CC 2018-06-12_09h Award Contract_2018 Concrete Repairs
MEMORANDUM
TO: CITY COUNCIL
FROM: BILL ROBESON, PUBLIC WORKS DIRECTOR
BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER
SUBJECT: CONSIDERATION OF AN AWARD OF CONTRACT TO G. SOSA
CONSTRUCTION, INC. FOR CONSTRUCTION OF THE 2018
CONCRETE REPAIRS PROJECT, PW 2018-03
DATE: JUNE 12, 2018
SUMMARY OF ACTION:
Award of a construction contract for concrete repairs and sidewalk installation within the
City. Work is anticipated in July and August 2018.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
It is proposed that the project be funded as follows. Staff time will be necessary to
coordinate construction activities with the contractor and construction management and
testing consultants.
REVENUE
FY 2018/19 Budget * $110,000
FY 2017/18 Carry Over 50,318
TOTAL REVENUE $160,318
EXPENDITURES
2018 Concrete Repairs Construction and Contingencies $ 141,790
Construction Mgt, Inspection, Advertisement 5,268
2018 Record Drawings and 2019 Concrete Design 13,260
TOTAL EXPENDITURES $ 160,318
* Pending Council approval of the FY 2018-19 Capital Improvement Program (CIP) budget.
RECOMMENDATION:
It is recommended the City Council:
1. Award a contract for the 2018 Concrete Repairs Project to G. Sosa Construction,
Inc. in the amount of $128,900; and
2. Authorize the City Manager to approve change orders for 10% of the contract
amount, $12,890 for unanticipated costs during the construction phase of the
project (total construction costs = $128,900 + $12,890 = $141,790).
Item 9.h. - Page 1
CITY COUNCIL
CONSIDERATION OF AN AWARD OF CONTRACT TO G. SOSA CONSTRUCTION,
INC. FOR CONSTRUCTION OF THE 2018 CONCRETE REPAIRS PROJECT, PW
2018-03
JUNE 12, 2018
PAGE 2
BACKGROUND:
On May 8, 2018, the Council approved construction plans and specifications for the
2018 Concrete Repairs project which consists of the replacement of damaged/uplifted
sidewalk and uplifted curb and gutter adjacent to mature trees along segments of
Halcyon Road and in locations in the vicinity of Harloe Elementary School, replacement
of a section of sidewalk on Huasna Road east of Callie Court, and the installation of
sidewalk on Farroll Avenue between Gaynfair Terrace and Alder Street. The project
includes locations in the Base Bid and Add Alternate Bid locations in order to allow the
City to award the Base Bid as well as Add Alternate Bid items in any order or quantity of
Add Alternates based on available funding.
The specifications restrict work hours on Farroll Avenue and on South Halcyon Road
between Fair Oaks Avenue and Farroll Avenue for work extending past August 15,
2018, in order to maintain student pedestrian traffic.
ANALYSIS OF ISSUES:
On May 31, 2018, three bids were received for the 2018 Concrete Repairs project. The
lowest bid, from G. Sosa Construction, Inc. was in the amount of $128,900. The bid has
been determined to be responsive and G. Sosa Construction, Inc. to be a responsible
bidder.
Based on the total concrete repair program budget available, the award of a
construction contract to G. Sosa Construction, Inc. is recommended as follows:
BASE BID (RECOMMENDED)
Location Limits Proposed Improvement
Farroll Avenue Gaynfair Terrace to
Alder Street
Installation of new sidewalk
and ADA curb ramps
South Halcyon Road
(west side, 6 locations)
Fair Oaks Avenue to
Farroll Avenue Sidewalk repair
South Halcyon Road
(4 locations) 310 S Halcyon Road Sidewalk, curb, and gutter repair;
sidewalk underdrain replacement
South Halcyon Road
(1 location) 204 S Halcyon Road Sidewalk repair
South Halcyon Road
(2 locations) 200 S Halcyon Road Sidewalk repair
Huasna Road
(north side; 1 location) East of Callie Court Sidewalk, curb, and gutter repair;
sidewalk underdrain removal
Item 9.h. - Page 2
CITY COUNCIL
CONSIDERATION OF AN AWARD OF CONTRACT TO G. SOSA CONSTRUCTION,
INC. FOR CONSTRUCTION OF THE 2018 CONCRETE REPAIRS PROJECT, PW
2018-03
JUNE 12, 2018
PAGE 3
BID ADD ALTERNATES (NOT RECOMMENDED DUE TO AVAILABLE FUNDING)
Location Limits Proposed Improvement
1. South Halcyon Road
(1 location) 382 S Halcyon Road Sidewalk repair
2. South Halcyon Road
(1 location) 280 S Halcyon Road Sidewalk, curb, and gutter repair
3. North Halcyon Road
(1 location) 310 N Halcyon Road Sidewalk, curb, gutter & driveway
approach repair; remove one tree
4. South Halcyon Road
(2 locations) 303 S Halcyon Road Sidewalk, curb, and gutter repair
5. South Halcyon Road
(1 location) 345 S Halcyon Road Sidewalk repair
6. South Halcyon Road
(east side, 1 location)
Todd Lane to Olive
Street Sidewalk, curb, and gutter repair
The contract time is 30 working days. It is anticipated work will be completed in July and
August 2018.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Approve staff’s recommendations;
2. Do not approve staff’s recommendations and request further information;
3. Modify staff’s recommendation and approve; or
4. Provide direction to staff.
ADVANTAGES:
The project will reduce the potential trip and fall hazards along selected streets, address
complaints from the public, improve access for individuals with mobility limitations,
provide enhanced access to Harloe Elementary School and is consistent with the City
Council goal to support City infrastructure.
DISADVANTAGES:
There will be intermittent sidewalk closures during the project. These will be minimized
as much as possible with construction being scheduled during the school summer
break, and the project specifications require the contractor to notify affected businesses
and residents in advance.
Item 9.h. - Page 3
CITY COUNCIL
CONSIDERATION OF AN AWARD OF CONTRACT TO G. SOSA CONSTRUCTION,
INC. FOR CONSTRUCTION OF THE 2018 CONCRETE REPAIRS PROJECT, PW
2018-03
JUNE 12, 2018
PAGE 4
ENVIRONMENTAL REVIEW:
The project is categorically exempt from the California Environmental Quality Act
(CEQA) pursuant to Guideline Section 15301(c) for existing sidewalk, gutter and similar
facilities.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
Attachment:
1. Bid Opening Log Sheet
Item 9.h. - Page 4
ATTACHMENT 1
Item 9.h. - Page 5
SUBMITTED BY: 1.
BASE BID:
ALT.#1
ALT.#2
ALT.#3
ALT.#4
ALT. #5
ALT.#6
TOTAL BID:
CITY OF ARROYO GRANDE
BID OPENING LOG SHEET
DEADLINE: THURSDAY, MAY 31, 2018-2:00 PM
PROJECT NAME: 2018 CONCRETE REPAIRS
PROJECT NO.: PW-2018·03
ESTIMATED CONSTRUCTION COST: $108,800
F. Loduca, Co. 2. G. Sosa Construction
Stockton, CA 95269 Santa Marla, CA 93458
$132,642.00 $128,900.00
$3,300.00 $2,040.00
$4,125.00 $4,700.00
$19,580.00 $20,900.00
$15,025.00 $10,320.00
$1,400.00 $1,300.00
$4,100.00 $6,240.00
$180,172.00 $174,400.00
Glenda Boner, Administrative Secretary
C: Director of Public Works
Capital Improvement Project Manager
3. V. Lopez Jr. & Sons
Santa Marla, CA 93456
$129,546.00
$1,120.00
$3,248.00
$17,628.00
$11,089.00
$1,300.00
$3,991.00
$167,922.00