CC 2019-10-08_08f Accept 2019 Concrete Repairs ProjectMEMORANDUM
TO: CITY COUNCIL
FROM: BILL ROBESON, PUBLIC WORKS DIRECTOR
BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER
SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE 2019 CONCRETE
REPAIRS PROJECT, PW 2019-02
DATE: OCTOBER 8, 2019
SUMMARY OF ACTION:
Acceptance of the 2019 Concrete Repairs project and beginning of the one-year warranty
period for any defects that may arise.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
An allocation of $190,003 of Local Sales Tax funds is included in the FY 2019/20
amended Capital Improvement Program (CIP) budget for the Concrete Repairs Program.
Of this amount $98,498 has been expended ($89,518 for the 2019 Concrete Repairs
project and $8,980 for sidewalk repairs on East Cherry Avenue). There is a remaining
balance of $91,505 which staff intents to program to other prioritized concrete repairs
including ADA access improvements, repair and enhance flashing crosswalks in the
Village, and 2020 Concrete Repairs program design and record drawings. The design
and drawings for the next Concrete Repairs program (in this case 2020) are historically
done in the winter season of the prior year so that in bidding can take place in the spring
and actual construction occurs in the summer months when the new fiscal year funds
become available.
RECOMMENDATION:
It is recommended the City Council:
1. Accept the project improvements as constructed by CalPortland Construction in
accordance with the plans and specifications for the 2019 Concrete Repairs Project,
PW 2019-02;
2. Direct staff to file a Notice of Completion; and
3. Authorize release of retention, thirty-five (35) days after the Notice of Completion has
been recorded, if no liens have been filed.
BACKGROUND:
On June 11, 2019, the Council awarded a construction contract to perform the 2019
Concrete Repairs project to CalPortland Construction in the amount of $87,026.50 and
authorized the City Manager to approve change orders in the amount of $8,702.65 for a
Item 8.f. - Page 1
CITY COUNCIL
CONSIDERATION OF ACCEPTANCE OF THE 2019 CONCRETE REPAIRS
PROJECT, PW 2019-02
OCTOBER 8, 2019
PAGE 2
total amount of $95,729.15. The contractor’s final construction cost for this project is
$89,518.37.
The project consisted of the replacement of damaged/uplifted sidewalk adjacent to
mature trees throughout the Berry Gardens neighborhood, at two locations on Rodeo
Drive, at 310 North Halcyon Road, and the removal of seven trees to be replaced with
more appropriate species at a future date.
ANALYSIS OF ISSUES:
The contractor has completed the work in accordance with the approved plans and
specifications on schedule and within the available budget. There are no outstanding
issues. The project reduces potential trip and fall hazards along selected streets,
addresses complaints from the public, and improves access for individuals with mobility
limitations. The project helps protect existing City infrastructure by removing trees that
damage and uplift adjacent sidewalk panels. The project is consistent with the City
Council goal to support City infrastructure.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept the 2019 Concrete Repairs project;
2. Do not accept the project;
3. Accept the project but do not authorize release of retention; or
4. Provide direction to staff.
ADVANTAGES:
The project is complete and accepting the improvements will allow staff to close out the
project.
DISADVANTAGES:
No disadvantages have been identified.
ENVIRONMENTAL REVIEW:
No environmental review is needed to accept the project.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
Attachment:
1. Notice of Completion
Item 8.f. - Page 2
5(&25',1*5(48(67('%<
$1':+(15(&25'('5(785172
&,7<&/(5.
&,7<2)$552<2*5$1'(
(%5$1&+675((7
$552<2*5$1'(&$
127,&(2)&203/(7,21
127,&(,6+(5(%<*,9(17+$7
7KHXQGHUVLJQHGLVRZQHURUDJHQWRIRZQHURIWKHLQWHUHVWRUHVWDWHRUWKHSURSHUW\KHUHLQDIWHUGHVFULEHGDVVWDWHGEHORZ
7KH)8//1$0(RIWKH2:1(5LV
7KH)8//$''5(66RIWKH2:1(5LV
7KH1$785(2)7+(,17(5(67RU(67$7(RIWKHXQGHUVLJQHGLV
7+( )8// 1$0( DQG )8// $''5(66 RI $// 3(56216 LI DQ\ ZKR KROG VXFK LQWHUHVW RU HVWDWH ZLWK WKH
XQGHUVLJQHGDV-2,177(1$176RUDV7(1$176,1&20021DUH
1DPHV$GGUHVVHV
7+( )8// 1$0(6 DQG )8// $''5(66(6 RI WKH 35('(&(6625¶6 LQ LQWHUHVW RI WKH XQGHUVLJQHG LI WKH
SURSHUW\ZDV WUDQVIHUUHGVXEVHTXHQWWRWKHFRPPHQFHPHQWRIWKHZRUNRILPSURYHPHQWVKHUHLQUHIHUUHGWR
1DPHV$GGUHVVHV
$OOZRUNRILPSURYHPHQWRQWKHSURSHUW\KHUHLQDIWHUGHVFULEHGZDV&203/(7('RQ
7KH1$0(2)7+(25,*,1$/&2175$&725LIDQ\IRUVXFKZRUNRILPSURYHPHQWLV
7KHVWUHHWDGGUHVVRIVDLGSURSHUW\LV
7KHSURSHUW\RQZKLFKVDLGZRUNRILPSURYHPHQWZDVFRPSOHWHGLVLQWKH&LW\RI$UUR\R*UDQGH&RXQW\RI6DQ/XLV
2ELVSR6WDWHRI&DOLIRUQLDDQGLVGHVFULEHGDVIROORZV
9HULILFDWLRQRI121,1',9,'8$/RZQHU,WKHXQGHUVLJQHGGHFODUHXQGHUSHQDOW\RISHUMXU\XQGHUWKHODZVRIWKH6WDWHRI
&DOLIRUQLDWKDW,DPWKHBBBBBBBBBBBBBBBBBBBBBBBBRIWKHDIRUHVDLGLQWHUHVWRUHVWDWHLQWKHSURSHUW\GHVFULEHGLQWKH
DERYHQRWLFHWKDW,KDYHUHDGWKHVDLGQRWLFHWKDW,NQRZDQGXQGHUVWDQGWKHFRQWHQWVWKHUHRIDQGWKHIDFWVVWDWHGWKHUHLQ
DUHWUXHDQGFRUUHFW
BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB
BBBBBBBBBBBBB$UUR\R*UDQGH&DOLIRUQLD
(1'2)'2&80(17
'DWH
The City of Arroyo Grande
300 East Branch Street, Arroyo Grande, California 93420
in fee
None
None
09/04/2019
CalPortland Construction
Various Locations within the City of Arroyo Grande, CA
2019 Concrete Repairs, PW 2019-02
Public Works Director
Bill Robeson, Public Works Director
10/08/2019
ATTACHMENT 1
Item 8.f. - Page 3
THIS PAGE INTENTIONALLY LEFT BLANK
Item 8.f. - Page 4