Arroyo Grande Creek Debris and Vegetation Cleanup Update
11/14/2023
1
Project Schedule
Completed between Monday, October 16th and Monday October 30th
City PW and Engineering Staff and contract services
Each location was listed and inspected by FEMA in anticipation of reimbursement
Governor’s Order/ EXECUTIVE ORDER N-10-23
Allowed Emergency Activities - to reduce the risks of local catastrophic flooding
Removal of sediment or vegetation or both serves to either reestablish a functional low-flow channel or reestablish channel capacity, or clear sediment and debris
6/27/2023
2
Project Locations
6/27/2023
Hwy 101
Hwy 101
AGHS
S. Mason St.
The Village
3
Project Locations
6/27/2023
Paulding Middle School
Huasna Rd
4
Fair Oaks/Grieb Bridge – South Side
Before
After
5
Fair Oaks/Grieb Bridge – North Side
Before
After
6
Kiwanis Park
Before
After
7
Tally Ho Creek at Printz Road Bridge
Before
After
8
Behind Saruwatari Farms (Downed Tree)
Before
After
9
8/22/2024
ROW project at 1919 Tally Ho
1st Parklet placement at Andreini’s
Round planters just placed today