CC 2017-01-24_12a Bridge Street BridgeConsideration Of A Project Status Update And Elimination Of The Replacement Alternative For The Bridge Street Bridge Project
1/24/2017
Item 12.a
1
JANUARY 24, 2017 | CITY COUNCIL MEETING
2
11/6/13 – Project Design Alternatives Presented at Community Meeting
1/22/14 – Project Status Update Presented at Community Meeting
1/27/15 – Presented to City Council (2 Alternatives Selected)
1/2/2016 – Project Status Update Presented at a Community Meeting
Numerous Stakeholder Meetings
http://www.arroyogrande.org/524/Public-Involvement
1/24/2017
Item 12.a
Public input
3
What have we completed?
Continued Stakeholder Involvement
Delivered 65% Designs for both Alternatives
Completed several Draft Environmental Technical Studies
Received Confirmation of Finding of No Adverse Effect from Caltrans
What are we working on now?
Council Approval to Remove Replacement Alternative From Further Consideration
Addressing City and Stakeholder Rehabilitation Alternative Comments
City & Quincy Initiating Utility Relocation Work
Finalize Environmental Technical Studies
Begin Development of Environmental Document
What are the Next Steps?
Environmental Overview
Develop more detailed construction schedule
1/24/2017
Item 12.a
Project update
4
Finalize Remaining Environmental Technical Studies
Finding of No Adverse Effect (FONAE) – Awaiting Final Signature
Memorandum of Agreement (MOA) – May not be required
Section 4(f) Evaluation – May be finalized after FONAE approval
Archaeological Study Report (ASR) - Completed
Historic Resources Evaluation Report (HRER) - Completed
Historic Properties Survey Report (HPSR) - Completed
Visual Impact Assessment (VIA) - Completed
Noise Study - Completed
Water Quality Assessment Memo - Completed
Location Hydraulic Study (LHS) - Completed
Initial Site Assessment (ISA) - Completed
Natural Environmental Study (NES) – 2nd Draft into Caltrans
Biological Assessment (BA) – Draft Underway
Wetland Delineation – 2nd Draft into Caltrans
CEQA – Drafting Initial Study/ Mitigated Negative Declaration is proposed
Circulation of Draft Environmental Document & Public Comment Periods
City Council adopts Environmental Document
Final Design on Rehabilitation Alternative is initiated
Environmental Permits secured
1/24/2017
Item 12.a
Environmental overview
5
Complete Environmental Technical Studies
Adopt Environmental Document
Final PS&E, Permits, Utility Relocation
Right of Way Certification
1/24/2017
Item 12.a
Project Schedule
Summer 2017
Fall 2017
Spring 2018
Finalize Tech Studies
Winter 2017
Summer 2018
Winter 2018
Environmental Clearance
Final PS&E
Begin Construction
Spring 2019
Public Circulation of
Draft ED
Fall 2018
Permits, Certify Right of Way & Utilities
Advertise for Construction
Authorization for Construction
6
Questions & Answers
7