CC 2024-08-13_09j Accept the Swinging Bridge Retrofit ProjectItem 9.j.
MEMORANDUM
TO: City Council
FROM: Bill Robeson, Assistant City Manager/Public Works Director
BY: Shannon Sweeney, City Engineer
SUBJECT: Accept the Swinging Bridge Retrofit Project, PW 2021-06
DATE: August 13, 2024
RECOMMENDATION:
1) Accept improvements as constructed by Cushman Contracting Corporation, in
accordance with the plans and specifications for the Swinging Bridge Retrofit Project, PW
2021-06;
2) Direct staff to file a Notice of Completion; and
3) Authorize release of retention thirty-five (35) days after the Notice of Completion has
been recorded if no liens have been filed.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
The final contract and change orders totaled $959,996.35. Field change orders
(contingency costs) of $22,996.35, approximately 2.5%, were expended on this project to
address north fence coating and bridge fencing improvements, both items that we re
deemed necessary but were not included in the original drawings. The original contract
price was $937,000 with a 10% contingency of $93,700.
$500,000 of this project was funded through a federal earmark under the “Community
Project Funding/Congressionally Directed Spending” (CPF/CDS) program, and the
remainder of the project was funded with Measure O 2006 funds.
The project was completed within budget and ahead of schedule.
BACKGROUND:
On January 9, 2024, the City awarded a construction contract for the 2021 Swinging
Bridge Retrofit Project, PW 2021-06 to Cushman Contracting Corporation in the amount
of $937,000.
The project was deemed substantially complete on August 1, 2024.
Page 163 of 218
Item 9.j.
City Council
Accept the Swinging Bridge Retrofit Project, PW 2021-06
August 13, 2024
Page 2
ANALYSIS OF ISSUES:
This unique and iconic bridge provides safe pedestrian travel to and from the gazebo in
Olohan Alley at the former Short Street (Centennial Park) and Heritage Park. It is well-
loved by residents and is a popular tourist attraction because of its unique design and
span over Arroyo Grande Creek.
The 2021 Swinging Bridge Retrofit Project involved constructing structural improvements,
including new anchor points and abutments, and aesthetic improvements, including
coating and decking replacement.
The 2021 Swinging Bridge Retrofit Project was substantially completed to City staff’s
satisfaction on August 1, 2024. No punch list items remained at that time.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept the 2021 Swinging Bridge Retrofit Project and authorize release of
retention;
2. Do not accept the project;
3. Accept the project but do not authorize the release of retention; or
4. Provide other direction to staff.
ADVANTAGES:
The project is substantially complete and accepting the improvements allows staff to close
out the project. Retrofit of the Swinging Bridge removes the 5-person maximum weight
limit and provides a safe non-motorized crossing of Arroyo Grande Creek.
DISADVANTAGES:
No disadvantages have been identified in accepting this project.
ENVIRONMENTAL REVIEW:
The 2021 Swinging Bridge Retrofit Project was previously determined to be categorically
exempt from the California Environmental Quality Act (“CEQA”) under the Class 2
exemption, which applies to the replacement or reconstruction of existing structures and
facilities where the new structure will be located on the same site as the structure replaced
and will have substantially the same purpose and capacity as the structure replaced.
(State CEQA Guidelines, § 15302.)
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.
ATTACHMENTS:
1. Notice of Completion – 2021 Swinging Bridge Retrofit Project
Page 164 of 218
RECORDING REQUESTED BY
AND WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF ARROYO GRANDE
300 EAST BRANCH STREET
ARROYO GRANDE, CA 93420
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
1.The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below.
2.The FULL NAME of the OWNER is: ....:..:Th=e"----C=ity'-=o(._,A-=-=r-=-r,._oy=·o'-G.......,ra:::.,;n=d=e ____________________ _
3.The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420
4.The NATURE OF THE INTEREST or ESTATE of the undersigned is: _z�·n�ee ________________ _
5.THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as
JOINT TENANTS or as TENANTS IN COMMON are:
None
NAMES ADDRESSES
6.THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR'S in interest of the undersigned if the property was
transferred subsequent to the commencement of the work of improvements herein referred to:
None
NAMES ADDRESSES
7.All work of improvement on the property hereinafter described was COMPLETED _______ J;�u=l..,_y�3�1 ,�2�0=2-=-4 ___ _
8.The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is:
Cushman Contracting Corporation
9.The street address of said property is: �S�w�i=ng=z�·n,...g=B�n=·d=g�e ________ _
10.The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo,
State of California, and is described as follows: 2021 Swinging Bridge Retrofit. PW 2021-06
Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California
that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the
said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct.
Bill Robeson, Assistant City Manager/Public Works Director
August 1, 2024, Arroyo Grande, California
--END OF DOCUMENT --