CC 2019-08-13_08f Acceptance of Huasna-Oro CMP and Woodland Sewer Lining ProjectMEMORANDUM TO: CITY COUNCIL FROM: BILL ROBESON, PUBLIC WORKS DIRECTOR BY: JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER SUBJECT: CONSIDERATION OF ACCEPTANCE OF THE HUASNA ROAD/ORO DRIVE CORRUGATED METAL PIPE (CMP) AND WOODLAND DRIVE SEWER LINING PROJECT, PW 2018-01 DATE: AUGUST 13, 2019 SUMMARY OF ACTION: Acceptance of the Huasna Road/Oro Drive Corrugated Metal Pipe (CMP) and Woodland Drive Sewer Lining project and beginning of the one-year warranty period for any defects that may arise. IMPACT ON FINANCIAL AND PERSONNEL RESOURCES: An allocation of $251,300 of Local Sales Tax funds was included in the Capital Improvement Program (CIP) budget for lining existing storm drain pipes, and $55,000 of Sewer funds was included for lining an existing sewer main pipe. It is estimated that a total of $273,000 will be expended for design, construction, administration, and inspection. The recommended action will not impact staff resources. RECOMMENDATION: It is recommended the City Council: 1. Accept the project improvements as constructed by Sancon Technologies, Inc. in accordance with the plans and specifications for the Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining Project, PW 2018-01; 2. Direct staff to file a Notice of Completion; and 3. Authorize release of retention, thirty-five (35) days after the Notice of Completion has been recorded, if no liens have been filed. BACKGROUND: On April 23, 2019, the Council awarded a construction contract to perform the Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining project to Sancon Technologies, Inc. in the amount of $242,061 and authorized the City Manager to approve change orders in the amount of $24,206. The contractor’s final construction cost for this project is $245,986.20. Item 8.f. - Page 1 CITY COUNCIL CONSIDERATION OF ACCEPTANCE OF THE HUASNA ROAD/ORO DRIVE CORRUGATED METAL PIPE (CMP) AND WOODLAND DRIVE SEWER LINING PROJECT, PW 2018-01 AUGUST 13, 2019 PAGE 2 The project consists of the rehabilitation of approximately 900 feet of storm drain pipe along Oro Drive and Huasna Road, and the rehabilitation of approximately 543 linear feet of sewer pipe that runs beneath the backyards of homes along Woodland Drive between Fair Oaks Avenue and Olive Street. ANALYSIS OF ISSUES: The contractor has completed the work in accordance with the approved plans and specifications on schedule and under the available budget. There are no outstanding issues. ALTERNATIVES: The following alternatives are provided for the Council’s consideration: 1. Accept the Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining project; 2. Do not accept the project; 3. Accept the project but do not authorize release of retention; or 4. Provide direction to staff. ADVANTAGES: The project is complete and accepting the improvements will allow staff to close out the project. Rehabilitation and ongoing maintenance of storm drain and sewer mains is essential to maintaining a properly functioning system. The project is consistent with the City Council goal to support City infrastructure. DISADVANTAGES: No disadvantages have been identified. ENVIRONMENTAL REVIEW: No environmental review is needed to accept the project. PUBLIC NOTIFICATION AND COMMENTS: The Agenda was posted at City Hall and on the City’s website in accordance with Government Code Section 54954.2. Attachment: 1. Notice of Completion Item 8.f. - Page 2 RECORDING REQUESTED BY AND WHEN RECORDED RETURN TO: CITY CLERK CITY OF ARROYO GRANDE 300 EAST BRANCH STREET ARROYO GRANDE, CA 93420 NOTICE OF COMPLETION NOTICE IS HEREBY GIVEN THAT: 1.The undersigned is owner or agent of owner of the interest or estate or the property hereinafter described as stated below. 2.The FULL NAME of the OWNER is: The City of Arroyo Grande 3.The FULL ADDRESS of the OWNER is: 300 East Branch Street, Arroyo Grande, California 93420 4.The NATURE OF THE INTEREST or ESTATE of the undersigned is: in fee 5.THE FULL NAME and FULL ADDRESS of ALL PERSONS, if any, who hold such interest or estate with the undersigned as JOINT TENANTS or as TENANTS IN COMMON are: NAMES ADDRESSES None 6.THE FULL NAMES and FULL ADDRESSES of the PREDECESSOR’S in interest of the undersigned if the property was transferred subsequent to the commencement of the work of improvements herein referred to: NAMES ADDRESSES None 7.All work of improvement on the property hereinafter described was COMPLETED July 31, 2019 8.The NAME OF THE ORIGINAL CONTRACTOR, if any, for such work of improvement is: Sancon Technologies, Inc. 9.The street address of said property is: Oro Drive, Huasna Road, and Woodland Drive in the City of Arroyo Grande, CA 10.The property on which said work of improvement was completed is in the City of Arroyo Grande, County of San Luis Obispo, State of California, and is described as follows: Huasna Road/Oro Drive CMP and Woodland Drive Sewer Lining Project, PW 2018-01 Verification of NON-INDIVIDUAL owner: I, the undersigned, declare under penalty of perjury under the laws of the State of California that I am the Public Works Director of the aforesaid interest or estate in the property described in the above notice; that I have read the said notice, that I know and understand the contents thereof, and the facts stated therein are true and correct. _________________________________________________ Bill Robeson, Public Works Director August 13, 2019, Arroyo Grande, California -- END OF DOCUMENT -- ATTACHMENT 1 Item 8.f. - Page 3 THIS PAGE INTENTIONALLY LEFT BLANK Item 8.f. - Page 4