CC 2019-08-13_08f Acceptance of Huasna-Oro CMP and Woodland Sewer Lining ProjectMEMORANDUM
TO: CITY COUNCIL
FROM: BILL ROBESON, PUBLIC WORKS DIRECTOR
BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER
SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE HUASNA ROAD/ORO
DRIVE CORRUGATED METAL PIPE (CMP) AND WOODLAND DRIVE
SEWER LINING PROJECT, PW 2018-01
DATE: AUGUST 13, 2019
SUMMARY OF ACTION:
Acceptance of the Huasna Road/Oro Drive Corrugated Metal Pipe (CMP) and Woodland
Drive Sewer Lining project and beginning of the one-year warranty period for any defects
that may arise.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
An allocation of $251,300 of Local Sales Tax funds was included in the Capital
Improvement Program (CIP) budget for lining existing storm drain pipes, and $55,000 of
Sewer funds was included for lining an existing sewer main pipe. It is estimated that a
total of $273,000 will be expended for design, construction, administration, and
inspection. The recommended action will not impact staff resources.
RECOMMENDATION:
It is recommended the City Council:
1. Accept the project improvements as constructed by Sancon Technologies, Inc. in
accordance with the plans and specifications for the Huasna Road/Oro Drive CMP
and Woodland Drive Sewer Lining Project, PW 2018-01;
2. Direct staff to file a Notice of Completion; and
3. Authorize release of retention, thirty-five (35) days after the Notice of Completion has
been recorded, if no liens have been filed.
BACKGROUND:
On April 23, 2019, the Council awarded a construction contract to perform the Huasna
Road/Oro Drive CMP and Woodland Drive Sewer Lining project to Sancon Technologies,
Inc. in the amount of $242,061 and authorized the City Manager to approve change orders
in the amount of $24,206. The contractor’s final construction cost for this project is
$245,986.20.
Item 8.f. - Page 1
CITY COUNCIL
CONSIDERATION OF ACCEPTANCE OF THE HUASNA ROAD/ORO DRIVE
CORRUGATED METAL PIPE (CMP) AND WOODLAND DRIVE SEWER LINING
PROJECT, PW 2018-01
AUGUST 13, 2019
PAGE 2
The project consists of the rehabilitation of approximately 900 feet of storm drain pipe
along Oro Drive and Huasna Road, and the rehabilitation of approximately 543 linear feet
of sewer pipe that runs beneath the backyards of homes along Woodland Drive between
Fair Oaks Avenue and Olive Street.
ANALYSIS OF ISSUES:
The contractor has completed the work in accordance with the approved plans and
specifications on schedule and under the available budget. There are no outstanding
issues.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept the Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining
project;
2. Do not accept the project;
3. Accept the project but do not authorize release of retention; or
4. Provide direction to staff.
ADVANTAGES:
The project is complete and accepting the improvements will allow staff to close out the
project. Rehabilitation and ongoing maintenance of storm drain and sewer mains is
essential to maintaining a properly functioning system. The project is consistent with the
City Council goal to support City infrastructure.
DISADVANTAGES:
No disadvantages have been identified.
ENVIRONMENTAL REVIEW:
No environmental review is needed to accept the project.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
Attachment:
1. Notice of Completion
Item 8.f. - Page 2
RECORDING REQUESTED BY
AND WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE, CA 93420
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1.The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2.The FULL NAME of the OWNER is: The City of Arroyo Grande
3.The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420
4.The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee
5.THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as
JOINT TENANTS or as TENANTS IN COMMON are:
NAMES ADDRESSES
None
6.THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was
transferred subsequent to the commencement of the work of improvements herein referred to:
NAMES ADDRESSES
None
7.All work of improvement on the property hereinafter described was COMPLETED July 31, 2019
8.The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
Sancon Technologies, Inc.
9.The street address of said property is: Oro Drive, Huasna Road, and Woodland Drive in the City of Arroyo Grande, CA
10.The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo,
State of California, and is described as follows: Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining Project,
PW 2018-01
Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California
that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the
said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct.
_________________________________________________
Bill Robeson, Public Works Director
August 13, 2019, Arroyo Grande, California
-- END OF DOCUMENT --