CC 2017-10-24_11a PP_Animal Services Shelter
1
Next Steps
2
Monthly Update
Animal Services New Facility
Steering Meeting – October 18, 2017
3
Monthly Update
Animal Services New Facility
Steering Meeting – October 18, 2017
4
2016
2020
Today
2016
2017
2018
2019
2020
Board Action - Woods Lease Revision
9/26/2016
CM / PM / Master Architect RFP Released
9/30/2016
CM/PM Proposals Received
11/10/2016
Board Action – Award Consultant Contract / Cities MOA
2/28/2017
251 days
July 2016 – January 2017
Scope & Charter
135 days
September 2016 – March 2017
CM/PM RFP and Project Kick-off
399 days
March 2017 – February 2018
Needs Assessment (update) & Bridging Docs
714 days
December 2017 – February 2018
Design Build (DB) Pre-Qualification
302 days
May 2018 – November 2018
D-BE Design and Construction documents
644 days
Sept. 2018 – February 2020
Design Build Implementation
(Construction with fast track grading permit)
84 days
Feb. 2020 – April 2020
Commissioning and Project Closeout
New Animal Shelter – Timeline October 2017
Board Update: Discuss Conceptual Layouts / Value Engineering / Request for Pre-Qualification (D-B Entities)
9/19/2017
February 2018 - May 2018
RFP & Design Competition
5
Project Cost Summary October 2017
6
Bridging Document Status - October 2017
Nearing Schematic Design Level of Completion
Held Standards Meeting with Various Groups
Waiting of Final Consultant Reports
Hydrology Study Geotechnical Report
CEQA Documents Fire Flow Tests
CEQA Document
Targeting end of October for draft delivery to County
7
Funding/Expenses Summary through Mid-October 2017
8