CC 2017-02-14_09g Accept 2016 Street Resurfacing
MEMORANDUM
TO: CITY COUNCIL
FROM: GEOFF ENGLISH, PUBLIC WORKS DIRECTOR
BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER
SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE 2016 STREET
RESURFACING PROJECT, PW 2016-08
DATE: FEBRUARY 14, 2017
RECOMMENDATION:
It is recommended the City Council:
1. Accept the project improvements as constructed by American Asphalt South, Inc.
in accordance with the plans and specifications for the 2016 Street Resurfacing
Project;
2. Direct staff to file a Notice of Completion; and
3. Authorize release of retention, thirty-five (35) days after the Notice of Completion
has been recorded, if no liens have been filed.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
The FY 2016/17 Capital Improvement Program Budget includes $905,000 for the
pavement management program. The contractor’s final construction cost is $82,268.26
which is within the project budget approved by Council at time of contract award and
within the available pavement management program budget reserved for slurry seals.
The recommended action will not result in any impact on staff resources.
BACKGROUND:
On September 13, 2016, Council awarded a construction contract to perform the 2016
Street Resurfacing project to American Asphalt South, Inc. in the amount of $75,374.03
and authorized the City Manager to approve change orders in the amount of $7,537.40.
The project consisted of applying a slurry seal application to the street segments that
received repairs as part of the 2016 Street Repairs project.
Item 9.g. - Page 1
CITY COUNCIL
CONSIDERATION OF ACCEPTANCE OF THE 2016 STREET RESURFACING
PROJECT, PW 2016-08
FEBRUARY 14, 2017
PAGE 2
ANALYSIS OF ISSUES:
The contractor has completed the work in accordance with the approved plans and
specifications at the locations identified in the award of contract staff report within the
contract time and within budget. There are no outstanding issues.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept the 2016 Street Resurfacing project;
2. Do not accept the project;
3. Accept the project but do not authorize release of retention; or
4. Provide direction to staff.
ADVANTAGES:
The project is complete. Accepting the improvements will allow staff to close out the
project. The project is consistent with the Council goal to support City infrastructure.
DISADVANTAGES:
The disadvantage of accepting the improvements would be if subsequent deficiencies in
the work are identified. However, the contract documents include a one-year warranty
period for the contractor to address any construction defects that may arise.
ENVIRONMENTAL REVIEW:
The project is categorically exempt from the California Environmental Quality Act
(CEQA) pursuant to CEQA Guideline Section 15301(c) covering the repair and
maintenance of existing highways and streets.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
Attachment:
1. Notice of Completion
Item 9.g. - Page 2
RECORDING REQUESTED BY ATTACHMENT 1
AND WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE, CA 93420
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1. The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2. The FULL NAME of the OWNER is: The City of Arroyo Grande
3. The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420
4. The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee
5. THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as
JOINT TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6. THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was
transferred subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7. All work of improvement on the property hereinafter described was COMPLETED December 14, 2016
8. The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
American Asphalt South, Inc.
9. The street address of said property is: Various streets throughout the City of Arroyo Grande
10. The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo,
State of California, and is described as follows: 2016 Street Resurfacing, PW 2016-08
Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of
California that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I
have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct.
_________________________________________________
Geoff English, Public Works Director
February 14, 2017, Arroyo Grande, California
-- END OF DOCUMENT --