CC 2016-06-28_09g Award Contract_Le Point Water Main Upgrade MEMORANDUM TO: CITY COUNCIL FROM: GEOFF ENGLISH, PUBLIC WORKS DIRECTOR BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER SUBJECT: CONSIDERATION OF AN AWARD OF CONTRACT TO SPECIALTY CONSTRUCTION INC. FOR CONSTRUCTION OF THE LE POINT AREA WATER MAIN UPGRADE PROJECT, PW 2015-15 DATE: JUNE 28, 2016 RECOMMENDATION: It is recommended the City Council: 1. Award a contract for the Le Point Area Water Main Upgrade Project to Specialty Construction Inc. in the amount of $486,892; 2. Authorize the City Manager to approve change orders for 15% of the contract amount, $73,034 for unanticipated costs during the construction phase of the project (total construction costs = $486,892 + $73,034 = $559,926); and 3. Direct the City Clerk to file a Notice of Exemption. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: The FY 2015/16 and FY 2016/17 Capital Improvement Program Budget includes $684,100 for the subject project. The engineer’s estimate for the project was $490,000. The total cost of the project including design, construction inspection and contingencies is estimated at $684,100. BACKGROUND: As presented in the City’s Water Master Plan as priority B-7, the project is to install approximately 2,300 linear feet of 8-inch diameter PVC potable water mains in the Le Point area, replace water services and appurtenances, install additional fire hydrants, and abandon the existing cast iron 4-inch water mains that were installed in 1938. The City has experienced numerous breaks in these cast iron mains, and an analysis showed that the cast iron pipe is in poor condition. Cast iron pipe is estimated to have a useful life of 50 to 100 years. The recent main breaks signal that the cast iron pipe in the Le Point area has reached the end of its useful life. Item 9.g. - Page 1 CONSIDERATION OF AN AWARD OF CONTRACT TO SPECIALTY CONSTRUCTION INC. FOR CONSTRUCTION OF THE LE POINT AREA WATER MAIN UPGRADE PROJECT, PW 2015-15 JUNE 28, 2016 PAGE 2 The waterlines to be replaced are within the public right of way on (1) Crown Terrace from Crown Hill Street to Le Point Street, (2) Le Point Street from Crown Terrace to Highway 227/Corbett Canyon Road, and (3) McKinley Street from Le Point Street to Crown Hill Street. Staff conducted a non-mandatory pre-bid meeting to ensure that all prospective bidders were informed of potential impacts to Paulding Middle School. The project has been designed to allow for phased construction beginning with the pipelines on McKinley Street, and Le Point Street between McKinley Street and Highway 227/Corbett Canyon to avoid potential traffic and pedestrian conflicts. Should construction not be completed on those streets by August 16, 2016, work hours on these streets will be restricted from 10:00 am to 2:00 pm Mondays, and from 9:00 am to 2:00 pm Tuesday through Friday. ANALYSIS OF ISSUES: On June 14, 2016, seven bids were opened for the Le Point Area Water Main Upgrade project. The lowest bid, $486,892 from Specialty Construction, Inc., was deemed responsive and staff recommends award of a construction contract to Specialty Construction, Inc. accordingly. The contract time is 80 working days. Work is expected to begin in July and be completed in November. ALTERNATIVES: The following alternatives are provided for the Council’s consideration: 1. Approve staff’s recommendation to award a construction contract to Specialty Construction, Inc. for the Le Point Area Water Main Upgrade project; 2. Do not award a construction contract for the project; or 3. Provide direction to staff. ADVANTAGES: Replacement of the water mains and installation of additional fire hydrants will ensure safe and reliable delivery of drinking water and provide enhanced fire protection to the surrounding properties. DISADVANTAGES: There may be some impact to traffic and pedestrians accessing Paulding Middle School. However, phased construction and/or limited work hours should help avoid potential impacts. ENVIRONMENTAL REVIEW: The project is categorically exempt from CEQA pursuant to Section 15301(b). Item 9.g. - Page 2 CONSIDERATION OF AN AWARD OF CONTRACT TO SPECIALTY CONSTRUCTION INC. FOR CONSTRUCTION OF THE LE POINT AREA WATER MAIN UPGRADE PROJECT, PW 2015-15 JUNE 28, 2016 PAGE 3 PUBLIC NOTIFICATION AND COMMENTS: The agenda was posted at City Hall on Thursday, June 23, 2016. The agenda and staff report were posted on the City’s website on Friday, June 24, 2016. No public comments were received as of the time of preparation of this report. Attachment: 1. Bid Opening Log Sheet 2. Notice of Exemption Item 9.g. - Page 3 Attachhment Noo. 1 Item 9.g. - Page 4 Attachment No. 2 Notice of Exemption To: Office of Planning Research From: (Public Agency) City of Arroyo Grande 1440 Tenth Street, Room 121 300 East Branch Street Sacramento, CA 95814 Arroyo Grande, CA 93420  County Clerk County of San Luis Obispo County Government Center San Luis Obispo, CA 93408 Project Title: Le Point Area Water Main Upgrade Project, PW 2015-15 Project Location - Specific: Le Point Street, Crown Terrace, and McKinley Street Project Location - City: Arroyo Grande Project Location - County: San Luis Obispo Description of Project: Installation of approximately 2,300-lf of potable water mains and service laterals, and installation of additional fire hydrants Name of Public Agency Approving Project: City of Arroyo Grande – Public Works Department Name of Person or Agency Carrying Out Project: Geoff English, Director of Public Works Exempt Status: (check one)  Ministerial (Section 12080(b)(1); 15268);  Declared Emergency (Sec. 21080(b)(3); 15269(a));  Emergency Project (Sec. 21080(b)(4); 15269(b)(c));  Categorical Exemption. State type and section number: Section 15301(b)  Statutory Exemptions. State code number: Reason Why Project is Exempt: Negligible expansion of an existing publicly owned utility facility Lead Agency Contract Person: Jill McPeek, CIP Manager Area Code/Telephone/Extension: (805) 473-5444 E-mail: jmcpeek@arroyogrande.org If filed by Applicant: 1. Attach a certified document of exemption finding. 2. Has a Notice of Exemption been filed by the public agency approving the project?  Yes  No Signature: Date: Teresa McClish Director of Community Development  Signed by Lead Agency  Date received for filing at OPR:  Signed by Applicant Item 9.g. - Page 5 THIS PAGE INTENTIONALLY LEFT BLANK Item 9.g. - Page 6