CC 2020-11-24_08j Amendment to Agreements_Quincy_Filippin_Bridge Street Bridge MEMORANDUM TO: CITY COUNCIL FROM: BILL ROBESON, ASSISTANT CITY MANAGER/PUBLIC WORKS DIRECTOR BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER SUBJECT: CONSIDERATION TO APPROVE AN AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES WITH QUINCY ENGINEERING, INC., APPROVE AN AMENDMENT TO CONTRACT FOR CONSULTANT SERVICES WITH FILIPPIN ENGINEERING, INC., AND APPROVE A CORRESPONDING BUDGET AMENDMENT REQUEST IN THE AMOUNT OF $389,590 TO FUND 350-CAPITAL IMPROVEMENT PROGRAM FOR THE BRIDGE STREET BRIDGE REHABILITATION AND HABITAT MITIGATION PROJECTS DATE: NOVEMBER 24, 2020 SUMMARY OF ACTION: Approval of amendments to the existing Agreement with Quincy Engineering for additional construction engineering services and the existing Contract with Filippin Engineering, Inc. for additional construction management and inspection services for the Bridge Street Bridge Rehabilitation project; and approval of a budget adjustment to add additional Federal Highway Bridge Program (HBP) funds to the Capital Improvement Program budget for both the Bridge Street Bridge Rehabilitation and Habitat Mitigation projects. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: The City was successful in securing an additional $389,590 of Federal Highway Bridge Program (HBP) funds ($213,000 for the Rehabilitation project and $176,590 for the Habitat Mitigation project) which fully funds both projects. This will allow for the return of $166,060 of Local Sales Tax funds previously transferred to the Habitat Mitigation Project from the City’s Pavement Management Program budget. The total amount of HBP funding secured is $9,144,900 ($8,719,310 for the Rehabilitation Project and $425,590 for the Habitat Mitigation Project). Staff time will be necessary to coordinate construction activities with the contractor and consultants. RECOMMENDATION: It is recommended the City Council: 1) Approve a Tenth Amendment to the Agreement for Consultant Services ("Tenth Amendment") with Quincy Engineering, Inc. for additional construction engineering services; 2) Approve a Third Amendment to the Contract for Consultant Services ("Third Amendment") with Filippin Engineering, Inc. for additional construction management and inspection services; and 3) approve an amendment to the Fiscal Year 2020-21 Capital Improvement Program budget to add $389,590 of HBP funds to the Bridge Street Bridge Rehabilitation and Habitat Mitigation projects. Item 8.j. - Page 1 CITY COUNCIL CONSIDERATION TO APPROVE AN AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES WITH QUINCY ENGINEERING, INC., APPROVE AN AMENDMENT TO CONTRACT FOR CONSULTANT SERVICES WITH FILIPPIN ENGINEERING, INC., AND APPROVE A CORRESPONDING BUDGET AMENDMENT REQUEST IN THE AMOUNT OF $389,590 TO FUND 350-CAPITAL IMPROVEMENT PROGRAM FOR THE BRIDGE STREET BRIDGE REHABILITATION AND HABITAT MITIGATION PROJECTS NOVEMBER 24, 2020 PAGE 2 BACKGROUND OF PAST AMENDMENTS: Amendments 1 through 9 to Quincy Engineering Agreement On May 22, 2012, the Council approved an Agreement for Consultant Services with Quincy Engineering, Inc. for design phase services for the Bridge Street Bridge Rehabilitation project. Subsequently, nine amendments to the Agreement have been executed consisting of items such as reallocation of budgeted tasks within the overall contract, extension of the contract end date, and the addition of services such as utility relocation design and engineering support services during construction of the Bridge Street Bridge Rehabilitation and Habitat Mitigation projects. Amendments 1 and 2 to Filippin Engineering Contract On January 28, 2020, the Council approved a Contract for Consultant Services with Filippin Engineering, Inc. for construction management, resident engineer, inspection, material testing, and environmental monitoring services for the Bridge Street Bridge Rehabilitation project. Subsequently, two amendments to the Contract have been executed consisting of items such as preconstruction management, inspection and environmental services for the Rehabilitation Project, and construction management and inspection services for the Habitat Mitigation project. Amendment to the Capital Improvement Program Budget On October 13, 2020, the Council approved the transfer of $166,060 of Sales Tax funds from the Annual Pavement Management Program budget to fully fund the Bridge Street Bridge Habitat Mitigation project while staff concurrently applied for additional HBP funding. The application for additional HBP funding which was successful and a further budget adjustment is necessary to reflect this change. ANALYSIS OF ISSUES: Amendment to Quincy Engineering Agreement and Filippin Engineering Contract Due to several unforeseen and uncontrollable factors during the course of construction of the Rehabilitation project, the Quincy Engineering and Filippin Engineering teams are spending significantly more effort than what was included in their original scope of services. The efforts by Quincy Engineering include a higher than anticipated number of contractor requests for information (RFIs), shop plan reviews, and associated coordination primarily due to the inexperience of the contractor’s subcontractor responsible for detailing and fabricating the steel elements of the bridge. The efforts by Filippin Engineering include additional construction management, inspection and environmental monitoring services during contractor overtime hours, including weekend work, and an anticipated extended construction end date. These efforts are needed to Item 8.j. - Page 2 CITY COUNCIL CONSIDERATION TO APPROVE AN AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES WITH QUINCY ENGINEERING, INC., APPROVE AN AMENDMENT TO CONTRACT FOR CONSULTANT SERVICES WITH FILIPPIN ENGINEERING, INC., AND APPROVE A CORRESPONDING BUDGET AMENDMENT REQUEST IN THE AMOUNT OF $389,590 TO FUND 350-CAPITAL IMPROVEMENT PROGRAM FOR THE BRIDGE STREET BRIDGE REHABILITATION AND HABITAT MITIGATION PROJECTS NOVEMBER 24, 2020 PAGE 3 keep the project moving forward and to not further delay construction activities. The fee for these additional services is estimated to be $213,000 (Quincy Engineering $45,000 and Filippin Engineering $168,000) and will be reimbursed by HBP funds. Below is a summary of prior contract Amendments for both Quincy Engineering and Filippin Engineering on the Bridge Street Bridge Rehabilitation and Habitat Mitigation Projects: Rehabilitation Habitat Mitigation Total Quincy Engineering Original Contract 857,000.00 0.00 857,000.00 Amendment No. 1 39,895.19 0.00 39,895.19 Amendment No. 2 100,092.83 0.00 100,092.83 Amendment No. 3 0.00 0.00 0.00 Amendment No. 4 0.00 0.00 0.00 Amendment No. 5 39,585.65 0.00 39,585.65 Amendment No. 6 68,805.93 0.00 68,805.93 Amendment No. 7 0.00 0.00 0.00 Amendment No. 8 146,000.00 0.00 146,000.00 Amendment No. 9 0.00 22,800.00 22,800.00 Amendment No. 10 45,000.00 0.00 45,000.00 Subtotal 1,296,379.60 22,800.00 1,319,179.60 Filippin Engineering Original Contract 579,339.42 0.00 579,339.42 Amendment No. 1 135,874.74 0.00 135,874.74 Amendment No. 2 0.00 44,100.00 44,100.00 Amendment No. 3 168,000.00 0.00 168,000.00 Subtotal 883,214.16 44,100.00 927,314.16 Total 2,179,593.76 66,900.00 2,246,493.76 Amendment to the Capital Improvement Program Budget This month, the City was successful in securing an additional $389,590 of HBR funds to fully fund the Bridge Rehabilitation and Habitat Mitigation Projects. This will allow for the $166,060 of Sales Tax Funds to be returned to the Annual Pavement Management Program budget. Item 8.j. - Page 3 CITY COUNCIL CONSIDERATION TO APPROVE AN AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES WITH QUINCY ENGINEERING, INC., APPROVE AN AMENDMENT TO CONTRACT FOR CONSULTANT SERVICES WITH FILIPPIN ENGINEERING, INC., AND APPROVE A CORRESPONDING BUDGET AMENDMENT REQUEST IN THE AMOUNT OF $389,590 TO FUND 350-CAPITAL IMPROVEMENT PROGRAM FOR THE BRIDGE STREET BRIDGE REHABILITATION AND HABITAT MITIGATION PROJECTS NOVEMBER 24, 2020 PAGE 4 Below is a summary of the awarded HBP funding for the Projects: Current Additional Total Rehabilitation Construction 5,541,899 0 5,541,899 Construction Contingencies 554,110 0 554,110 Construction Engineering 914,401 213,000 1,127,401 Right-of-Way and Utilities 350,000 0 350,000 Preliminary Engineering 1,144,900 0 1,144,900 Subtotal 8,505,310 213,000 8,718,310 Habitat Mitigation Construction 250,000 67,419 (1) 317,419 Construction Contingencies 0 31,741 (1) 31,741 Engineering Services 0 22,800 (1) 22,800 Construction Management/Inspection 0 44,100 (1) 44,100 City Staff/Costs 0 10,530 10,530 Subtotal 250,000 176,590 426,590 Total 8,755,310 389,590 9,144,900 (1) $166,060 of Sales Tax Funds to be returned to the Annual Pavement Management Program budget. It is recommended that the City Council approve an amendment to the Fiscal Year 2020- 21 Capital Improvement Program budget to add $389,590 of HBP funds to the Bridge Street Bridge Rehabilitation and the Habitat Mitigation Projects and to return $166,060 of Sales Tax Funds to the Annual Pavement Management Program budget. ALTERNATIVES: The following alternatives are provided for the Council’s consideration: 1. Approve staff’s recommendations; 2. Do not approve staff’s recommendations and request further information; 3. Modify staff’s recommendation and approve; or 4. Provide direction to staff. Item 8.j. - Page 4 CITY COUNCIL CONSIDERATION TO APPROVE AN AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES WITH QUINCY ENGINEERING, INC., APPROVE AN AMENDMENT TO CONTRACT FOR CONSULTANT SERVICES WITH FILIPPIN ENGINEERING, INC., AND APPROVE A CORRESPONDING BUDGET AMENDMENT REQUEST IN THE AMOUNT OF $389,590 TO FUND 350-CAPITAL IMPROVEMENT PROGRAM FOR THE BRIDGE STREET BRIDGE REHABILITATION AND HABITAT MITIGATION PROJECTS NOVEMBER 24, 2020 PAGE 5 ADVANTAGES: Approval of the contract amendments will allow for continuing construction phase consultant services necessary to oversee the completion of the Bridge Street Bridge Rehabilitation and Habitat Mitigation projects. Approval of the amendment to the Fiscal Year 2020-21 Capital Improvement Program will add HBP funds to fully fund the Bridge Street Bridge Rehabilitation and Habitat Mitigation Projects and will return $166,060 of Sales Tax Funds to the Annual Pavement Management Program budget. Bringing the Bridge Street Bridge up to standard loading conditions will remove the 3-ton maximum load limit and will allow school buses and fire and delivery trucks to utilize Bridge Street as a route. DISADVANTAGES: None Identified at this time. ENVIRONMENTAL REVIEW: Caltrans, as lead agency, has determined that the project is categorically excluded from the requirements to prepare and Environmental Assessment (EA) or Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA) pursuant to 23 CFR 771.117(d): activity (d)(13) covering bridge rehabilitation that avoids an adverse effect to historic properties under the National Historic Preservation Act. The City, as lead agency, has adopted a Mitigated Negative Declaration (MND) prepared in accordance with the California Environmental Quality Act (CEQA), Public Resources Code §21000 et seq., and the State CEQA Guidelines, California Code of Regulations (CCR) §15000 et seq. for the Bridge Street Bridge Rehabilitation and Habitat Mitigation Projects. PUBLIC NOTIFICATION AND COMMENTS: The Agenda was posted at City Hall and on the City’s website in accordance with Government Code Section 54954.2. Item 8.j. - Page 5 CONSULTANT SERVICES AGREEMENT AMENDMENT NO. 10 This Tenth Amendment ("Tenth Amendment") to Consultant Services Agreement (“CSA”) by and between the CITY OF ARROYO GRANDE (“City”) and QUINCY ENGINEERING, INC. (“Consultant”) is made and entered into this day of 2020. WHEREAS, the parties entered into a CSA dated May 22, 2012, for preliminary engineering work on the Bridge Street Bridge Improvement project; and WHEREAS, the First Amendment to the CSA was approved on May 27, 2014, which included an increase in scope and fee to perform additional analysis and more detailed costs estimates as requested by Caltrans to determine funding eligibility of the rehabilitation alternative; and WHEREAS, the Second Amendment to the CSA was approved on January 27, 2015, which included an increase in scope and fee to carry two design alternatives through the environmental process of Phase I, and to complete Phase II - Final Design Plans, Specifications and Estimates (PS&E) and Permitting, and extended the agreement term; and WHEREAS, the Third Amendment to the CSA was approved on July 18, 2016, which included a no cost change for extra work required to complete the project by a reallocation within the existing budget; and WHEREAS, the Fourth Amendment to the CSA was approved on March 16, 2017, which included a no cost change for extra work required to complete the project by a reallocation within the existing budget; and WHEREAS, the Fifth Amendment to the CSA was approved on July 27, 2017, which included an increase in scope and fee to prepare an alternatives evaluation and preliminary cost estimates for the permanent waterline relocation and temporary/ permanent relocation of the existing sanitary sewer crossing Arroyo Grande Creek for grant programming purposes; and WHEREAS, the Sixth Amendment to the CSA was approved on March 13, 2018, which allowed for the design of both temporary and permanent utility relocations required as part of the project, and extended the agreement term; and WHEREAS, the Seventh Amendment to the CSA was approved on August 13, 2019, which extended the agreement term and included a no cost change for extra work required to complete construction documents by a reallocation within the existing budget; and Item 8.j. - Page 6 WHEREAS, the Eight Amendment to the CSA was approved on October 8, 2019, which included an increase in scope and fee to perform design support services during the construction phase of the Bridge Street Bridge Rehabilitation Project; and WHEREAS, the Ninth Amendment to the CSA was approved on August 25, 2020, which included an increase in scope and fee to perform engineering services for the Bridge Street Bridge Habitat Mitigation Project. WHEREAS, the parties desire to further modify the CSA as set forth herein. NOW THEREFORE, for valuable consideration the receipt and sufficiency of which is acknowledged, the parties agree as follows: 1. To include the additional services at the increased cost as specified in Exhibit “A” attached hereto and incorporated herein by this reference. 2. Except as modified herein, all other terms and conditions set forth in the CSA, as amended, shall remain unchanged. IN WITNESS WHEREOF, CITY and CONSULTANT have executed this Tenth Amendment the day and year first above written. CITY OF ARROYO GRANDE CONSULTANT By: By: Caren Ray Russom, Mayor Mark Reno, Principal Attest: Approved As To Form: Kelly Wetmore, City Clerk Timothy J. Carmel, City Attorney Item 8.j. - Page 7 www.quincyeng.com | 11017 Cobblerock, Drive Suite 100 | Rancho Cordova, CA 95670 | P: 916.368.9181 | F: 916.368.1308 Jill McPeek October 28, 2020 Capital Improvement Project Manager City of Arroyo Grande Department of Community Development 300 East Branch Street Arroyo Grande, CA 93420 Re: Bridge Street Bridge Rehabilitation Project in Arroyo Grande Amendment 10 – Additional Construction Support Services Dear Ms. McPeek, As has been discussed with the City, and documented in invoices/monthly summary reports, the Quincy Team has had to expend significantly more effort in supporting the City and CM Team. These efforts can be attributed to a very in-experienced subcontractor who was responsible for detailing and fabricating the steel elements of this project. The Quincy Team took proactive measures to schedule and participate in teleconference meetings, sharing of CAD information and preliminary review of documents in order to attempt to meet the Contractor and Environmental schedule. However, numerous revisions to shop plans, additional RFIs and general support time has been required to accomplish this. We understand that the City along with the CM Team may implement an administration deduction in order to recapture funds from the Contractor to cover these additional construction support services since these efforts are directly related to non- performance of the Contractor’s subconsultant. It is also our understanding that the City has approached Caltrans for additional Highway Bridge Program (HBP) funds to cover these additional services. The additional construction support services can be broken down into the following two tasks: Task 28 – Additional Construction Support As a result of a higher than anticipated number for Contractor Request For Information (RFI) and the necessary coordination with the CM Team, City and Contractor, the number of hours has exceeded what was anticipated in the original scope of work. This has resulted in additional emails, documentation, phone calls and collaboration with the City and CM Team. These proposed amendment hours reflect efforts beyond the original scope. Task 29- Additional Submittals The original assumption for our anticipated level of effort was based on providing two (2) reviews of the steel shop plans. To date we have been called upon to complete up to seven (7) reviews of various shop plans. Often finding new mistakes, or nuances in the submittals, which were not present in the previous submittals. Only by actively coordinating CAD files and discussing discrepancies has there been progress towards finally approving these shop plans, but at nearly 3 times the effort. These hours document these efforts. As we have discussed, some of these additional efforts to date have been covered by reallocating budgets from other tasks to cover the work now and keep the reviews and response timely for EXHIBIT A Item 8.j. - Page 8 | Page 2 of 2 the contractor. So, though this amendment discusses the additional efforts for Task 28 and 29, these funds will be used to reallocate back to other tasks to complete the scope of work. Please give me a call to discuss any questions or comments you may have on this proposed amendment. We can adjust meetings or assumed level of efforts. I can be reached at (916) 368- 9181. Sincerely, Quincy Engineering, Inc. Mark L. Reno, P.E. Project Manager Cc: File Item 8.j. - Page 9 Cost Proposal Supplemental Construction Support Services Date: 10/26/2020 Quincy Engineering, Inc. Direct Labor:$14,957.50 Estimated Salary Increases for Multi-Year Project $0.00 Subtotal $14,957.50 Overhead (1.731):$25,891.43 A. Labor Subtotal $40,848.93 Subconsultant Costs: 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 0 $0.00 B. Subconsultant Subtotal $0.00 Other Direct Costs: Travel (@ active IRS mileage rate)0 miles @ $0.575 $0.00 Pier Diem/ Hotel 0 days @ $150.00 $0.00 Delivery 0 @ $20.00 $0.00 Vendor Reproduction Vellum @ $0.00 81/2 X 11 Reproduction @ $0.00 11 X 17 Reproduction @ $0.00 Mounting Boards for Presentations @ $0.00 Newsletters (Translation and printing)@ $0.00 Subtotal Vendor Reproduction $0.00 Title Report @ $0.00 Miscellaneous C. Other Direct Cost Subtotal:$0.00 Labor Subtotal A. =$40,848.93 Fixed Fee (10.0%):$4,084.89 Subconsultant Subtotal B. =$0.00 Fixed Fee (0.0%):$0.00 Other Direct Cost Subtotal: C. =$0.00 Fixed Fee (0.0%):$0.00 TOTAL =$44,933.83 Say $45,000.00 Note: Invoices will be based upon actual QEI hourly rates plus overhead at 173.1% plus prorated portion of fixed fee. Subconsultant and Direct Costs will be billed at actual cost. The overhead rate (ICR) shall remain fixed for the contract duration or until both parties agree to modify the rate in writing. Bridge Street Bridge Bridge Street Bridge Amendment #10 20201026 Project 1 Budget Item 8.j. - Page 10 Cost Proposal TASKS Principal Eng.Principal Eng.Senior Eng.Senior Eng.Assist Eng. IInternInternQuincy Total HoursQuincy Total Labor DollarsQuincy LaborQuincy ProfitQuincy NLF BudgetSubconsultant SubtotalBL MR GY RS Aha AJ Bko Direct Labor Labor+OH Multiplier Fee Multiplier Actual Labor Multiplier No.Initial Hourly Rate $112.98 $110.00 $80.00 $80.00 $34.65 $20.00 $20.00 2.731 10%3.004 0 $0 28 Additional Construction Support 8 10 18 $1,680 $4,588 $458.81 $5,047 $0 29 Additional Submittals 40 40 150 52 32 314 $13,278 $36,261 $3,626.09 $39,887 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 0 $0 $0 $0.00 $0 $0 $0 $0 Subtotal- Hours 0 8 50 40 150 52 32 332 $14,957.50 $40,848.93 $4,084.89 $44,933.83 0 Estimated Salary Increases for Multi-Year Project $0.00 $0.00 $0.00 $0.00 Other Direct Costs $0.00 0Total Cost $0 $880 $4,000 $3,200 $5,198 $1,040 $640 $14,958 $14,958 $40,849 $4,085 $44,934 $0 $0 Supplemental Construction Support Services Project Name: Bridge Street Bridge Bridge Street Bridge Amendment #10 20201026 Project 1 Hrs 10/27/2020 Item 8.j. - Page 11 Local Assistance Procedures Manual EXHIBIT 10-H Cost Proposal X Prime Consultant Subconsultant Consultant Project Name Project No. Contract No. Date 10/26/2020 Name Initials Hours Total Brent Lemon BL 0 112.98$ -$ *Mark Reno MR 8 110.00$ 880.00$ *Greg Young GY 50 80.00$ 4,000.00$ Rodney Simmons RS 40 80.00$ 3,200.00$ Ashley Hansen Aha 150 34.65$ 5,197.50$ Anna Johnson AJ 52 20.00$ 1,040.00$ Boris Kotsyubuk Bko 32 20.00$ 640.00$ 332 14,957.50$ LABOR COSTS a) b) (see calculation page attached) c) TOTAL DIRECT LABOR COSTS [(a) + (b)] $14,957.50 INDIRECT COSTS d)e) Total Fringe Benefits [(c) x (d)] $6,434.72 f)g) Overhead [(c) x (f)] $19,456.72 h)i) Gen & Admin [(c) x (h)] $0.00 j) TOTAL INDIRECT COSTS [(e) + (g) + (i)] $25,891.43 FIXED FEE k)l) TOTAL FIXED FEE [(c) + (j)] x (k) $4,084.89 CONSULTANT'S OTHER DIRECT COSTS (ODC) Travel (@ active IRS mileage rate)miles @ $0.00 Pier Diem/ Hotel days @ $0.00 Delivery 0 @ $0.00 Vendor Reproduction Vellum @ $0.00 81/2 X 11 Reproduction @ $0.00 11 X 17 Reproduction @ $0.00 Mounting Boards for Presentations @ $0.00 Newsletters (Translation and printing)@ $0.00 Subtotal Vendor Reproduction $0.00 Title Report 0 @ $0.00 Miscellaneous $0.00 m) TOTAL OTHER DIRECT COSTS $0.00 $0.00 n)SUBCONSULTANT COSTS (attach detailed cost proposal for each subconsultant ) 0 0 0 0 0 0 0 0 0 $0.00 o) TOTAL COST [(c) + (j) + (l) + (m) + (n)] NOTES: 1.Key personnel marked with an asterisk (*). 2.Employees subject to prevailing wage marked with two asterisks (**). 3.Anticipated salary increases calculation (Item"b") on attached page. 4.Note: Invoices will be based upon actual QEI hourly rates plus overhead at 173.1% plus prorated portion of fixed fee. Subconsultant and Direct Costs will be billed at actual cost. The overhead rate (ICR) shall remain fixed for the contract duration or until both parties agree to modify the rate in writing. $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0 N/A Exhibit 10‑H1 Cost Proposal Actual Cost-Plus-Fixed Fee Contracts Subtotal Direct Labor Costs DIRECT LABOR Classification/Title Principal Eng. Principal Eng. Senior Eng. Senior Eng. Bridge Street Bridge $44,933.83 Overhead (Rate: 130.08%): General Administration (Rate: 0.0%): $14,957.50 $0.00Estimated Salary Increases for Multi-Year Project $0.00 $0.00 Intern Initial Hourly Rate $0.575 $150.00 $20.00 $0.00 Quincy Engineering, Inc. Fixed Fee (10.0%): Assist Eng. I Intern Range $70-$120 $70-$120 $50-$100 $50-$100 $26-$46 $16-$25 $16-$25 Fringe Benefits (Rate: 43.02%): Bridge Street Bridge Amendment #10 20201026 LAPM 10-H 10/27/2020 Item 8.j. - Page 12 Local Assistance Procedures Manual Exhibit 10-H PAGE 2 OF 2 Consultant Contract No. N/A Date 10/26/2020 1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours) Avg Hourly 5 Year Contract Rate Duration $ 14,957.50 =$45.05 Year 1 Avg Hourly Rate Proposed Escalation = Avg Hourly Rate Year 1 $45.05 +=$46.18 Year 1 Avg Hourly Rate Year 2 $46.18 +=$48.49 Year 2 Avg Hourly Rate Year 3 $48.49 +=$50.91 Year 3 Avg Hourly Rate Year 4 $50.91 +=$53.46 Year 4 Avg Hourly Rate Year 5 $53.46 +=$56.13 Year 5 Avg Hourly Rate Total Hours per Year Year 1 100.00%*=332.0 Estimated Hours Year 1 Year 2 0.00%*=0.0 Estimated Hours Year 2 Year 3 0.00%*=0.0 Estimated Hours Year 3 Year 4 0.00%*=0.0 Estimated Hours Year 4 Year 5 0.00%*=0.0 Estimated Hours Year 5 Total 100%=332.0 Year 1 $45.05 *=$14,957.50 Estimated Hours Year 1 Year 2 $46.18 *=$0.00 Estimated Hours Year 2 Year 3 $48.49 *=$0.00 Estimated Hours Year 3 Year 4 $50.91 *=$0.00 Estimated Hours Year 4 Year 5 $53.46 *=$0.00 Estimated Hours Year 5 =$14,957.50 =$14,957.50 =$0.00 Transfer to Page 1 NOTES: • This assumes that an average of one half year will be worked at the rate on the cost proposal. 332 ACTUAL COST-PLUS-FIXED FEE CONTRACTS (CALCULATIONS FOR ANTICIPATED SALARY INCREASES) Quincy Engineering, Inc. Bridge Street Bridge Direct Labor Subtotal Total Hours per Cost Proposal per Cost Proposal Estimated % Total Hours 2. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %) Proposed Escalation 2.5% 5.0% 5.0% 5.0% 5.0% 5.0% 3. Calculate estimated hours per year (Multiply estimate % each year by total hours) Estimated hours Cost per Year(calculated above)(calculated above) Completed Each Year per Cost Proposal 332.0 332.0 332.0 332.0 Direct Labor Subtotal before Escalation Estimated total of Direct Labor Salary Increase EXHIBIT 10-H1 COST PROPOSAL 332 0 0 0 0 Total Direct Labor Cost with Escalation 332.0 Total 4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours) Avg Hourly Rate LPP 15-01 January 14, 2015 Item 8.j. - Page 13 _ Local Assistance Procedures Manual EXHIBIT 10-H1 Cost Proposal EXHIBIT 10-H 1 COST PROPOSAL Page 3 of 3 Certification of Direct Costs: I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal{s) in this contract are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements: 1.Generally Accepted Accounting Principles {GAAP) 2.Terms and conditions of the contract 3.Title 23 United States Code Section 112 -Letting of Contracts 4.48 Code of Federal Regulations Part 31 -Contract Cost Principles and Procedures 5.23 Code of Federal Regulations Part 172 -Procurement, Management, and Administration of Engineering and Design Related Service 6.48 Code of Federal Regulations Part 9904 - Cost Accounting Standards Board {when applicable) All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files and be in compliance with applicable federal and state requirements. Costs that are noncom pliant with the federal and state requirements are not eligible for reimbursement. Local governments are responsible for applying only cognizant agency approved or Caltrans accepted Indirect Cost Rate{s). Prime Consultant or Subconsultant Certifying: Name: ______________ _ Title*: Signature: ____ _ _ ____ __ ____ _ Date of Certification {mm/dd/yyyy): _ Email: ______ ______ __ _ Phone Number: Address: ________________________________ _ *An individual executive or financial officer of the consultant's or subconsultant's organization at a level no lower than a Vice President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish the cost proposal for the contract. List services the consultant is providinq under the proposed contract: Page 3 of 9 January 2020 Item 8.j. - Page 14 CONTRACT FOR CONSULTANT SERVICES AMENDMENT NO. 3 This Third Amendment ("Third Amendment") to Contract for Consultant Services (“Contract”) by and between the CITY OF ARROYO GRANDE and FILIPPIN ENGINEERING, INC. (“Consultant”) is made and entered into this day of 2020. WHEREAS, the parties entered into a Contract dated January 29, 2020, for construction management, resident engineer, inspection, materials testing, and environmental services for the Bridge Street Bridge Rehabilitation Project; and WHEREAS, the First Amendment to the Contract was approved on July 14, 2020, which included an increase in scope and fee to perform additional construction management and environmental services necessary to move the project forward into construction; and WHEREAS, the Second Amendment to the Contract was approved on August 25, 2020, for construction management, resident engineer, inspection, and environmental services for the Bridge Street Bridge Habitat Mitigation Project; and WHEREAS, the parties desire to further modify the Contract as set forth herein. NOW THEREFORE, for valuable consideration the receipt and sufficiency of which is acknowledged, the parties agree as follows: 1. To include the additional services at the increased cost as specified in Exhibit "A" attached hereto and incorporated herein by this reference. 2. Except as modified herein, all other terms and conditions set forth in the Contract, as amended, shall remain unchanged. IN WITNESS WHEREOF, the parties hereto have caused this Third Amendment to be executed the day and year first above written. CITY OF ARROYO GRANDE CONSULTANT By: By: Caren Ray Russom, Mayor Gino Filippin, President Attest: Approved As To Form: Kelly Wetmore, City Clerk Timothy J. Carmel, City Attorney Item 8.j. - Page 15 November 10, 2020 W.O. 194101 City of Arroyo Grande Attn: Jill McPeek 1375 Ash Street Arroyo Grande, CA 93420 (transmitted via email) SUBJECT: REQUEST FOR AUTHORIZATION OF EXTRA SERVICES FOR CMIT SERVICES, BRIDGE STREET BRIDGE REPLACEMENT PROJECT Dear Ms. McPeek, Filippin Engineering, Inc. (FE) is submitting this Request for Additional Authorization to provide additional Construction Management and Inspection Services (CMIT) to the City of Arroyo Grande for the Bridge Street Bridge Replacement project, due to Contractor delays in performing the work per the approved baseline schedule and Contractor work acceleration (extended hours and weekend work) through the first fifteen weeks of the construction phase; and the currently estimated two months of contract prolongation post the current contract completion date. An analysis of addition staff time requested is attached on the following page. Our work analysis shows average hours per week per our proposal and based on that usage what we anticipated spending during the first 15 weeks of the construction phase (thru Friday 9/11). Next is the time actually spent during the construction phase (for the same period); additional costs during this period were due primarily to Granite’s attempt to accelerate the project schedule via overtime during the regular week and weekend work. Additional costs during this period were roughly FE $38k, ATS, ES, and Rincon (estimate) $16K for a total of $54K during the first 15 weeks of construction. In addition, we’ve included estimates for additional service during Jan & Feb of 2021 (the time Granite estimates it will take to complete the project). This period is approx. 2 months; we have based our estimate on the same time consumption rate in our original proposal. Cost for service during this period (1/1/21 to 2/28/21) are estimated to be FE $93k, ES and Rincon $21k for a total of roughly $114k. Total estimated additional services for work under this authorization request are $54K for contract acceleration (NTP to 9/11/20) + $144K for 2 months of contact prolongation(Jan & Feb 2021) = making the grand total of our additional authorization request = $168K. If you have any questions, please do not hesitate to call, (805) 729-0041. Sincerely, FILIPPIN ENGINEERING Gino Filippin, P.E. President RCE 57254 EXHIBIT A Item 8.j. - Page 16 BRIDGE STREET BRIDGE ‐ ADDITIONAL AUTHORIZATION REQUEST NO.3Rate Tot hours during 29 wks of cstr phaseAve. hours per week during cstr phaseBudget hrs for 15 wksActual hrs for 15 wks @ straight timeActual OT hrs during 15 wks @ 1.5 straight timeBudget cost for 15 wksActual cost for 15 wksContract Acceleration cost during first 15 wks of the cstr phase anticipated additional time to contract completion dateContract Prolongation      8 weeks during Jan & Feb 2021Resident Engineer (RE)227.69$            2368.14 122.072470 27,793.88$       56,239.43$       28,445.55$       0 14,823.40$       Assistant RE149.91$            733 25.28 379.143364 56,836.57$       51,149.29$       (5,687.28)$        0 30,312.84$       Senior Inspector147.30$            1164 40.14 602.0758274 88,684.76$       99,898.86$       11,214.10$       0 47,298.54$       Office Engineer51.64$              752.59 38.791270 2,003.28$         6,558.28$         4,555.00$         0 1,068.41$         FE Totals175,318.48$    213,845.86$    38,527.38$       ‐$ 93,503.19$       ATS5,000.00$         ‐$ Earth Systems5,000.00$         3,000.00$         Rincon6,000.00$         18,000.00$       TOTALS54,527.38$      ‐$                  114,503.19$    Item 8.j. - Page 17 THIS PAGE INTENTIONALLY LEFT BLANK