Loading...
CC 2016-12-13_09g Accept Mid-Block Crosswalk Project MEMORANDUM TO: CITY COUNCIL FROM: GEOFF ENGLISH, PUBLIC WORKS DIRECTOR BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE MID-BLOCK CROSSWALK BARRIER REMOVAL PROJECT, PW 2015-03 DATE: DECEMBER 13, 2016 RECOMMENDATION: It is recommended the City Council: 1. Accept the project improvements as constructed by Victor Concrete, Inc. in accordance with the plans and specifications for the Mid-Block Crosswalk Barrier Removal Project; 2. Direct staff to file a Notice of Completion; and 3. Authorize release of retention, thirty-five (35) days after the Notice of Completion has been recorded, if no liens have been filed. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: The amended FY 2015-16/FY 2016-17 Capital Improvement Program Budget includes $73,089 for the subject project, which includes $63,363 of Community Development Block Grant (CDBG) funds. The total cost of the completed project (including contingencies, design, contract administration and inspection) is estimated to be $68,600. In order to maximize the CDBG funds, $3,025 of local funds from the Various Striping and Sidewalks Improvements project was transferred to the project at time of contract award in order to fund both the base bid and additive bid. Only a small contingency was needed during the course of the project and there was less contract administration and inspection needed than planned for in the project budget. Therefore, the $3,025 of local funds can be returned to the Various Striping and Sidewalks Improvements project. The recommended action will not result in any impact on staff resources. BACKGROUND: On October 11, 2016, Council awarded a construction contract to perform the Mid-Block Crosswalk Barrier Removal Project to Victor Concrete, Inc. in the amount of $43,482.00 Item 9.g. - Page 1 CITY COUNCIL CONSIDERATION OF ACCEPTANCE OF THE MID-BLOCK CROSSWALK BARRIER REMOVAL PROJECT, PW 2015-03 DECEMBER 13, 2016 PAGE 2 and authorized the Interim City Manager to approve change orders in the amount of $4,348.20. The project provides American with Disability Act (ADA) accessible curb ramps where none currently exist at three mid-block crosswalk locations: Huasna Road/Rosewood Lane, East Grand Avenue/Alder Street and Ash Street/Spruce Street. ANALYSIS OF ISSUES: The contractor has completed the work in accordance with the approved plans and specifications at the three locations identified in the award of contract staff report ahead of contract timelines and within budget. There are no outstanding issues. ALTERNATIVES: The following alternatives are provided for the Council’s consideration: 1. Accept the Mid-Block Crosswalk Barrier Removal project; 2. Do not accept the project; 3. Accept the project but do not authorize release of retention; or 4. Provide direction to staff. ADVANTAGES: The project is complete. Accepting the improvements will allow staff to close out the project. Remaining funds in this project account will be returned to the Various Striping and Sidewalks Improvements project fund balance. The project is consistent with the Council goal to support City infrastructure. DISADVANTAGES: The disadvantage of accepting the improvements would be if subsequent deficiencies in the work are identified. However, the contract documents include a one-year warranty period for the contractor to address any construction defects that may arise. ENVIRONMENTAL REVIEW: The project is categorically exempt from California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301(c) covering the repair and maintenance of existing highways, streets and sidewalks. PUBLIC NOTIFICATION AND COMMENTS: The Agenda was posted at City Hall and on the City’s website in accordance with Government Code Section 54954.2. Attachment: 1. Notice of Completion Item 9.g. - Page 2 RECORDING REQUESTED BY ATTACHMENT 1 AND WHEN RECORDED RETURN TO: CITY CLERK CITY OF ARROYO GRANDE 300 EAST BRANCH STREET ARROYO GRANDE, CA 93420 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN THAT: 1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below. 2. The FULL NAME of the OWNER is: The City of Arroyo Grande 3. The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420 4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee 5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as JOINT TENANTS or as TENANTS IN COMMON are: NAMES ADDRESSES None 6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was transferred subsequent to the commencement of the work of improvements herein referred to: NAMES ADDRESSES None 7. All work of improvement on the property hereinafter described was COMPLETED December 1, 2016 8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is: Victor Concrete, Inc. 9. The street address of said property is: Huasna Road/Rosewood Lane, East Grand Avenue/Alder Street and Ash Street/ Spruce Street , in the City of Arroyo Grande, CA 10. The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo, State of California, and is described as follows: Mid-Block Crosswalk Barrier Removal project, PW 2015-03 Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct. _________________________________________________ Geoff English, Public Works Director December 13, 2016, Arroyo Grande, California -- END OF DOCUMENT -- Item 9.g. - Page 3 THIS PAGE INTENTIONALLY LEFT BLANK Item 9.g. - Page 4