CC 2024-09-09_11a Traffic Way Bridge ReplacementItem 11.a.
MEMORANDUM
TO: City Council
FROM: Bill Robeson, Assistant City Manager/Public Works Director
BY: Shannon Sweeney, City Engineer
SUBJECT: Traffic Way Bridge Replacement Project, Traffic Detour Plan, and
Parking Impacts
DATE: September 9, 2024
RECOMMENDATION:
Review and provide input regarding the traffic detour plan and parking impacts associated
with construction of the Traffic Way Bridge Replacement Project.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
$6,911,469 is budgeted in FY 2024-25 and the same amount is budgeted in FY 2025-26
for the Traffic Way Bridge Replacement Project (the “Project”), for a total of $13,822,938
over the next two fiscal years. The Highway Bridge Program (HBP) is funding 88.53%
($12,237,447) of the project, and Measure O-2006 Sales Tax is funding the remaining
11.47% ($1,585,491) of the project. The detour plan is included in the plans and
specifications and will be funded as part of the construction project, scheduled to be
awarded in December 2024.
BACKGROUND:
Traffic Way Bridge was first constructed over Arroyo Grande Creek in 1932. Its piles are
concrete posts originally embedded 23 feet into the ground for support (Figure 1).
Scour, the washing away of soils and creek materials due to creek flow, has resulted in a
loss of embedment or reduction of piling depth. Loss of embedment negatively impacts
the structural integrity of the bridge. In 2006, Caltrans first identified concerns about the
bridge pilings. A 2016 inspection revealed signs of deck cracking, failed expansion joints,
spalling concrete, concrete abrasion, and creek channel erosion.
On July 24, 20181, the City Council approved agreements for the City to seek
reimbursement from the HBP to replace the bridge. This funding covers 88.53% of the
bridge replacement cost, with the balance coming from local funds.
1 https://www.arroyogrande.org/AgendaCenter/ViewFile/Item/7342?fileID=13214
Page 200 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 2
Figure 1: Traffic Way Bridge Piles
On July 28, 20202, the City Council reviewed options for the bridge's full or partial closure
during construction and selected a full closure option as the preferred alternative for the
project. A significant factor in this decision was the construction time frame. A partial
closure would take approximately two years, while full closure is estimated at one year.
Figure 2 is a rendering of the new bridge d esign, which eliminates the potential for scour
and reduces the probability of debris accumulation in the future.
Figure 2: Rendering of the New Bridge Design
2 https://www.arroyogrande.org/AgendaCenter/ViewFile/Item/9992?fileID=16092
Page 201 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 3
Bridge replacement plans and specifications are complete. As the Project continues to
move forward, plans to reroute traffic through the area is increasingly becoming a focal
point due to the Project’s impact on the community.
ANALYSIS OF ISSUES:
A project of this magnitude, the City’s largest capital project in its history, has many items
to consider reducing the overall impact on the community. Accordingly, staff have
conducted early and more recent community and stakeholder outreach to help inform
plans associated with traffic detours and parking impacts . The traffic detour plans and
parking impacts can be realistically evaluated now that the design and construction plans
have been completed and certified. Staff continues to evaluate and incorporate feedback
and will provide further updates and plan confirmations at a subsequent Council meeting,
potentially the meeting on September 24, 2024.
Community Outreach
Community meetings on the Project were held on November 18, 20213, and April 24 and
25, 20244. Press Releases were sent out for these meetings and community members
and local business owners were encouraged to attend to receive updates on the status
of the Project. Each meeting was productive and had about ten members of the
public/business owners in attendance.
A Village Business Group email was sent out on August 30, 2024 that provided a reminder
about the Project, encouraged a conduit for feedback through email, phone calls, and/or
individual meetings between Village businesses and Project staff, included an invitation
to a Project review meeting on September 4, 2024, and contained specific notification of
tonight’s City Council meeting where the Project’s detour and parking impacts will be
considered.
The Project has been a frequent topic at several Village Business Group meetings over
the past year.
Traffic Detour
Traffic Way is an arterial roadway that conveys approximately 11,000 vehicles per day.
Throughout the design process decisions have been made to accomplish the full closure
option previously approved by the City Council. The current construction schedule is April
2025 through December 2025. The main points to the detour plan due to the closure of
the Traffic Way Bridge are:
routing northbound traffic on Traffic Way onto Bridge Street
modifying traffic circulation on Bridge Street to one way
3https://www.arroyogrande.org/DocumentCenter/View/9815/Community-Meeting-Presentation-
111821?bidId=
4 https://www.arroyogrande.org/DocumentCenter/View/12362/Traffic-Way-Bridge-Replacement-Project---
Community-Meeting-20240424r3
Page 202 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 4
installing a temporary traffic signal light at the Bridge Street and East Branch
Street intersection that will allow traffic to turn in both directions (Nevada Street
will be temporarily closed)
parking modification on East Branch Street from Bridge Street heading west
several other safety measures designed to alleviate traffic congestion are
discussed further in this report
Detour maps5 are available on the Traffic Way Bridge Replacement Project6 website. The
planned detour affects several groups as listed below.
Five Cities Fire Authority (FCFA), Arroyo Grande Police Department (AGPD), and San
Luis Ambulance
Fire Station 1 is located on Traffic Way and Station Way, just south of the proposed road
closure. Public Works staff have met with FCFA and AGPD staff and emailed San Luis
Ambulance staff to discuss the detour plan and project schedule. FCFA staff indicated
that they are considering moving certain fire apparatus to the Grover Beach station to
improve their response times during the construction phase of this Project.
Lucia Mar Unified School District (LMUSD)
Student traffic at Paulding Middle School (Paulding) and Arroyo Grande High School
(AGHS) will be impacted by the closure. In addition, LMUSD has notified City staff that
they have a sizeable 16-month construction project to build a new administration building
within the construction fencing shown in Figure 3 at Paulding starting November 2024.
This could add additional construction traffic through the Village. City staff is working with
LMUSD staff to consider diverting construction traffic through the currently barricaded
entrance at Crown Hill Road and Huasna Road.
5 https://www.arroyogrande.org/DocumentCenter/View/12363/Traffic -Way---Traffic-Flow_20240425
6 https://www.arroyogrande.org/753/Traffic-Way-Bridge-Replacement-Project
Page 203 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 5
Figure 3: Preliminary LMUSD Construction Project
The detour plan and project schedule were shared with LMUSD operations staff because
of the potential impact that the detour will have on LMUSD bus routes and City and
LMUSD staff are committed to remaining in regular communication during the respective
projects.
United States Postal Service (USPS)
The detour plan and project schedule were shared with the USPS postmasters in Arroyo
Grande and Pismo Beach to ensure they had adequate time to plan for consistent mail
delivery during the construction period.
Regional Transit Authority (RTA)
Three of the four South County RTA bus routes7 traverse Traffic Way between Branch
Street and Station Way hourly and will be affected by the street closure. The detour plan
and project schedule were shared with RTA operations staff and City staff will continue
to work with RTA staff on alternate bus routes and accommodations.
Village Business Owners
Village businesses will be impacted by the street closures, loss of parking, and increased
traffic congestion resulting from the detour plan. The detour plan and project schedule
were shared with Village business owners, who were encouraged to meet with City staff
to discuss the detour plan and parking impacts. During a meeting on September 4, 2024,
7 https://www.slorta.org/wordpress/wp-content/uploads/SCT-schedule-brochure-March-2024.pdf
Page 204 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 6
City staff and Village business owners had a productive conversation that included the
following topics:
Bridge Street backup caused by high school traffic in the afternoon.
Potential impacts of the stop sign on Mason Street at Le Point.
Removing parking on the south side of Branch Street rather than the north.
Consideration of adding tables in front of Humdinger’s if the parklet is removed.
Bridge Street and Branch Street traffic signal timing to accommodate pedestrian
traffic.
Elevated enforcement.
Adding a “keep clear” area on Bridge Street in front of Olohan Alley.
Adding a “no right turn” sign from the Klondike’s parking lot onto Bridge Street.
Importance of communication.
Recreation Services
Several community events occur in or around the Village. While each event may not
directly use Traffic Way Bridge, Traffic Way does serve as a detour route for several of
the community events. Each of those events is listed below with the evaluation of potential
impact.
Harvest Festival Parade – the road closure map for the Harvest Festival Parade
already includes street shutdown at Traffic Way Bridge. Therefore, the detour
associated with the construction project will not negatively impact this event in
2025.
Halloween – Halloween in the Village does not ordinarily involve street closure at
Traffic Way Bridge. For this event to be considered in 2025, additional costs may
be incurred to accommodate a larger road closure, like that for the Harvest Festival
Parade, or alternate locations may be considered.
Holiday Parade – the Holiday Parade does not ordinarily involve street closure at
Traffic Way Bridge. For this event to be considered in 2025, additional costs may
be incurred to accommodate a larger road closure, similar to that of the Harvest
Festival Parade, or an alternate route can be considered.
Farmer’s Market – while a partial closure of Olohan Alley will exacerbate Village
traffic congestion, no additional conflicts exist to accommodate this event during
construction.
Concerts in the Park – while events at Heritage Park will exacerbate Village traffic
congestion, no additional conflicts exist to accommodate this event during
construction.
Traffic Relief Opportunities
Several options were considered for potentially alleviating traffic congestion during
Project construction. Each of these opportunities is discussed below.
Page 205 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 7
Allow LMUSD construction traffic access through the currently K-rail barricaded
section of Crown Hill Road at East Branch/Huasna/Corbett Canyon intersection.
This modification will reduce construction traffic through the Village and will be
futher reviewed with LMUSD staff. (Figure 4)
Figure 4: Crown Hill Road
Open the fire gate on Miller W ay at Emerald Bay Drive. This alternative was
considered to provide an additional alternate path for some Paulding traffic. After
further discussion, it was determined that this alternate path would not provide
much relief to traffic congestion because it is parallel to James Way. (Figure 5)
Page 206 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 8
Figure 5: Miller Way/Emerald Bay Drive
Open the fire gate on Cerro Vista/W oodland. This alternative was considered as
an additional alternate path for some AGHS traffic. After further discussion, it was
determined that this alternate path would not provide much relief to traffic
congestion and traffic would be better detoured to Halcyon Road. (Figure 6)
Figure 6: Cerro Vista/Woodland
Red curb the north side of Fair Oaks, just east of Halcyon Road. This removes
eight parking spaces adjacent to Arroyo Grande Hospital. This change has already
been discussed with hospital staff, who are amenable, but requested that City staff
defer implementing this change until after they have completed their current
construction project that impacts their parking lot. Removing these parking spaces
can reduce congestion on westbound Fair Oaks Avenue by accommodating two
Page 207 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 9
full lanes of traffic rather than traffic stacking behind parked cars. (Figure 7)
Figure 7: Arroyo Grande Hospital
Adjust egress from AGHS. The City’s former Traffic Commission advised the
prohibition of left turns from the AGHS parking lot in 2004. On January 24, 2012,
the City Council adopted Resolution 4420 establishing a policy to prohibit left turns
onto Fair Oaks Avenue from the AGHS parking lot. City staff is considering
mechanisms for allowing westbound traffic onto Fair Oaks Avenue to alleviate
anticipated congestion through the Village on school day afternoons. One potential
alternative is a temporary traffic circle in the middle entrance/exit of the AGHS
parking lot. Staff continues to evaluate such an option and is not yet certain of its
feasibility. (Figure 8)
Page 208 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 10
Figure 8: Arroyo Grande High School
Parking Impacts
During construction, some parking spaces will need to be temporarily removed to
accommodate traffic lane adjustments. The potential parking space losses include:
Ten parking spaces, a loading zone and an 80-foot parklet in front of Humdinger
Brewing and Rori’s Artisanal Creamery will be removed on East Branch Street,
west of Bridge Street to accommodate two westbound lanes on East Branch Street
west of Bridge Street.
Two parking spaces on the east side of Bridge Street will be converted to a loading
zone (yellow curb) to address the loss of a loading zone on East Branch Street in
the vicinity of Bridge Street.
Three parking spaces on the west side of Bridge Street just south of Branch Street
will be removed.
One parking space on the north side of Branch Street just west of Mason Street
will be removed to accommodate trucks turning left from northbound Mason Street
to westbound East Branch Street.
In total, 16 parking spaces will be impacted. All parking spaces removed during
construction will be restored back to their previous arrangement following construction.
Page 209 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 11
At a recent stake holder meeting, Village business owners requested that staff consider
shifting all travel lanes on East Branch Street just west of Bridge Street to the south to
preserve the parklet in front of Humdinger Restaurant and Rori’s Ice Cream. The north
side of East Branch includes more storefronts, outdoor dining in front of Sidewalk Café,
and a mini plaza adjacent to the clock tower. Focusing parking on the north side rather
than the south side could reduce the number of pedestrians crossing East Branch Street,
creating a safer environment. However, doing so will eliminate an additional four parking
spaces. The design engineer is currently evaluating this option to ensure it is technically
feasible from a lane transition and turning radius perspective.
While any reduction in parking is undesirable, the number of parking spaces reduced for
the Project is less than the 25 parking spaces temporarily removed to accommodate the
Swinging Bridge Retrofit Project in Summer 2024. To help alleviate parking concerns,
clear parking signs informing the public of parking behind businesses north of East
Branch Street are being installed as part of the Wayfinding Project and are scheduled to
be installed before the Project begins in Spring 2025.
Buy Local Campaign
Additional opportunities are being investigated to support the community during the
Project. Staff have been in discussions with the South County Chamber of Commerce to
develop and administer a Buy Local campaign for Village businesses during the Project.
More information regarding timing, duration, scope, and funding will be provided at a
future City Council meeting.
ALTERNATIVES:
The following alternatives are provided for the Council’s consideration:
1. Accept information provided regarding detour planned parking reductions
associated with the Traffic Way Bridge Replacement Project;
2. Provide additional input to City staff for consideration or implementation to reduce
negative impacts associated with detour plans and parking reductions currently
planned for the Traffic Way Bridge Replacement Project; or
3. Provide other direction to staff.
ADVANTAGES:
Traffic Way Bridge is a critical element in City traffic circulation. Failure of this bridge will
result in long-term repercussions that will be much more detrimental to the community
than the short-term impacts associated with traffic detours and temporary parking
reductions needed to accommodate project construction.
DISADVANTAGES:
The traffic detour and parking reduction will negatively impact the community, other
agencies, and local businesses for approximately one year. City staff are evaluating
opportunities to alleviate traffic congestion. City staff have opened dialogue with other
agencies to discuss alternate routes and accommodations. City staff have also held
Page 210 of 211
Item 11.a.
City Council
Traffic Way Bridge Replacement Project, Traffic Detour Plan, and Parking Impacts
September 9, 2024
Page 12
community meetings and reached out to local businesses to communicate impacts during
the construction phase. In addition, the contract documents include signage to indicate to
the public that all businesses will remain open during construction.
NEXT STEPS
Plans and specifications have been reviewed by City staff. The design engineer is
finalizing plans and specifications for a planned bid date of September 18, 2024. Bid
opening date is scheduled for November 7, 2024. Project award is scheduled for
December 10, 2024. The goal is to have a contractor on site to address environmental
issues prior to February 15, 2025. Construction is scheduled for April through December
2025. Meanwhile, the consultant and City staff continue to work with regulatory agencies
to finalize environmental documentation.
ENVIRONMENTAL REVIEW:
On September 26, 2023, the City Council adopted a Mitigated Negative Declaration
(MND) for the Project (SCH No. 2022060452). The MND analyzed the environmental
impacts of the Project in compliance with the California Environmental Quality Act.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with
Government Code Section 54954.2.