CC 2021-02-09_06b City Manager Communications_PP Presentation
1
2
3
New 36” HDPE
Ex. Failing 30”CMP
Surface flow
4
Approx.: 2.2 miles of CMP
To reline the entire 2.2 miles=
Approx. $5.5 to $6 million
$45,000 annually budgeted
To wait until failure – 3 times
the cost on average
A 5 year program can be
considered in anticipation of a future
funding source
5
6
7
New 36” HDPE
Ex. Failing 30”CMP
Surface flow
8
9