CC 2021-04-27_11b Streets Selection_2021 Street Repairs projectMEMORANDUM
TO: CITY COUNCIL
FROM: BILL ROBESON, ASSISTANT CITY MANAGER/PUBLIC WORKS
DIRECTOR
BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER
SUBJECT: CONSIDERATION OF STREETS SELECTION FOR THE 2021 STREET
REPAIRS PROJECT, PW 2021-01
DATE: APRIL 27, 2021
SUMMARY OF ACTION:
Review and select streets to be included in the 2021 Street Repairs Project.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
A total of $1,843,037 is available for the Pavement Management Program budget in FY
2020-21, consisting of $63,000 of Urban State Highway Account (USHA) funds, $307,200
of Senate Bill 1 (SB1) monies, and $1,472,837 of Local Sales Tax funds. Of the overall
budget, it is estimated $1,408,300 will be used for construction and $140,776 for
construction contingencies. The remaining $293,961 will be used to pay for engineering,
testing, design specifications, and final retention payment to the contractor of last year’s
project. This type of payment is held for 35 days to ensure all liens are cleared, due to
the timeframe of this payment, the payment crossed over last year’s fiscal year into the
current fiscal year.
RECOMMENDATION:
It is recommended the City Council review the potential streets for the 2021 Street Repairs
Project and select Option 2 - Correct Base Failures (Digouts) and Alligator Cracking.
BACKGROUND:
On April 10, 2018, the City Council reviewed treatment options for the 2018 Street Repairs
project (James Way) and selected Alternative 1 - Digouts and Overlay, as the preferred
alternative. For this alternative, is was estimated that 2-1/2 years of the City’s Pavement
Management Program budget would be dedicated to James Way. As follow-up to
Council’s action, the digouts were completed in Summer 2018 and the curb ramps and
overlay were scheduled to be performed in the subsequent years (e.g., 2019 and 2020).
However, due to ongoing deterioration and the winter rains of 2019, two vital arterials,
West Branch Street and Traffic Way, reached a critical point of deterioration that would
have moved into a full “reconstruction category” without immediate repairs to multiple
segments. In response, on June 11, 2019, Council approved digout improvements on
Item 11.b. - Page 1
CITY COUNCIL
CONSIDERATION OF STREETS SELECTION FOR THE 2021 STREET REPAIRS
PROJECT, PW 2021-01
APRIL 27, 2021
PAGE 2
West Branch Street and Traffic Way and delayed the curb ramps and overlay on James
Way based on the fact that the digouts previously completed were effective and could
hold up another year or two without deteriorating while awaiting a full overlay treatment.
In addition, Council approved refreshed striping on James Way while it awaits an overlay.
In consideration of upcoming years of streets repair (2022, 2023, 2024), staff may
continue to recommend delaying the overlay treatment step at James Way due to other
more critical conditions that are occurring on other street segments.
ANALYSIS OF ISSUES:
Staff and the City’s pavement design engineering consultant, Pavement Engineers Inc.
(PEI) have analyzed James Way, West Branch Street, and Traffic Way and found that
the digouts previously completed remain effective and will defer significant deterioration
while awaiting a top surface overlay treatment. Based on this, staff and its pavement
design engineering consultant suggest that continuing to correct base failures (digouts)
is the best course of action for the 2021 Street Repairs Project and the best way to stretch
the available budget and slow the deterioration of certain streets to help avoid near-term
reconstruction.
The following factors are used by City’s Public Works Streets Division staff and the City’s
pavement design engineering team to prioritize street segments for repair:
- visual observations of street conditions
- assessment of safety issues caused by asphalt conditions
- most heavily traveled streets (degree and intensity of use)
- cost of deferring maintenance (focused structural digouts versus full replacement and
reconstruction) based on annual funding allocations
- frequency of street maintenance issues (cost and time commitment)
The streets listed below were found to be in the most urgent condition based on multiple
observations and assessments:
Street Segment From To
Valley Road Sunrise Terrace Los Berros Creek Bridge
Corbett Canyon Road Route 227 City Limits (n/o Gularte Rd)
Fair Oaks Avenue South Halcyon Road Fred Grieb Bridge
Wesley Street End of Street (n/o of Larchmont Dr) West Branch Street
Vernon Street End of Street (n/o of Larchmont Dr) West Branch Street
East Grand Avenue Halcyon Road El Camino Real
North Halcyon Road El Camino Real East Grand Avenue
South Elm Street Ash Street City Limits (s/o Paul Place)
Rancho Parkway James Way West Branch Street
Item 11.b. - Page 2
CITY COUNCIL
CONSIDERATION OF STREETS SELECTION FOR THE 2021 STREET REPAIRS
PROJECT, PW 2021-01
APRIL 27, 2021
PAGE 3
In order to determine the structural adequacy of the pavement of these nine streets,
deflection testing and core sampling was performed by the City’s design engineer.
Through this work, it was found that the streets have differing degrees of structural
deficiencies and that $13,000,000 would be needed to fully rehabilitate (replacement and
reconstruction) the pavement on all nine streets. Current budget levels do not allow full
rehabilitation so the “spot treatment maintenance” option, also known as digout
segments, was evaluated with the intention of providing the highest estimated service life
while stretching the amount of the available budget.
Two maintenance options are considered appropriate options for these streets:
- Option 1 – Correct Base Failures (Digouts) Only
- Option 2 – Correct Base Failures (Digouts) and Alligator Cracking (which progresses
to base failure)
Based on the available budget of $1.4M for construction, it is estimated that the following
streets and repairs can be accomplished under each Option.
Option 1 - Correct
Base Failures Only
(Digouts)
Option 2 - Correct
Base Failures
(Digouts)
and Alligator Cracking
Street Segment Expected Service Life
3 - 5 Years
Expected Service Life
5 - 7 Years
Valley Rd - Sunrise Terrace to Bridge $ 113,000 $ 149,000
Corbett Cyn Rd - Rte 227 to City Limits 183,000 184,000
Fair Oaks Ave - S Halcyon to Bridge 167,000 230,000
Wesley Street - End Street to W Branch 79,000 95,000
Vernon Street - End Street to W Branch 91,000 132,000
S Elm Street - The Pike to City Limits 64,000 166,000
E Grand Ave - Halcyon to ECR 289,000 382,000
N Halcyon Rd - ECR to E Grand Ave 230,000 351,000
S Elm Street - Ash St to Farroll Ave 330,000 525,000
S Elm Street - Farroll Ave to The Pike 37,000 162,000
Rancho Pkwy - James Wy to W Branch 489,000 713,000
Total $ 1,216,000 $ 1,338,000
Option 1 treats more streets but results in shorter service life for the treated streets, while
Option 2 treats less streets but provides longer service life for the treated streets. Based
on available funding and the goal of extending the service lives of the treated streets, staff
recommends selecting Option 2. Although the number of streets repaired will be less, this
Item 11.b. - Page 3
CITY COUNCIL
CONSIDERATION OF STREETS SELECTION FOR THE 2021 STREET REPAIRS
PROJECT, PW 2021-01
APRIL 27, 2021
PAGE 4
option will provide longer service life and more extensive repairs on these heavily used
streets. This approach will allow the City to focus on and support these streets rather than
spreading out more minimal asphalt treatments.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Approve staff’s recommended treatment of Option 2 - Correct Base Failures
(Digouts) and Alligator Cracking; or
2. Approve Option 1 - Correct Base Failures Only (Digouts); or
3. Direct Staff to investigate other potential streets; or
4. Provide other direction to staff.
ADVANTAGES:
Utilizing the Option 2 approach will provide longer service life due to the more extensive
repairs.
DISADVANTAGES:
Selection of either option reduces available funding for other needed street maintenance
projects.
ENVIRONMENTAL REVIEW:
The project is categorically exempt from the California Environmental Quality Act (CEQA)
pursuant to CEQA Guideline Section 15301(c) covering the repair and maintenance of
existing streets, sidewalks, gutters and similar facilities.