described in the above
notice; that I have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and
correct.
Geoff English, Public Works Director
October 30, 2015, Arroyo Grande, California
--END OF DOCUMENT --